Question
Book Icon
Chapter 7, Problem 15E

(1)

To determine

To prepare: Direct material budget for September, October.

(1)

Expert Solution
Check Mark

Explanation of Solution

Given,
September,
Production units are 4,600.
Raw material required per unit 2 pounds.
Opening raw material is 3,680 units.
October,
Production units are 6,200.
Raw material required per unit 2 pounds.
November,
Production units are 5,800 units.

    Direct Material Budget
    Particulars September October
    Production (units) 4,600 6,200
    Raw material required (pounds) (working note) 9,200 12,400
    Add: Ending raw material (working note) 4,960 4,640
    Less: Opening raw material 3,680 4,960
    Total material required (pounds) [A] 10,480 12,080
    Purchase cost [B] 4 4
    Total Purchase Cost ($) [ A×B ] 49,920 48,320
    Table (1)

Working notes:

Formula to compute raw material required,

Raw material required=Production×Raw material required per unit

For September,

Substitute 4,600 units for production and 2 pounds for raw material required per unit.

Raw material required=4,600units×2pounds =9,200pounds

For October,

Substitute 6,200 units for production and 2 pounds for raw material required per unit.

Raw material required=6,200units×2pounds =12,400pounds

November’s material requirement,

    Raw material required=Production×Raw material required per unit

Substitute 5,800 for production and 2 pounds for raw material required per unit.

Raw material required=5,800units×2pounds =11,600pounds

Formula to compute ending raw material,

    Endingraw material=40%×Nextquarter'smaterialrequirement

For September,

Substitute 12,400 for third October’s material requirement,

Endingraw material=40%×12,400units =4,960units

For October,

Substitute 11,600 for November’s material requirement,

Endingraw material=40%×11,600units =4,640units

(2)

To determine

To prepare: Direct labor budget for September, October.

(2)

Expert Solution
Check Mark

Explanation of Solution

Given,

September,
Production is 4,600 units.
Labor rate per hour is $16.
Labor hours per unit are 0.8.
October,
Production is 6,200 units.
Labor rate per hour is $16.
Labor hours per unit are 0.8.

    Direct Labor Budget
    Particulars September October
    Production(units) [ A ] 4,600 6,200
    Hours required per unit [ B ] 0.8 0.8
    Total hours required [ A×B ] 3,680 4,960
    Labor rate per hour 16 16
    Total labor cost($)[working note] 58,880 79,360
    Table (2)

Working note:

Formula to compute total labor cost,

Total labor cost=Total hours required×Labor rate per hour

For September,

Substitute 3,680 hours for total hours required and $16 for labor rate per hour.

Total labor cost=3,680 hours×$16 =$58,880

For October,

Substitute 4,960 hours for total hours required and $16 for labor rate per hour.

Total labor cost=4,960 hours×$16 =$79,360

(3)

To determine

To prepare: Factory overhead budget for September, October.

(3)

Expert Solution
Check Mark

Explanation of Solution

    Factory Overhead Budget
    Particulars September October
    Total labor hours required (From part 2) [ A ] 3,680 4,960
    Application rate per labor hour ($) [ B ] 2 2
    Variable overheads ($) [ A×B ] 7,360 9,920
    Add: Fixed overheads (given) 10,000 10,000
    Total factory overheads 17,360 19,920
    Table (3)

Hence, Direct material budget of September is $49,920, October.$48,320.
Direct labor budget of September is $58,880, October.$79,360.
Factory Overhead Budget of September is $17,360, October.$19,920.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 7 Solutions

Managerial Accounting

Ch. 7 - How does budgeting help management coordinate and...Ch. 7 - Why is the sales budget so important to the...Ch. 7 - What is the selling expense budget? What is the...Ch. 7 - Prob. 9DQCh. 7 - GOOGLE Google prepares a cash budget. What is a...Ch. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Coca-cola recently redesigned its bottle to reduce...Ch. 7 - Activity-based budgeting is a budget system based...Ch. 7 - Budget motivation C1 For each of the following...Ch. 7 - Budgeting benefits C1 For each of the following...Ch. 7 - Prob. 3QSCh. 7 - Prob. 4QSCh. 7 - Prob. 5QSCh. 7 - Prob. 6QSCh. 7 - Prob. 7QSCh. 7 - Prob. 8QSCh. 7 - Prob. 9QSCh. 7 - Prob. 10QSCh. 7 - Prob. 11QSCh. 7 - Prob. 12QSCh. 7 - Prob. 13QSCh. 7 - Prob. 14QSCh. 7 - Prob. 15QSCh. 7 - Manufacturing: Production budget P1 Atlantic Surf...Ch. 7 - Prob. 17QSCh. 7 - Prob. 18QSCh. 7 - Prob. 19QSCh. 7 - Cash receipts, with uncollectible accounts P2 The...Ch. 7 - Cash receipts, with uncollectible accounts P2 Well...Ch. 7 - Prob. 22QSCh. 7 - Budgeted loan activity P2 Santos Co. is preparing...Ch. 7 - Prob. 24QSCh. 7 - Prob. 25QSCh. 7 - Prob. 26QSCh. 7 - Prob. 27QSCh. 7 - Prob. 28QSCh. 7 - Prob. 29QSCh. 7 - Prob. 30QSCh. 7 - Prob. 31QSCh. 7 - Prob. 1ECh. 7 - Prob. 2ECh. 7 - Prob. 3ECh. 7 - Prob. 4ECh. 7 - Exercise 20-5 Manufacturing: Direct labor budget...Ch. 7 - Prob. 6ECh. 7 - Prob. 7ECh. 7 - Prob. 8ECh. 7 - Prob. 9ECh. 7 - Prob. 10ECh. 7 - Prob. 11ECh. 7 - Prob. 12ECh. 7 - Prob. 13ECh. 7 - Prob. 14ECh. 7 - Prob. 15ECh. 7 - Prob. 16ECh. 7 - Prob. 17ECh. 7 - Prob. 18ECh. 7 - Prob. 19ECh. 7 - Prob. 20ECh. 7 - Prob. 21ECh. 7 - Prob. 22ECh. 7 - Prob. 23ECh. 7 - Prob. 24ECh. 7 - Prob. 25ECh. 7 - Prob. 26ECh. 7 - Prob. 27ECh. 7 - Prob. 28ECh. 7 - Prob. 29ECh. 7 - Prob. 30ECh. 7 - Prob. 31ECh. 7 - Prob. 32ECh. 7 - Prob. 33ECh. 7 - Prob. 34ECh. 7 - Prob. 35ECh. 7 - Prob. 1PSACh. 7 - Prob. 2PSACh. 7 - Prob. 3PSACh. 7 - Prob. 4PSACh. 7 - Prob. 5PSACh. 7 - Prob. 6PSACh. 7 - Prob. 7PSACh. 7 - Prob. 8PSACh. 7 - Prob. 1PSBCh. 7 - Prob. 2PSBCh. 7 - Prob. 3PSBCh. 7 - Prob. 4PSBCh. 7 - Prob. 5PSBCh. 7 - Prob. 6PSBCh. 7 - Prob. 7PSBCh. 7 - Prob. 8PSBCh. 7 - Prob. 7SPCh. 7 - Prob. 1AACh. 7 - Prob. 2AACh. 7 - Prob. 3AACh. 7 - ETHICS CHALLENGE C1 BTN 20-3 Both the budget...Ch. 7 - Prob. 2BTNCh. 7 - Prob. 3BTNCh. 7 - Prob. 4BTNCh. 7 - Prob. 5BTNCh. 7 - Prob. 6BTN
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles