INTER. ACCOUNTING - CONNECT+ALEKS ACCESS
10th Edition
ISBN: 9781264770335
Author: SPICELAND
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 6, Problem 6.24E
Long-term contract; revenue recognition over time; solve for unknowns
• LO5–9
In 2018, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2018, is as follows:
Required:
1. What was the cost of construction actually incurred in 2018?
2. How much cash was collected in 2018 on this contract?
3. What was the estimated cost to complete as of the end of 2018?
4. What was the estimated percentage of completion used to calculate revenue in 2018? (AICPA adapted)
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Please help me to solve this problem
3
Please don't give image format
Chapter 6 Solutions
INTER. ACCOUNTING - CONNECT+ALEKS ACCESS
Ch. 6 - What are the five key steps a company follows to...Ch. 6 - What indicators suggest that a performance...Ch. 6 - What criteria determine whether a company can...Ch. 6 - We recognize service revenue either at one point...Ch. 6 - What characteristics make a good or service a...Ch. 6 - Prob. 6.6QCh. 6 - What must a contract include for the contract to...Ch. 6 - How might the definition of probable affect...Ch. 6 - When a contract includes an option to buy...Ch. 6 - Prob. 6.10Q
Ch. 6 - Prob. 6.11QCh. 6 - Is a customers right to return merchandise a...Ch. 6 - Prob. 6.13QCh. 6 - Under what circumstances should sellers consider...Ch. 6 - When should a seller view a payment to its...Ch. 6 - What are three methods for estimating stand-alone...Ch. 6 - When is revenue recognized with respect to...Ch. 6 - In a franchise arrangement, what are a franchisors...Ch. 6 - When does a company typically recognize revenue...Ch. 6 - Prob. 6.20QCh. 6 - Prob. 6.21QCh. 6 - Prob. 6.22QCh. 6 - Must bad debt expense be reported on its own line...Ch. 6 - Explain the difference between contract assets,...Ch. 6 - Explain how to account for revenue on a long-term...Ch. 6 - Prob. 6.26QCh. 6 - Prob. 6.27QCh. 6 - Timing of revenue recognition LO53 Estate...Ch. 6 - Allocating the transaction price LO54 Sarjit...Ch. 6 - Existence of a contract LO5-5 Tulane Tires wrote...Ch. 6 - Prob. 6.6BECh. 6 - Prob. 6.7BECh. 6 - Performance obligations; warranties LO55 Vroom...Ch. 6 - Prob. 6.9BECh. 6 - Prob. 6.10BECh. 6 - Variable consideration LO56 Leo Consulting enters...Ch. 6 - Prob. 6.16BECh. 6 - Prob. 6.17BECh. 6 - Prob. 6.18BECh. 6 - Prob. 6.19BECh. 6 - Prob. 6.20BECh. 6 - Prob. 6.21BECh. 6 - Estimating stand-alone selling prices: expected...Ch. 6 - Estimating stand-alone selling prices; residual...Ch. 6 - Prob. 6.24BECh. 6 - Prob. 6.25BECh. 6 - Contract assets and contract liabilities LO58...Ch. 6 - Long-term contract; revenue recognition over time;...Ch. 6 - Prob. 6.34BECh. 6 - Long-term contract; revenue recognition upon...Ch. 6 - Long-term contract; revenue recognition; loss on...Ch. 6 - Prob. 6.1ECh. 6 - Allocating transaction price LO54 Video Planet...Ch. 6 - Prob. 6.4ECh. 6 - Prob. 6.6ECh. 6 - Prob. 6.7ECh. 6 - Prob. 6.9ECh. 6 - Variable considerationmost likely amount; change...Ch. 6 - Variable considerationexpected value; change in...Ch. 6 - Prob. 6.12ECh. 6 - Prob. 6.13ECh. 6 - Prob. 6.14ECh. 6 - Approaches for estimating stand-alone selling...Ch. 6 - FASB codification research LO56, LO57 Access the...Ch. 6 - FASB codification research LO58 Access the FASB...Ch. 6 - Long-term contract; revenue recognition over time;...Ch. 6 - Prob. 6.1PCh. 6 - Prob. 6.2PCh. 6 - Prob. 6.3PCh. 6 - Prob. 6.5PCh. 6 - Variable consideration; change of estimate LO53,...Ch. 6 - Prob. 6.7PCh. 6 - Prob. 6.8PCh. 6 - Prob. 6.10PCh. 6 - Long-term contract; revenue recognition over time...Ch. 6 - Prob. 6.1DMPCh. 6 - Judgment Case 52 Satisfaction of performance...Ch. 6 - Judgment Case 53 Satisfaction of performance...Ch. 6 - Prob. 6.5DMPCh. 6 - Prob. 6.7DMPCh. 6 - Prob. 6.9DMPCh. 6 - Prob. 6.10DMPCh. 6 - Prob. 6.12DMPCh. 6 - Prob. 6.13DMPCh. 6 - Prob. 6.14DMPCh. 6 - Prob. 6.15DMPCh. 6 - Prob. 1CCTC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2021 2022 $2,044,000 $2,628,000 5,256,000 2,628,000 2,170,000 2,502,000 1,885,000 2,600,000 Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate…arrow_forwardQ.3.arrow_forwardH1.arrow_forward
- shj.7arrow_forward56 On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022? On February 20, 2022, ABC Construction Company entered into a fixed-price contract to construct a commercial building for P9,000,000. ABC determined that the performance obligation is satisfied over time. Information relating to the contract is as follows: 2022 2023 Percentage of completion 25% 75% Estimated costs at completion P6,750,000 P7,200,000 How much is the contract costs charged to profit or loss in 2022?arrow_forwardDineshbhaiarrow_forward
- Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Problem 6-10 (Algo) Part 5 Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) $ $ 2024 $ 2,610,000 6,390,000 2,100,000 1,850,000 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. X Answer is complete but not entirely correct. 2026 3,939,962 (110,038)…arrow_forwardProblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end 2024 $ 2,610,000 6,390,000 2,100,000 2025 2026 $ 3,162,000 $ 2,230,800 2,028,000 0 3,672,000 1,850,000 3,000,000 4,228,000 5,150,000 Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest…arrow_forwardRahularrow_forward
- Required information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Problem 6-10 (Algo) Part 3 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Current liabilities: 2024 $ 2,156,000 5,544,000 2,130,000 1,865,000 3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Note: Do not round intermediate calculations. 2024 2025 2026 $ 3,388,000 $ 2,371,600 2,156,000 0 3,414,000 3,300,000 2025 4,456,000…arrow_forward7arrow_forwardExercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 2024 $ 50 200 2025 $ 150 2026 $ 45 50 31 Required: 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Depreciation -MACRS; Author: Ronald Moy, Ph.D., CFA, CFP;https://www.youtube.com/watch?v=jsf7NCnkAmk;License: Standard Youtube License