Concept explainers
a
Interpretation: Tasks for each workstation, total time and idle time are to be calculated.
Concept Introduction:
Longest task time first rule:In this rule of line balancing, the task which has highest cycle time is assigned first to the workstation.
a
Explanation of Solution
Cycle Time:
It is the time between two consecutive outputs come out from a process.
Here CT = Cycle time; A = Available time to produce output; R = Demand
Assembly line:
It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:
Here t = Task time; N= Actual no. of workstations; CT = cycle time
Idle time:
It is time for which machines or employees do not work due to the stoppage or work for any causes.
Here N= Actual no. of work stations; CT= cycle time; t = task time
Assembly time per shift (A) = 480 min
No. of shifts each day = 1
Output forecasted per shift(R) = 60 units
The theoretical minimum no. of the workstation can be obtained as follows:
Here CT= Cycle time; t= Sum of tasks time;
Theoretically, minimum no. of the workstation is:
Line balancing by longest task time first rule can be calculated as follows:
Lines balanced by the assignable task are determined by longest task time first rule. It has following steps:
Task 2 has highest processing time and no prerequisite is required therefore it is assigned on station A.
Although task 1 has highest processing time after task 2 in that case, total time exceeds the cycle time, therefore, task 4 and 3 is assigned on station A along with task 2 as no prerequisite is required for these tasks.
Task 1 is assigned to station B and there is a tie between task 6 and 7 as both task time is same.
Task5 is assigned to station C as its preceding task 1, 2, 3 has already assigned.
Either task 6 or 7 is assigned to station D.
Finally, task 8 is assigned to station E.
In actual situation no. of workstation are 5 in order to follow precedence and cycle time rule.
Station | Tasks | Total Time(min) | Idle Time(min) |
A | 2,4,3 | 8 | 0 |
B | 1,6 (or 7 tie) | 7 | 1 |
C | 5 | 6 | 2 |
D | 7 (or 6) | 3 | 5 |
E | 8 | 8 | 0 |
Total | 32 | 8 |
Total time at station A= Task Time of task 2+ Task Time of task 3+ Task Time of task 4
Total time at station A = 5+1+2
= 8 min
Idle time at station A= Cycle time-Total tasks at station A
= 8-8
= 0 min
Total time at station B = Task Time of task 1+ Task Time of task (6 or 7)
Total time at station B = 4+3
=7 min
Idle time at station B= Cycle time-Total tasks time at station B
=8-7
=1 min
Total time at station C = 6 min
Idle time at station C= Cycle time-Total tasks time at station c
= 8-6
= 2 min
Total time at station D= Task time of task 7 or 6
Total time at station D= 3 min
Idle time at station D= Cycle time-Total tasks time at station D
= 8-3
= 5 min
Total time at station E= Task Time of task D
Total time at station E= 8 min
Idle time at station E= Cycle time- Total tasks time at Station E
= 8-8
= 0 min
Total time
Total idle time:
It can be calculated as follows:
b
Interpretation:Assembly line efficiency is to be determined.
Concept Introduction:
Assembly line:It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:
Here t = Task time; N= Actual no. of workstations; CT = cycle time
b
Explanation of Solution
Assembly line efficiency can be calculated as follows:
c
Interpretation:Whether assembly line balance solution is good or bad and a criterion for assessment is to be explained.
Concept Introduction:
Idle time:It is time for which machines or employees do not work due to the stoppage or work for any causes.
c
Explanation of Solution
The assembly line balancing goodness is assessing its assembly line efficiency and idle time. In present case, although the assembly line efficiency is 80% the idle time is 8 min which is very high. It is highest for station D i.e. 5 min and at station B and C has 1 and 2 min idle time respectively. Therefore a fair chance that station B and C becomes bottleneck station for the assembly line. So it is not the very good balancing solution.
Want to see more full solutions like this?
- Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Find the answers in the…arrow_forwardCanine Kernels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see Figure). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product’s price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone, and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Which of the three workstations, W, X, or Y, has the…arrow_forwardCanine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to working on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day or 40 hours/week. Which of the three workstations, W, X, or…arrow_forward
- Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $10 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Product A $4 Raw materials Product B $7 Raw…arrow_forwardA small assembly line for the assembly of power steering pumps needs to be balanced. Precedence diagram is shown below. The cycle time is determined to be 1.7 minutes. How would the line be balanced by choosing the assignable task having the longest task time first? Fill in the table below. If your answer is zero, enter "0". Round your answers to one decimal place. Station Tasks Total Time Idle Time 1 B,A,C,D 2 E,F 3 G,H,I Total What is the assembly-line efficiency? Round your answer to one decimal place. %arrow_forwardThe table below shows the time for each work element in an manual assembly process, along with the predecessor(s) required for each element. The ideal cycle time is 1.4 minutes, the repositioning time is 0.1 minutes, and there is one worker at each station. Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3 0.2 Immediate predecessors - A A B B C E,F D,E G,H I 1. Using the ranked positional weights method, assign work elements to stations.arrow_forward
- Management wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: A) Determine the maximum and minimum cycle times.B) Determine the optimum cycle time.C) What is the minimum number of stations needed?D) Draw the precedence diagram.E) Assign tasks to stations in order of most following tasks first. Submit an Excel file based on Chapter 6 Excel Template to indicate your computation.arrow_forwardA small assembly line for the assembly of power steering pumps needs to be balanced. Precedence diagram is shown below. The cycle time is determined to be 2.1 minutes. How would the line be balanced by choosing the assignable task having the longest task time first? Fill in the table below. If your answer is zero, enter "0". Round your answers to one decimal place. Station Tasks Total Time Idle Time 1 B,A,C,D 2 E,F 3 G,H,I Total What is the assembly-line efficiency? Round your answer to one decimal place. %arrow_forwardK Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to work on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day, or 40 hours/week. Product A $2 Step 1 Station W (11 min) Raw…arrow_forward
- Francis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forwardA production schedule requires six work stations. However, there are nine work tasks to be performed to produce a unit of output. The warchouse is operated for seven days a week and three 8-hour shifts per day. The desired output per week is 1.728 units. The tasks, precedence relationships and the approximate amount of time required to carry out cach task is presented below. Use this information to answer questions 62 - 69 Task 1. Duration (min) 5.0 Immediate Preceding Task 3 4 4.5 2.0 3.0 3.5 2,3 4,5 1.5 2.5 7. 4.8 2.5 62. What is the available time for production in minutes? (a) 1260 (b) 1440 (c) 3,360 (d) 10080 63. The required cycle time for this operation is: (а) 2.58 (b) 5.83 (c) 7.25 (d) 9.42 64. Which activity or set of activities should be assigned to station 2? (a) 2 only (b) I and 2 (c) 3 only (d) 3 and 4 65. Which activity or set of activities should be assigned to station 4? (a) 3 only (b) 3 and 4 (c) 5 and 6 (d) 7 only 66. Which activity or set of activities should be…arrow_forwarddefine the workflow design concept. Additionally, it discusses how an optimal design of a production system influences employee efficiency, waste reduction, and bottleneck avoidance. Explain each of the following production processes:Project or tasklotsProduction linesContinuous flow or process and mass productionarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,