Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days) involved in the construction of a house that Habitat for Humanity is building.
Activity Optimistic Most Probable Pessimistic
A
6
7.0
8
B
7
8.0
9
C
7
7.5
11.5
D
7
9.0
10
E
6
7.0
9
F
3
4.0
5
(a) Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.)
Activity
Expected
Times
A
B
C
D
E
F
Variance
(b) An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.)
expected project completion time
variance of projection completion time
To manage the production of an animated movie, Pixar Animation Studios has listed the major activities involved, the predecessor relationships, and activity times (in months). The project is completed when activities F and G are both complete.
Activity
Immediate Predecessor
G
A
B
CD
E
A A
C, B C, B
D, E
Time
4
6
2
6
3
3
5
(a) Find the critical path. (Enter your answers as a comma-separated list.)
(b) The project must be completed in 1.5 years. Do you anticipate difficulty in meeting the deadline? Explain.
The critical path activities require
months to complete. Thus the project ---Select--- be completed in 1.5 years.
To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. In addition, they have estimated the time of each activity (in weeks).
Start
D
F
B
E
G
Activity A B C
DEFGH
Time 5 3 6 6 6 3 11 10
(a) Identify the critical path. (Enter your answers as a comma-separated list.)
H
Finish
(b) How much time (in weeks) will be needed to complete this project?
week(s)
(c) Can activity D be delayed without delaying the entire project? If so, by how many weeks? (If the activity can not be delayed, enter 0.)
week(s)
(d) Can activity C be delayed without delaying the entire project? If so, by how many weeks? (If the activity can not be delayed, enter 0.)
week(s)
(e) What is the schedule for activity E (in weeks)?
Earliest Start
Latest Start
Earliest Finish
Latest Finish
week(s)
week(s)
week(s)
week(s)
Chapter 7 Solutions
Advanced Engineering Mathematics
Ch. 7.1 - Equality. Give reasons why the five matrices in...Ch. 7.1 - Double subscript notation. If you write the matrix...Ch. 7.1 - Sizes. What sizes do the matrices in Examples 1,...Ch. 7.1 - Main diagonal. What is the main diagonal of A in...Ch. 7.1 - Scalar multiplication. If A in Example 2 shows the...Ch. 7.1 - If a 12 × 12 matrix A shows the distances between...Ch. 7.1 - Addition of vectors. Can you add: A row and a...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...
Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Let
Find the following expressions, indicating...Ch. 7.1 - Prob. 18PCh. 7.1 - Prob. 19PCh. 7.1 - TEAM PROJECT. Matrices for Networks. Matrices have...Ch. 7.2 - Multiplication. Why is multiplication of matrices...Ch. 7.2 - Square matrix. What form does a 3 × 3 matrix have...Ch. 7.2 - Product of vectors. Can every 3 × 3 matrix be...Ch. 7.2 - Skew-symmetric matrix. How many different entries...Ch. 7.2 - Same questions as in Prob. 4 for symmetric...Ch. 7.2 - Triangular matrix. If U1, U2 are upper triangular...Ch. 7.2 - Idempotent matrix, defined by A2 = A. Can you find...Ch. 7.2 - Nilpotent matrix, defined by Bm = 0 for some m....Ch. 7.2 - Transposition. Can you prove (10a)–(10c) for 3 × 3...Ch. 7.2 - Transposition. (a) Illustrate (10d) by simple...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Let
Showing all intermediate results, calculate...Ch. 7.2 - Prob. 21PCh. 7.2 - Product. Write AB in Prob. 11 in terms of row and...Ch. 7.2 - Product. Calculate AB in Prob. 11 columnwise. See...Ch. 7.2 - Commutativity. Find all 2 × 2 matrices A = [ajk]...Ch. 7.2 - TEAM PROJECT. Symmetric and Skew-Symmetric...Ch. 7.2 - Production. In a production process, let N mean...Ch. 7.2 - Concert subscription. In a community of 100,000...Ch. 7.2 - Profit vector. Two factory outlets F1 and F2 in...Ch. 7.2 - TEAM PROJECT. Special Linear Transformations....Ch. 7.3 - Prob. 1PCh. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Prob. 5PCh. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Solve the linear system given explicitly or by its...Ch. 7.3 - Prob. 10PCh. 7.3 - Prob. 11PCh. 7.3 - Prob. 12PCh. 7.3 - Prob. 13PCh. 7.3 - Prob. 14PCh. 7.3 - Prob. 15PCh. 7.3 - Prob. 17PCh. 7.3 - Prob. 18PCh. 7.3 - Prob. 19PCh. 7.3 - Prob. 20PCh. 7.3 - Prob. 21PCh. 7.3 - Prob. 22PCh. 7.3 - Prob. 23PCh. 7.3 - Prob. 24PCh. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Prob. 5PCh. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Find the rank. Find a basis for the row space....Ch. 7.4 - Prob. 8PCh. 7.4 - Prob. 9PCh. 7.4 - Prob. 10PCh. 7.4 - Show the following:
rank BTAT = rank AB. (Note the...Ch. 7.4 - Show the following:
rank A = rank B does not imply...Ch. 7.4 - Prob. 14PCh. 7.4 - Prob. 15PCh. 7.4 - Prob. 16PCh. 7.4 - Prob. 17PCh. 7.4 - Prob. 18PCh. 7.4 - Prob. 19PCh. 7.4 - Prob. 20PCh. 7.4 - Prob. 21PCh. 7.4 - Prob. 22PCh. 7.4 - Prob. 23PCh. 7.4 - Prob. 24PCh. 7.4 - Prob. 25PCh. 7.4 - Prob. 26PCh. 7.4 - Prob. 27PCh. 7.4 - Prob. 28PCh. 7.4 - Prob. 29PCh. 7.4 - Prob. 30PCh. 7.4 - Prob. 31PCh. 7.4 - Prob. 32PCh. 7.4 - Prob. 33PCh. 7.4 - Prob. 34PCh. 7.4 - Prob. 35PCh. 7.7 - Prob. 1PCh. 7.7 - Prob. 2PCh. 7.7 - Prob. 3PCh. 7.7 - Prob. 4PCh. 7.7 - Prob. 5PCh. 7.7 - Prob. 6PCh. 7.7 - Showing the details, evaluate:
Ch. 7.7 - Showing the details, evaluate:
Ch. 7.7 - Showing the details, evaluate:
Ch. 7.7 - Showing the details, evaluate:
Ch. 7.7 - Showing the details, evaluate:
Ch. 7.7 - Prob. 12PCh. 7.7 - Prob. 13PCh. 7.7 - Prob. 14PCh. 7.7 - Prob. 15PCh. 7.7 - Prob. 17PCh. 7.7 - Prob. 18PCh. 7.7 - Prob. 19PCh. 7.7 - Prob. 21PCh. 7.7 - Prob. 22PCh. 7.7 - Prob. 23PCh. 7.7 - Prob. 24PCh. 7.7 - Prob. 25PCh. 7.8 - Prob. 1PCh. 7.8 - Prob. 2PCh. 7.8 - Prob. 3PCh. 7.8 - Prob. 4PCh. 7.8 - Prob. 5PCh. 7.8 - Prob. 6PCh. 7.8 - Prob. 7PCh. 7.8 - Prob. 8PCh. 7.8 - Prob. 9PCh. 7.8 - Prob. 10PCh. 7.8 - Prob. 11PCh. 7.8 - Prob. 12PCh. 7.8 - Prob. 13PCh. 7.8 - Prob. 14PCh. 7.8 - Prob. 15PCh. 7.8 - Prob. 16PCh. 7.8 - Prob. 17PCh. 7.8 - Prob. 18PCh. 7.8 - Prob. 19PCh. 7.8 - Prob. 20PCh. 7.9 - Prob. 1PCh. 7.9 - Prob. 2PCh. 7.9 - Prob. 3PCh. 7.9 - Prob. 4PCh. 7.9 - Prob. 5PCh. 7.9 - Prob. 6PCh. 7.9 - Prob. 7PCh. 7.9 - Prob. 8PCh. 7.9 - Prob. 9PCh. 7.9 - Prob. 10PCh. 7.9 - Prob. 11PCh. 7.9 - Prob. 12PCh. 7.9 - Prob. 13PCh. 7.9 - Prob. 14PCh. 7.9 - Prob. 15PCh. 7.9 - Prob. 16PCh. 7.9 - Prob. 17PCh. 7.9 - Prob. 18PCh. 7.9 - Prob. 19PCh. 7.9 - Prob. 20PCh. 7.9 - Prob. 21PCh. 7.9 - Prob. 22PCh. 7.9 - Prob. 23PCh. 7.9 - Prob. 24PCh. 7.9 - Prob. 25PCh. 7 - Prob. 1RQCh. 7 - Prob. 2RQCh. 7 - Prob. 3RQCh. 7 - Prob. 4RQCh. 7 - Prob. 5RQCh. 7 - Prob. 6RQCh. 7 - Prob. 7RQCh. 7 - Prob. 8RQCh. 7 - Prob. 9RQCh. 7 - Prob. 10RQCh. 7 - Prob. 11RQCh. 7 - Prob. 12RQCh. 7 - Prob. 13RQCh. 7 - Prob. 14RQCh. 7 - Prob. 15RQCh. 7 - Prob. 16RQCh. 7 - Prob. 17RQCh. 7 - Prob. 18RQCh. 7 - Prob. 19RQCh. 7 - Prob. 20RQCh. 7 - Prob. 21RQCh. 7 - Prob. 22RQCh. 7 - Prob. 23RQCh. 7 - Prob. 24RQCh. 7 - Prob. 25RQCh. 7 - Prob. 26RQCh. 7 - Prob. 27RQCh. 7 - Prob. 28RQCh. 7 - Prob. 29RQCh. 7 - Prob. 30RQCh. 7 - Prob. 31RQCh. 7 - Prob. 32RQCh. 7 - Prob. 33RQCh. 7 - Prob. 34RQCh. 7 - Prob. 35RQ
Knowledge Booster
Similar questions
- 30.6. Classify the zeros and singularities of the functions tanz (a). f(z)=sin(1-2-1), (b). f(2) = (c). f(z)= tanh .arrow_forward1. Locate the singularities of three of the following functions, and determine their type. (a) f(z)=2(z-sinz). (b) f(z) = (-) (c) f(z) = (z+2-22²)-1 (d) f(z) = sinzarrow_forwardQ 2/classify the zeros and poles of the function f(z) = tanz Zarrow_forward
- 30.1. Show that z = 0 is a removable singularity of the following functions. Furthermore, define f(0) such that these functions are analytic at z = 0. (a). f(z) = 2 sin z- z 1-12² - cos z (b). f(z) = (c). f(z) = sin 22arrow_forward3. Consider the polynomial equation 6-iz+7z² -iz³ +z = 0 for which the roots are 3i, -2i, -i, and i. (a) Verify the relations between this roots and the coefficients of the polynomial. (b) Find the annulus region in which the roots lie.arrow_forward30.3. Find and classify the isolated singularities of the following func- tions: (a). 23+1 22(2-1) (b). ²e¹/, (c). sin 3z (d). COS 2arrow_forward
- 3. Consider the polynomial equation 6-iz+7z2-iz³ +z = 0 for which the roots are 3i, -2i, -i, and i. (a) Verify the relations between this roots and the coefficients of the polynomial. (b) Find the annulus region in which the roots lie.arrow_forwardDetermine the set of odd primes p for which 23 is a quadratic residue.arrow_forwardQ/ Find and classify the singularities of the functions- = 52+3 (1-2) sin² Z a fcz) b f(z) = tanz Z © f(2)= [z (e²-1)]arrow_forward
- A linear programming computer package is needed. As part of the settlement for a class action lawsuit, Hoxworth Corporation must provide sufficient cash to make the following annual payments (in thousands of dollars). Year 1 2 2 3 4 5 6 Payment 210 235 260 305 335 480 The annual payments must be made at the beginning of each year. The judge will approve an amount that, along with earnings on its investment, will cover the annual payments. Investment of the funds will be limited to savings (at 4% annually) and government securities, at prices and rates currently quoted in The Wall Street Journal. Hoxworth wants to develop a plan for making the annual payments by investing in the following securities (par value = $1,000). Funds not invested in these securities will be placed in savings. Security Current Price Rate (%) Years to Maturity 1 2 $1,055 $1,000 6.750 5.125 3 4 Assume that interest is paid annually. The plan will be submitted to the judge and, if approved, Hoxworth will be…arrow_forwardA linear programming computer package is needed. Hanson Inn is a 96-room hotel located near the airport and convention center in Louisville, Kentucky. When a convention or a special event is in town, Hanson increases its normal room rates and takes reservations based on a revenue management system. A large professional organization has scheduled its annual convention in Louisville for the first weekend in June. Hanson Inn agreed to make at least 50% of its rooms available for convention attendees at a special convention rate in order to be listed as a recommended hotel for the convention. Although the majority of attendees at the annual meeting typically request a Friday and Saturday two-night package, some attendees may select a Friday night only or a Saturday night only reservation. Customers not attending the convention may also request a Friday and Saturday two-night package, or make a Friday night only or Saturday night only reservation. Thus, six types of reservations are…arrow_forwardA linear programming computer package is needed. Epsilon Airlines services predominately the eastern and southeastern United States. A vast majority of Epsilon's customers make reservations through Epsilon's website, but a small percentage of customers make reservations via phone. Epsilon employs call-center personnel to handle these reservations along with any problems with the website reservation system and for the rebooking of flights for customers if their plans change or their travel is disrupted. Staffing the call center appropriately is a challenge for Epsilon's management team. Having too many employees on hand is a waste of money, but having too few results in very poor customer service and the potential loss of customers. Epsilon analysts have estimated the minimum number of call-center employees needed by day of week for the upcoming vacation season (June, July, and the first two weeks of August). These estimates are given in the following table. Day Minimum Number of…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Advanced Engineering MathematicsAdvanced MathISBN:9780470458365Author:Erwin KreyszigPublisher:Wiley, John & Sons, IncorporatedNumerical Methods for EngineersAdvanced MathISBN:9780073397924Author:Steven C. Chapra Dr., Raymond P. CanalePublisher:McGraw-Hill EducationIntroductory Mathematics for Engineering Applicat...Advanced MathISBN:9781118141809Author:Nathan KlingbeilPublisher:WILEY
- Mathematics For Machine TechnologyAdvanced MathISBN:9781337798310Author:Peterson, John.Publisher:Cengage Learning,

Advanced Engineering Mathematics
Advanced Math
ISBN:9780470458365
Author:Erwin Kreyszig
Publisher:Wiley, John & Sons, Incorporated

Numerical Methods for Engineers
Advanced Math
ISBN:9780073397924
Author:Steven C. Chapra Dr., Raymond P. Canale
Publisher:McGraw-Hill Education

Introductory Mathematics for Engineering Applicat...
Advanced Math
ISBN:9781118141809
Author:Nathan Klingbeil
Publisher:WILEY

Mathematics For Machine Technology
Advanced Math
ISBN:9781337798310
Author:Peterson, John.
Publisher:Cengage Learning,