Concept explainers
The reason to hold the comprehensive knowledge of carpentry details and practices for the estimator of carpentry work.
Explanation of Solution
The estimate for any project is to be prepared before the work and various factors influence and contribute to the cost of the work. So before making an estimate for any carpentry or any work, comprehensive and detailed knowledge of principal and practices of the project is required.
The drawing of the project contains information regarding designing, dimension and location of the project but very few details are provided on the drawings of carpentry work of a housing project. It is assumed by architecture that the construction of the building is done by the builder as per the standard codes of the building and construction of the particular area.
So the estimator should be well-known to the building codes and standard methods of framing in the area for accurately estimating the work. He should be also known to the conditions which may require extra work such as the requirement of additional studs, joist and reinforced joints for completion of the project.
Want to see more full solutions like this?
Chapter 7 Solutions
Fundamentals Of Construction Estimating
- What types of materials should be paid to the contractor upon delivery, even before they are assembled into the completed work?arrow_forwardWhat are the three major divisions of the construction industry?arrow_forwardIt is a well-known principle that the engineer should not tell the contractor how to do the work; but, if the engineer observes that the contractor’s construction methods appear to be unable to meet the specifications,what should the engineer do?arrow_forward
- HI! PLEASE ANSWER THIS QUESTION. THANK YOU! NEED ASAParrow_forwardYou’re a construction engineer and one of your responsibilities is to estimate and schedule construction workers to complete projects. You’ve been given the job to frame a house and you know that 30 men can complete the job in 12 days if the number of working hours per day is 8. However, you only have a construction crew of 24 workers and your contract requires that you complete the framing in 10 days. If the job is to be completed in 10 days with 24 workers, what will be the working hours per dayarrow_forwardWhich trades are likely to be involved with the construction of an elevated concrete slab? Select all that apply. Group of answer choices A)Carpenters B)Laborers C)Painters d)Ironworkers E)Operating Engineersarrow_forward
- What are some of the methods that the architect or engineer may use to reduce the cost of construction?arrow_forwardDescribe the role of the owner, designer, and the contractor in the construction process?arrow_forwardWhich of the following trades would be likely to be involved with the construction of a building’s 3rd floor concrete slab? (please indicate either “yes” or “no” for each choice) Group of answer choices Carpenters y/n Laborers y/n Ironworkers y/n Operating Engineers y/narrow_forward
- Note: This is not an assignment question. Please kindly give me both answers. Help me Explain briefly the material selection criteria and the materials which are used to manufacture 1. Girders 2. Drill bitsarrow_forwardWho is responsible for contracting for subcontractor services for construction on a project? a. The owner b. The architect c. The engineer d. The constructor e. All of the abovearrow_forwardAs a mechanical engineer, why is it vital to understand construction safety? What crucial factors need to be taken into account to provide a secure working environment for contractors?arrow_forward
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,