EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 8, Problem 12PA

a

Summary Introduction

Interpretation: Tasks for each workstation, total time and idle time are to be calculated.

Concept Introduction:

Longest task time first rule:In this rule of line balancing, the task which has highest cycle time is assigned first to the workstation.

a

Expert Solution
Check Mark

Explanation of Solution

Cycle Time:

It is the time between two consecutive outputs come out from a process.

  CT=AR

Here CT = Cycle time; A = Available time to produce output; R = Demand Forecast

Assembly line:

It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:

  Assembly line efficiency=tN×CT

Here t = Task time; N= Actual no. of workstations; CT = cycle time

Idle time:

It is time for which machines or employees do not work due to the stoppage or work for any causes.

  Nt=tCT

Here N= Actual no. of work stations; CT= cycle time; t = task time

Assembly time per shift (A) = 480 min

No. of shifts each day = 1

Output forecasted per shift(R) = 60 units

  CT=AR

  =480/60

  =8min

The theoretical minimum no. of the workstation can be obtained as follows:

  Nt=tCT

Here CT= Cycle time; t= Sum of tasks time; N1 = Minimum no. of work station required

  t=Tasktime1+Tasktime2+TaskTime3+Tasktime4

  +Tasktime5+Tasktime6+Tasktime7+Tasktime8

  =4+5+1+2+6+3+3+8

  =32min

Theoretically, minimum no. of the workstation is:

  Nt=328

  =4workstation

Line balancing by longest task time first rule can be calculated as follows:

Lines balanced by the assignable task are determined by longest task time first rule. It has following steps:

Task 2 has highest processing time and no prerequisite is required therefore it is assigned on station A.

Although task 1 has highest processing time after task 2 in that case, total time exceeds the cycle time, therefore, task 4 and 3 is assigned on station A along with task 2 as no prerequisite is required for these tasks.

Task 1 is assigned to station B and there is a tie between task 6 and 7 as both task time is same.

Task5 is assigned to station C as its preceding task 1, 2, 3 has already assigned.

Either task 6 or 7 is assigned to station D.

Finally, task 8 is assigned to station E.

In actual situation no. of workstation are 5 in order to follow precedence and cycle time rule.

    Station TasksTotal Time(min)Idle Time(min)
    A 2,4,3 8 0
    B 1,6 (or 7 tie) 7 1
    C 5 6 2
    D 7 (or 6) 3 5
    E 8 8 0
    Total 32 8

Total time at station A= Task Time of task 2+ Task Time of task 3+ Task Time of task 4

Total time at station A = 5+1+2

  = 8 min

Idle time at station A= Cycle time-Total tasks at station A

  = 8-8

  = 0 min

Total time at station B = Task Time of task 1+ Task Time of task (6 or 7)

Total time at station B = 4+3

  =7 min

Idle time at station B= Cycle time-Total tasks time at station B

  =8-7

  =1 min

Total time at station C = 6 min

Idle time at station C= Cycle time-Total tasks time at station c

  = 8-6

  = 2 min

Total time at station D= Task time of task 7 or 6

Total time at station D= 3 min

Idle time at station D= Cycle time-Total tasks time at station D

  = 8-3

  = 5 min

Total time at station E= Task Time of task D

Total time at station E= 8 min

Idle time at station E= Cycle time- Total tasks time at Station E

  = 8-8

  = 0 min

Total time (t)=TotaltimeatstationA+Totaltimeatstation B+

  Totaltimeatstation C+Totaltimeatstation D+

  Totaltimeatstation E

  Totaltime=8+7+6+3+8

  =32min

Total idle time:

It can be calculated as follows:

  Totalidletime=(N)×(CT)-t

  HereN=5;CT=8min;t=32min

  =5×832

  =4032

  =8min

b

Summary Introduction

Interpretation:Assembly line efficiency is to be determined.

Concept Introduction:

Assembly line:It is a manufacturing process in which goods or services created in previous steps are joined together. Assembly line efficiency can be calculated by following formula:

  Assembly line efficiency=tN×CT

Here t = Task time; N= Actual no. of workstations; CT = cycle time

b

Expert Solution
Check Mark

Explanation of Solution

Assembly line efficiency can be calculated as follows:

  Assembly line efficiency=tN×CT

  Heret=32min;N=5;CT=32min

  Assemblylineefficiency=32(5×8)

  =32/40

  =.8

  =80.00%

c

Summary Introduction

Interpretation:Whether assembly line balance solution is good or bad and a criterion for assessment is to be explained.

Concept Introduction:

Idle time:It is time for which machines or employees do not work due to the stoppage or work for any causes.

c

Expert Solution
Check Mark

Explanation of Solution

The assembly line balancing goodness is assessing its assembly line efficiency and idle time. In present case, although the assembly line efficiency is 80% the idle time is 8 min which is very high. It is highest for station D i.e. 5 min and at station B and C has 1 and 2 min idle time respectively. Therefore a fair chance that station B and C becomes bottleneck station for the assembly line. So it is not the very good balancing solution.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value.  Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be included
i). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.
In the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why.  ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY