To determine
For a signal phase determine the yellow interval by the given conditions.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis
and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical
intersection v/c of 0.90 is desired.
O 15.552 sec
O 11.462 sec
O 14.825 sec
Phase
O 16.065 sec
Allowed movements
Analysis flow rate
Saturation flow rate
Using v/c equalization ratio, calculate the effective green time for phase 3
1
NB L, SB L
330, 365 veh/h
1700, 1750 veh/h
2
NB T/R, SB T/R
1125, 1075 veh/h
3400, 3300 veh/h
EB L, WB L
110, 80 veh/h
650, 600 veh/h
3
EB T/R, WB T/R
250, 285 veh/h
1750, 1800 veh/h
If there is no pedestrian traffic, the yellow interval needed by northbound vehicles to clear the intersection travelling at a speed of 35 mph is:
Question 16 options:
4.6 sec
5.0 sec
4.75 sec
none of the above
An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis
and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical
intersection v/c of 0.90 is desired.
O 12.105 sec
O 15.954 sec
O 13.190 sec
Phase
O 14.127 sec
Allowed movements
Analysis flow rate
Saturation flow rate
1
NB L, SB L
330, 365 veh/h
1700, 1750 veh/h
Using v/c equalization ratio, calculate the effective green time for phase 1
2
NB T/R, SB T/R
1125, 1075 veh/h
3400, 3300 veh/h
EBL, WBL
110, 80 veh/h
650, 600 veh/h
3
EB T/R, WB T/R
250, 285 veh/h
1750, 1800 veh/h
Chapter 8 Solutions
MindTap Engineering for Garber/Hoel's Traffic and Highway Engineering, 5th Edition, [Instant Access], 1 term (6 months)
Ch. 8 - Prob. 1PCh. 8 - Prob. 2PCh. 8 - Prob. 3PCh. 8 - Prob. 4PCh. 8 - Prob. 5PCh. 8 - Prob. 6PCh. 8 - Prob. 7PCh. 8 - Prob. 8PCh. 8 - Prob. 9PCh. 8 - Prob. 10P
Ch. 8 - Prob. 11PCh. 8 - Prob. 12PCh. 8 - Prob. 13PCh. 8 - Prob. 14PCh. 8 - Prob. 15PCh. 8 - Prob. 16PCh. 8 - Prob. 17PCh. 8 - Prob. 18PCh. 8 - Prob. 19PCh. 8 - Prob. 20PCh. 8 - Prob. 21PCh. 8 - Prob. 22PCh. 8 - Prob. 23PCh. 8 - Prob. 24PCh. 8 - Prob. 25PCh. 8 - Prob. 26PCh. 8 - Prob. 27PCh. 8 - Prob. 28P
Knowledge Booster
Similar questions
- An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. O 20.464 sec O 22.411 sec O 24.460 sec Phase O 21.035 sec Allowed movements Analysis flow rate Saturation flow rate Using v/c equalization ratio, calculate the effective green time for phase 2 NB L, SB L 330, 365 veh/h 1700, 1750 veh/h 2 NB T/R, SB T/R 1125, 1075 veh/h 3400, 3300 veh/h EB L, WBL 110, 80 veh/h 650, 600 veh/h 3 EB T/R, WB T/R 250, 285 veh/h 1750, 1800 veh/harrow_forwardAn intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. Phase Allowed movements NB L, SB L NB T/R, SB T/R EB L, WB L EB T/R, WB T/R Analysis flow rate 330, 365 veh/h 1125, 1075 veh/h 110, 80 veh/h 250, 285 veh/h Saturation flow rate 1700, 1750 veh/h 3400, 3300 veh/h 650, 600 veh/h 1750, 1800 veh/h Calculate the sum of the flow ratios for the critical lane groups. O 0.709 O 0.857 O 0.787 O 0.829arrow_forwardDetermine whether a T intersection (one leg on the minor approach) with the hourly volume data satisfy MUTCD Warrant 3 (peak-hr vehicular volume) for signalization. All approaches have one lane entering the intersection. For the warrant that is met, explain how the warrant is met (rules applied, hours in which the volume criteria were met, etc.) and refer to necessary graphs and tables. The major street speed limit is 60 km/h, and the minor street speed limit is 40 km/h.arrow_forward
