INTER. ACCOUNTING - CONNECT+ALEKS ACCESS
10th Edition
ISBN: 9781264770335
Author: SPICELAND
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
2. Prepare journal entries for 2018 and 2019 to record the transactions described (credit "various accounts" for
construction costs incurred).
3. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018 and 2019.
Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
In 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $1,090,000. Sunland
uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the
proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this
contract at December 31, 2025, are shown below.
Balance Sheet
Accounts receivable
Construction in process
Less: Billings
Costs and recognized profit in excess of billings
Income Statement
$16,600
$62,500
58,000
4,500
Income (before tax) on the contract recognized in 2025
(a)
Your answer is correct.
How much cash was collected in 2025 on this contract?
(b)
Portion of contract billings collected $
eTextbook and Media
* Your answer is incorrect.
$20,000
41400
What was the initial estimated total income before tax on this contract?
Income before tax on this contract
$
4500
Attempts: 2 of 15 used
Knowledge Booster
Similar questions
- Koolman Construction Company began work on a contract in 2019. The contract price is 3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: Required: 1. Compute the gross profit or loss recognized in 2019 and 2020. 2. Prepare the appropriate sections of the income statement and ending balance sheet for each year.arrow_forwardJhun Co. recognizes construction revenues and expenses using the percentage of completion method. During 2019, a single long-term contract was started, which continued through the year 2020. Information the project follows: 2019 Account receivable on contract 100,000 Construction expense 105,000 Construction in progress 122,000 Partial billings on contract 100,000 2020 Account receivable on contract 300,000 Construction expense 192,000 Construction in progress 364,000 Partial billings on contract 420,000 Profit recognized in 2019 should be? Profit recognized in 2020 should be?arrow_forwardUsing the percentage-of-completion method and the cost-to-cost basis, prepare the journal entry to record progress billings of$1,638,800 during 2023. Using the percentage-of-completion method and the cost-st basis, prepare the journal entries to record the revenue andgross proft for 2023. Transcribed Image Text:Crane Corp. contracted to build a bridge for $4,820,000. Construction began in 2023 and was completed in 2024. Data relating to the construction are: 2023 2024 Costs incurred $1,561,680 $1,349,600 Estimated costs to complete 1,330,320 Using the percentage-of-completion method and the cost-to-cost basis, how much gross proft should be reported for 2024?arrow_forward
- Morneau Contractors Inc. agreed to construct a building for $475,000 Construction commenced in 2023 and was completed in 2025 Data Pelating to the below. (Click the icon to view the contract data.) Required a. For each of the three years, determine the following amounts relating to the above contract revenue, expenses, gross profit, accounts receivable balance, and construction-in-process inventory balance b. Record the journal entries using T-accounts Requirement a For each of the three years, d decimal places, XXX% Round your final answ 2023 Revenues-current year Expenses Gross profit (loss) pages Get more help - 19 7 Contract data Costs incurred during the year Estimated costs to complete Billings during year Collections during year Estimated profit on contract S Print 2023 114,155 S 280,045 95,000 85.000 Done 2024 210 215 5 73,630 213,760 208.750 2025 130 630 166 250 181.250 DICHT UM fact are summarize X cent complete to two Check answer BOLDLEarrow_forwardIn 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: Laguna uses the completed contract method of accounting for long-term construction contracts. Calculate the amount of gross profit to be recognized in each of the three years. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred). Prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.arrow_forwardIn 2021, the westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Less: Billings Costs and profit in excess of billings Current liabilities: Answer is complete but not entirely correct. ✓ ✓ 2021 2021 $2,184,000 2022 $3,510,000 5,616,000 2,106,000 2,120,000 3,574,000 4,306,000 3,400,000 4,740,000 1,860,000 $ 2,800,000✔ 2,120,000 $ 260,000 $ 680,000arrow_forward
- Using the percentage-of-completion method and the cost-to-cost basis, prepare the journal entry to record progress billings of$1,638,800 during 2023. Using the percentage-of-completion method and the cost-st basis, prepare the journal entries to record the revenue andgross proft for 2023.arrow_forwardIn 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: Laguna uses the percentage-of-completion method of accounting for long-term construction contracts. Required: Calculate the amount of gross profit to be recognized in each of the three years. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred). Prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.arrow_forward1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forward
- In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.)arrow_forwardIn 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Answer is complete and correct. 2024 $ 2,400,000 5,600,000 2,000,000 1,800,000 2024 $ 3,000,000 $ $ 600,000 $ 2025 2026 4,500,000 $ 2,500,000 900,000 $ 300,000 2025 $ 3,600,000 2,000,000 4,000,000 3,600,000 2026 $ 2,200,000 0 4,000,000 4,600,000arrow_forwardroad was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Assume that Westgate Construction's contract with Santa Clara County does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. 2-a. In the journal below, complete the necessary journal entries for the year 2024 (credit "Cash, Materials, etc." for construction costs incurred). 2-b. In the journal below, complete the necessary journal entries for the year 2025 (credit "Cash, Materials, etc." for construction costs incurred). Cost incurred during the year. Estimated costs to complete as of year-end 2-c. In the journal below, complete the necessary journal entries for the year 2026 (credit "Cash,…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning