Sales, production, direct materials purchases, and direct labor cost budgets

The budget director of Royal Furniture Company requests estimates of sales, production, and other operating data from the various administrative units every month. Selected information concerning sales and production for February is summarized as follows:

Estimated sales of King and Prince chairs for February by sales territory:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  1

Estimated inventories at February 1:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  2

Desired inventories at February 28:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  3

Direct materials used in production:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  4

Anticipated purchase price for direct materials:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  5

Direct labor requirements:

Chapter 7, Problem 2PB, Sales, production, direct materials purchases, and direct labor cost budgets The budget director of , example  6

Instructions

Prepare a sales budget for February.

Prepare a production budget for February.

Prepare a direct materials purchases budget for February.

Prepare a direct labor cost budget for February.

1.

Expert Solution
Check Mark
To determine

Prepare the sales budget for the month ending February 28.

Explanation of Solution

Budgeting:

Budgeting is a process to prepare the financial statement by the manager to estimate the organization’s future actions. It is also helpful to satisfy the everyday activities.

The following table shows the sales budget.

Company R

Sales Budget

For the Month Ending February 28

Product and AreaUnit Sales VolumeUnit Selling Price ($)Total Sales ($)
(A)(B)(A) × (B)
King:   
      Northern Domestic610780475,800
      Southern Domestic340780265,200
      International360850306,000
Total1,310 1,047,000
Prince:   
      Northern Domestic750550412,500
      Southern Domestic440550242,000
      International290600174,000
Total1,480 828,500
Total Revenue from Sales1,875,500

Table (1)

2.

Expert Solution
Check Mark
To determine

Prepare the production budget for the month ending February 28.

Explanation of Solution

The following table shows the production budget.

Company R

Production Budget

For the Month Ending February 28

DetailsUnits
KingPrince
Expected Units to be Sold1,3101,480
Add: Desired Inventory, February 288035
Total Units Required1,3901,515
Less: Estimated Inventory, February 1(90)(25)
Total Units to be Produced1,3001,490

Table (2)

3.

Expert Solution
Check Mark
To determine

Prepare the direct materials purchase budget for the month ending February 28.

Explanation of Solution

The following table shows the direct materials purchase budget.

Company R

Direct Materials Purchase Budget

For the Month Ending February 28

DetailsUnits
FabricWoodFillerSprings
Required units for production:    
King7,800 (1)49,400 (2)5,460 (3)20,800 (4)
Prince5,960 (5)38,740 (6)5,066 (7)17,880 (8)
Add: Desired inventory, February 28390650300540
Total units required14,15088,79010,82639,220
Less: Estimated inventory, February 1 (420)(580)(250)(660)
Total units to be purchased (A)13,73088,21010,57638,560
Unit price (B)$12$7$3$4.50
Total (A) × (B)$164,760$617,470$31,728$173,520
Total direct materials to be purchased987,478

Table (3)

Working Note (1):

Calculate the direct material (fabric) for king.

Direct material (fabric) cost for king=1,300×6.0yds=7,800sq. yds

Working Note (2):

Calculate the direct material (wood) for king.

Direct material (wood) cost for king=1,300×38linear ft.=49,400linear ft.

Working Note (3):

Calculate the direct material (filler) for king.

Direct material (filler) cost for king=1,300×4.2cu.ft=5,460cu.ft

Working Note (4):

Calculate the direct material (springs) for king.

Direct material (springs) cost for king=1,300×16units=20,800units

Working Note (5):

Calculate the direct material (fabric) for prince.

Direct material (fabric) cost for prince=1,490×4.0yds=5,960sq. yds

Working Note (6):

Calculate the direct material (wood) for prince.

Direct material (wood) cost for prince=1,490×26linear ft.=38,740linear ft.

Working Note (7):

Calculate the direct material (filler) for prince.

Direct material (filler) cost for prince=1,490×3.4cu.ft=5,066cu.ft

Working Note (8):

Calculate the direct material (springs) for prince.

Direct material (springs) cost for prince=1,490×12units=17,880units

4.

Expert Solution
Check Mark
To determine

Prepare the direct labor cost budget of Company R.

Explanation of Solution

The following table shows the direct labor cost budget for framing, cutting, and upholstery department.

Company R
Direct Labor Cost Budget
For the Month Ending February 28
ParticularsFraming Department

Cutting

Department

Upholstery

Department

Hours Required for Production:   
     King1,560 (9)650 (10)1,040 (11)
     Prince1,490 (12)596 (13)894 (14)
Total Hours Required (A)3,0501,2461,934
Hourly Rate (B)$12$14$15
Total Cost (A) × (B)$36,600$17,444$29,010
Total Direct Labor Cost83,054

Table (4)

Working Note (9):

Calculate the hours required for the production of king in framing department.

Hours required for production=1,300×1.20hr=1,560hrs

Working Note (10):

Calculate the hours required for the production of king in cutting department.

Hours required for production=1,300×0.50hr=650hrs

Working Note (11):

Calculate the hours required for the production of king in upholstery department.

Hours required for production=1,300×0.80hr=1,040hrs

Working Note (12):

Calculate the hours required for the production of prince in framing department.

Hours required for production=1,490×1.00hr=1,490hrs

Working Note (13):

Calculate the hours required for the production of prince in cutting department.

Hours required for production=1,490×0.4hr=596hrs

Working Note (14):

Calculate the hours required for the production of prince in upholstery department.

Hours required for production=1,490×0.60hr=894hrs

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
What amount should Eagle Corporation record as the cost of the new van for this general accounting question?
Need help with this accounting questions
Kindly help me Accounting question

Chapter 7 Solutions

Managerial Accounting

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Text book image
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Responsibility Accounting| Responsibility Centers and Segments| US CMA Part 1| US CMA course; Master Budget and Responsibility Accounting-Intro to Managerial Accounting- Su. 2013-Prof. Gershberg; Author: Mera Skill; Rutgers Accounting Web;https://www.youtube.com/watch?v=SYQ4u1BP24g;License: Standard YouTube License, CC-BY