- An intersection has a three-phase signal with the movement allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired Phase 1 2 3 Allowed Movement NB L, SB L NB T/R, SB T/R EB L, WB L EB /T/R, WB T/R Analysis Flow Rate 330, 365 veh/h 1125, 1075 veh/h 110, 80 veh/h 250, 285 veh/h Saturation Flow Rate 1700, 1750 veh/h 3400, 300 veh/h 650, 600 veh/h 1750, 1800 veh/h Calculate the Following: 1.)Sum of flow ratios for critical lane groups 2.)minimum cycle length 3.)using v/c equation ratio, calculate the effective green time for phase 1 4.)using v/c equation ratio, calculate the effective green time for phase 2 5.)using v/c equation ratio, calculate the effective green time for phase 3arrow_forwardA traffic signal control is being designed for a four-leg intersection on a divided highway with the characteristics shown in the table below. Assuming the average vehicle length L is 6m, Determine an appropriate length of the yellow interval for each approach and how you will provide it. Use the AASHTO recommended deceleration rate and perception-reaction time. N-S Approaches E-W Approaches Median width, (m) 6. 3 No. of 3.5 lanes 3 on each approach Design speed, km/h 60 Grade -3.5 2. 80arrow_forwardAn intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. Phase 3 Allowed movements NB L, SB L NB T/R, SB T/R EB L, WB L EB TR, WB TR Analysis flow rate 330, 365 veh/h 1125, 1075 veh/h 110, 80 veh/h 250, 285 veh/h Saturation flow rate 1700, 1750 veh/h 3400, 3300 vehh 650, 600 veh/h 1750, 1 800 veh/h Using v/c equalization ratio, calculate the effective green time for phase 3 14.825 sec 15.552 sec O 11.462 sec O 16.065 secarrow_forward
- An intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. Phase 3 Allowed movements NB L, SB L NB T/R, SB T/R EB L, WB L ЕВ TR, WB TR Analy sis flow rate 330, 365 veh/h 1125, 1075 veh/h 110, 80 veb/h 250, 285 veh/h Saturation flow rate 1700, 1750 veh/h 3400, 3300 veh/h 650, 600 veh/h 1750, 1800 veh/h Calculate the sum of the flow ratios for the critical lane groups. 0.787 O 0.857 O 0.709 O 0,829arrow_forwardAn intersection has a three-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Assume the lost time is 4 seconds per phase and a critical intersection v/c of 0.90 is desired. Phase 2 3 Allowed movements NB L, SB L NB T/R, SB T/R EB L, WBL EB T/R, WB T/R Analysis flow rate 330, 365 veh/h 1125, 1075 veh/h 110, 80 veh/h 250, 285 veh/h Saturation flow rate 1700, 1750 veh/h 3400, 3300 veh/h 650, 600 veh/h 1750, 1800 veh/h Calculate minimum cycle length O 255 sec O 155 sec O 100 sec O 60 secarrow_forwardProblem 18-10 in Roess, Prassas, McShane, 5 th ed.An intersection approach has a demand volume of 500 veh/h, a saturation flow rate of 1,450veh/hg, a cycle length of 80 s, and 50 s of effective green time. What average delay per vehicle isexpected under these conditions?arrow_forward
- An intersection has a four-phase signal with the movements allowed in each phase and corresponding analysis and saturation flow rates shown in the table below. Phase 1 3 4 Allowed movements EB L, WB L EB T/R, WB T/R SB L, SB T/R NB L, NB T/R Analysis flow rate 245, 230 veh/h 975, 1030 veh/h 255, 235 veh/h 225, 215 veh/h Saturation flow rate 1750, 1725 vehh 3350, 3400 veh/h 1725, 1750 veh/h 1700, 1750 veh/h Calculate the optimum cycle length (Assume 4 seconds lost time per phase) O 116.466 sec O 104.693 sec 97.315 sec O 101.399 secarrow_forwardAn intersection has a three-phase signal shown in the graph below. if he intersection deceleration rate for vehicles is 3.05 m/sec, length of vehicle is 6.0 m, the driver perception/reaction time is 1.0 seconds, and the Speed Limits are 75 km/hr for N-S approach & 55 km/hr for E-W approach; Calculate the All Red (AR) time for E-W approach (to the nearest 0.5 second) 183 m 16.8 m Select one O 1.5 seconds O 2.0 seconds O 1.0 seconds O3.0 seconds 2.5 secondsarrow_forwardQ4: a. At a certain at grade intersection, it's decided to use a 4 phases traffic signal for the four approaches shown below. South Approach Width (m) Actual flow (DHV) pe/hr North East West 7 8 12 10.5 331 427 1104 715 Left turn vehicles of 478 630 1953 1047 saturation flow Assuming the following for each phase: Starting delay and falling discharge time = 3 sec, amber time = 5 sec, all red = 1 sec, red/amber I sec. Find the optimum cycle time and the controller green for each phase.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning