Chapter 7, Problem 89P
To determine

(a)

The value of APR.

Expert Solution
Check Mark

Answer to Problem 89P

The value of APR is 6.28%.

Explanation of Solution

Given:

The amount is $220,000.

Time period is 30 years.

Loan origination fees is 3%.

Concept used:

Write the expression to calculate the monthly payments.

Monthlypayments=PMT(r,n,A) ...... (I)

Here, the rate for loan is r, time period is n and the mortgage amount is A.

Calculation:

Calculate the total amount of mortgage with points.

A=$220,000+(3%of$220,000)=$220,000+(3100×$220,000)=$220,000+$6,600=$226,600

Calculate the time period in term of months.

Timeperiod=30years×(12 months1 year)=360months

Calculate the rate of interest for one month.

Rate=6%12=0.005

Calculate the monthly payments with points.

Substitute 0.005 for r, 360 for n and $226,600 for A in Equation (I).

Monthlypayment=PMT(0.005,360,$226,600)=$226,600(11(1+0.005)3600.005)=$226,600166.79=$1358.59

Mortgage amount without points is $220,000

Calculate the APR.

Substitute 1358.59 for monthly payment, 360 for n and 220,000 for A in Equation (I).

$1358.59=PMT(APR,360,$220,000)$1358.59=$220,000(11(1+APR)360APR)11(1+APR)360APR=$220,000$1358.59

Calculate the value of APR.

APR=6.28%.

Conclusion:

Thus, the value of APR is 6.28%.

To determine

(b)

The value of APR.

Expert Solution
Check Mark

Answer to Problem 89P

The value of APR is 7.04%.

Explanation of Solution

Given:

The amount is

$220,000.

Time period is 30 years.

Loan origination fees is 3%.

Concept used:

Write the expression to calculate the monthly payments.

Monthlypayments=PMT(r,n,A) ...... (II)

Here, the rate for loan is r, time period is n and the mortgage amount is A.

Calculation:

Calculate the total amount of mortgage with points.

A=$220,000+(3%of$220,000)=$220,000+(3100×$220,000)=$220,000+$6,600=$226,600

Calculate the time period in term of months.

Timeperiod=6years×(12 months1 year)=72months

Calculate the rate of interest for one month.

Rate=6%12=0.005

Calculate the monthly payments with points.

Substitute 0.005 for r, 72 for n and $226,600 for A in Equation (II).

Monthlypayment=PMT(0.005,72,$226,600)=$226,600(11(1+0.005)720.005)=$226,60060.33=$3756

Mortgage amount without points is $220,000 ./

Calculate the APR.

Substitute $3756 for monthly payment, 72 for n and $220,000 for A in Equation (I).

$3756=PMT(APR,360,$220,000)$3756=$220,000(11(1+APR)72APR)11(1+APR)72APR=$220,000$3756

Calculate the value of APR.

APR=7.04%.

Conclusion:

Thus, the value of APR is 7.04%.

To determine

(c)

The graph of effective interest rate.

Expert Solution
Check Mark

Answer to Problem 89P

The graph of effective interest and time is shown below.

ENGINEERING ECO ANALYSIS W/STUDY GUIDE, Chapter 7, Problem 89P , additional homework tip  1

Explanation of Solution

Given:

Amount is $220,000.

Time period is 30 years.

Loan origination fees is 3%.

Calculation:

The following table shows the value of time and effective interest rate.

Time to pay off mortgage Effective interest rate
1year 11.5714%
2year 8.9248%
3year 7.9962%
4year 7.5259%
7.2361% ath>5year
6year 7.0439%
7year 6.9061%
8year 6.8026%
9year 6.7220%
10year 6.6575%
11year 6.6048%
12year 6.5610%
13year 6.5329%
14year 6.4922%
15year 6.4648%

Plot the graph of effective interest and time as shown below.

ENGINEERING ECO ANALYSIS W/STUDY GUIDE, Chapter 7, Problem 89P , additional homework tip  2

Graph-(1).

Conclusion:

The graph of effective interest and time is shown below.

ENGINEERING ECO ANALYSIS W/STUDY GUIDE, Chapter 7, Problem 89P , additional homework tip  3

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Should Maureen question the family about the history of the home? Can Maureen access public records for proof of repairs?
3. Distinguish between a direct democracy and a representative democracy. Use appropriate examples to support your answers. [4] 4. Explain the distinction between outputs and outcomes in social service delivery [2] 5. A R1000 tax payable by all adults could be viewed as both a proportional tax and a regressive tax. Do you agree? Explain. [4] 6. Briefly explain the displacement effect in Peacock and Wiseman's model of government expenditure growth and provide a relevant example of it in the South African context. [5] 7. Explain how unbalanced productivity growth may affect government expenditure and briefly comment on its relevance to South Africa. [5] 8. South Africa has recently proposed an increase in its value-added tax rate to 15%, sparking much controversy. Why is it argued that value-added tax is inequitable and what can be done to correct the inequity? [5] 9. Briefly explain the difference between access to education and the quality of education, and why we should care about the…
20. Factors 01 pro B. the technological innovations available to companies. A. the laws that regulate manufacturers. C. the resources used to create output D. the waste left over after goods are produced. 21. Table 1.1 shows the tradeoff between different combinations of missile production and home construction, ceteris paribus. Complete the table by calculating the required opportunity costs for both missiles and houses. Then answer the indicated question(s). Combination Number of houses Opportunity cost of houses in Number of missiles terms of missiles J 0 4 K 10,000 3 L 17,000 2 1 M 21,000 0 N 23,000 Opportunity cost of missiles in terms of houses Tutorials-Principles of Economics m health care

Chapter 7 Solutions

ENGINEERING ECO ANALYSIS W/STUDY GUIDE

Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education