EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 8, Problem 12PA

a

Summary Introduction

Interpretation: Tasks for each workstation, total time and idle time are to be calculated.

Concept Introduction:

Longest task time first rule:In this rule of line balancing, the task which has highest cycle time is assigned first to the workstation.

a

Expert Solution
Check Mark

Explanation of Solution

Cycle Time:

It is the time between two consecutive outputs come out from a process.

  CT=AR

Here CT = Cycle time; A = Available time to produce output; R = Demand Forecast

Assembly line:

It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:

  Assembly line efficiency=tN×CT

Here t = Task time; N= Actual no. of workstations; CT = cycle time

Idle time:

It is time for which machines or employees do not work due to the stoppage or work for any causes.

  Nt=tCT

Here N= Actual no. of work stations; CT= cycle time; t = task time

Assembly time per shift (A) = 480 min

No. of shifts each day = 1

Output forecasted per shift(R) = 60 units

  CT=AR

  =480/60

  =8min

The theoretical minimum no. of the workstation can be obtained as follows:

  Nt=tCT

Here CT= Cycle time; t= Sum of tasks time; N1 = Minimum no. of work station required

  t=Tasktime1+Tasktime2+TaskTime3+Tasktime4

  +Tasktime5+Tasktime6+Tasktime7+Tasktime8

  =4+5+1+2+6+3+3+8

  =32min

Theoretically, minimum no. of the workstation is:

  Nt=328

  =4workstation

Line balancing by longest task time first rule can be calculated as follows:

Lines balanced by the assignable task are determined by longest task time first rule. It has following steps:

Task 2 has highest processing time and no prerequisite is required therefore it is assigned on station A.

Although task 1 has highest processing time after task 2 in that case, total time exceeds the cycle time, therefore, task 4 and 3 is assigned on station A along with task 2 as no prerequisite is required for these tasks.

Task 1 is assigned to station B and there is a tie between task 6 and 7 as both task time is same.

Task5 is assigned to station C as its preceding task 1, 2, 3 has already assigned.

Either task 6 or 7 is assigned to station D.

Finally, task 8 is assigned to station E.

In actual situation no. of workstation are 5 in order to follow precedence and cycle time rule.

    Station TasksTotal Time(min)Idle Time(min)
    A 2,4,3 8 0
    B 1,6 (or 7 tie) 7 1
    C 5 6 2
    D 7 (or 6) 3 5
    E 8 8 0
    Total 32 8

Total time at station A= Task Time of task 2+ Task Time of task 3+ Task Time of task 4

Total time at station A = 5+1+2

  = 8 min

Idle time at station A= Cycle time-Total tasks at station A

  = 8-8

  = 0 min

Total time at station B = Task Time of task 1+ Task Time of task (6 or 7)

Total time at station B = 4+3

  =7 min

Idle time at station B= Cycle time-Total tasks time at station B

  =8-7

  =1 min

Total time at station C = 6 min

Idle time at station C= Cycle time-Total tasks time at station c

  = 8-6

  = 2 min

Total time at station D= Task time of task 7 or 6

Total time at station D= 3 min

Idle time at station D= Cycle time-Total tasks time at station D

  = 8-3

  = 5 min

Total time at station E= Task Time of task D

Total time at station E= 8 min

Idle time at station E= Cycle time- Total tasks time at Station E

  = 8-8

  = 0 min

Total time (t)=TotaltimeatstationA+Totaltimeatstation B+

  Totaltimeatstation C+Totaltimeatstation D+

  Totaltimeatstation E

  Totaltime=8+7+6+3+8

  =32min

Total idle time:

It can be calculated as follows:

  Totalidletime=(N)×(CT)-t

  HereN=5;CT=8min;t=32min

  =5×832

  =4032

  =8min

b

Summary Introduction

Interpretation:Assembly line efficiency is to be determined.

Concept Introduction:

Assembly line:It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:

  Assembly line efficiency=tN×CT

Here t = Task time; N= Actual no. of workstations; CT = cycle time

b

Expert Solution
Check Mark

Explanation of Solution

Assembly line efficiency can be calculated as follows:

  Assembly line efficiency=tN×CT

  Heret=32min;N=5;CT=32min

  Assemblylineefficiency=32(5×8)

  =32/40

  =.8

  =80.00%

c

Summary Introduction

Interpretation:Whether assembly line balance solution is good or bad and a criterion for assessment is to be explained.

Concept Introduction:

Idle time:It is time for which machines or employees do not work due to the stoppage or work for any causes.

c

Expert Solution
Check Mark

Explanation of Solution

The assembly line balancing goodness is assessing its assembly line efficiency and idle time. In present case, although the assembly line efficiency is 80% the idle time is 8 min which is very high. It is highest for station D i.e. 5 min and at station B and C has 1 and 2 min idle time respectively. Therefore a fair chance that station B and C becomes bottleneck station for the assembly line. So it is not the very good balancing solution.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
An assembly line is to operate eight hours per day with a desired output of 200 units per day. The following table contains information on this product’s task times and precedence relationships:  TASK TASK TIME(SECONDS) IMMEDIATEPREDECESSOR A 60 — B 60 A C 50 A D 70 A E 30 B, C F 110 C, D G 70 E, F H 70 G   b. What is the required workstation cycle time to meet the desired output rate? (Round your answer to the nearest whole number.)     c. Balance this line using the longest task time. (Leave no cells blank - be certain to enter "0" wherever required.)   d. What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b? (Round your answer to 1 decimal place.)
The following is a list of activities that must be completed in order to assemble a car. Draw the precedence diagram. Calculate the cycle time if there5 are 8 hours in a workday and 800 units desired per day. Balance the line using the longest operation time as a selection rule. Calculate the efficiency rating. How much overtime would be needed for an additional 20 units? Is this possible?                                                                                                                                                 Task       Time                      Feasible                                 TASK TIME       PRECEDING                      Station   Task       Time      Remaining           Tasks TASK                    (Seconds)             TASK                    A                             16                           ----- B                             14                           ----- C                             22                           ----- D…
please answer quick in details within 30 mins.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY