INTER. ACCOUNTING - CONNECT+ALEKS ACCESS
10th Edition
ISBN: 9781264770335
Author: SPICELAND
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Question
error_outline
This textbook solution is under construction.
Students have asked these similar questions
Calculate the amount of revenue to be recognized in 2020 and 2021.
Calculate the construction costs to be expensed in 2021.
Prepare the journal entry at December 31, 2021, to record long-term contract revenues, expenses, and losses for 2021.
What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021?
Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021.
Assume that Cullumber uses the zero-profit or completed-contract method. What would be the journal entry recorded on December 31, 2021?
Prepare journal entries for 2024 to record the transactions described (credit "Cash, Materials, etc." for construction costs incurred).
Using the percentage-of-completion method and the cost-to-cost basis, prepare the journal entry to record progress billings of$1,638,800 during 2023.
Using the percentage-of-completion method and the cost-st basis, prepare the journal entries to record the revenue andgross proft for 2023.
Transcribed Image Text:Crane Corp. contracted to build a bridge for $4,820,000. Construction began in 2023 and was completed in 2024. Data relating to the construction are: 2023 2024 Costs incurred $1,561,680 $1,349,600 Estimated costs to complete 1,330,320
Using the percentage-of-completion method and the cost-to-cost basis, how much gross proft should be reported for 2024?
Knowledge Booster
Similar questions
- Using the percentage-of-completion method and the cost-to-cost basis, prepare the journal entry to record progress billings of$1,638,800 during 2023. Using the percentage-of-completion method and the cost-st basis, prepare the journal entries to record the revenue andgross proft for 2023.arrow_forwardIn 2021, the westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Balance Sheet (Partial) Current assets: Accounts receivable Construction in progress 3. Complete the information required below to prepare a partial balance sheet for 2021 and 2022 showing any items related to the contract. (Do not round intermediate calculations.) Less: Billings Costs and profit in excess of billings Current liabilities: Answer is complete but not entirely correct. ✓ ✓ 2021 2021 $2,184,000 2022 $3,510,000 5,616,000 2,106,000 2,120,000 3,574,000 4,306,000 3,400,000 4,740,000 1,860,000 $ 2,800,000✔ 2,120,000 $ 260,000 $ 680,000arrow_forwardIn 2025, Sunland Construction Corp. began construction work under a 3-year contract. The contract price was $1,090,000. Sunland uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of cost incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2025, are shown below. Balance Sheet Accounts receivable Construction in process Less: Billings Costs and recognized profit in excess of billings Income Statement $16,600 $62,500 58,000 4,500 Income (before tax) on the contract recognized in 2025 (a) Your answer is correct. How much cash was collected in 2025 on this contract? (b) Portion of contract billings collected $ eTextbook and Media * Your answer is incorrect. $20,000 41400 What was the initial estimated total income before tax on this contract? Income before tax on this contract $ 4500 Attempts: 2 of 15 usedarrow_forward
- Jhun Co. recognizes construction revenues and expenses using the percentage of completion method. During 2019, a single long-term contract was started, which continued through the year 2020. Information the project follows: 2019 Account receivable on contract 100,000 Construction expense 105,000 Construction in progress 122,000 Partial billings on contract 100,000 2020 Account receivable on contract 300,000 Construction expense 192,000 Construction in progress 364,000 Partial billings on contract 420,000 Profit recognized in 2019 should be? Profit recognized in 2020 should be?arrow_forwardKoolman Construction Company began work on a contract in 2019. The contract price is 3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: Required: 1. Compute the gross profit or loss recognized in 2019 and 2020. 2. Prepare the appropriate sections of the income statement and ending balance sheet for each year.arrow_forwardWhat would be the journal entry for the following statement when converting from modified accrual to accrual accounting? The City finished a new Admin building with a final cost of $8,500,000 on June 30, 2022. Construction in progress at the beginning of the fiscal year was $6,000,000.arrow_forward
- In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Answer is complete and correct. 2024 $ 2,400,000 5,600,000 2,000,000 1,800,000 2024 $ 3,000,000 $ $ 600,000 $ 2025 2026 4,500,000 $ 2,500,000 900,000 $ 300,000 2025 $ 3,600,000 2,000,000 4,000,000 3,600,000 2026 $ 2,200,000 0 4,000,000 4,600,000arrow_forwardAt the beginning of 2021, Florida Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available: Revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Cost incurred during 2022 2,400,000 Cost incurred during 2023 Cost incurred during 2024 1,600,000 2,800,000 Compute for the reported Gross Profit of Florida using: Year 2021 2022 2023 2024 Completed Contract Method Zero Profit Method Percentage of Completion Methodarrow_forwardIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Costs incurred during the year Estimated costs to complete as of year-end Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2022 2021 $2,184,000 $3,510,000 5,616,000 2,106,000 2021 2,120,000 1,860,000 2022 . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs curred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest hole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 $2,184,000 5,616,000 2023 2023 $2,316,600 3,574,000 4,306,000…arrow_forward
- 1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forwardUsing the percentage-of-completion method and the cost-to-cost basis, prepare the journal entry to record progress billings of$1,638,800 during 2023.arrow_forwardNeed part 1, 2a, 2b, 2c please 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.2-a. In the journal below, complete the necessary journal entries for the year 2021 (credit "Various accounts" for construction costs incurred).2-b. In the journal below, complete the necessary journal entries for the year 2022 (credit "Various accounts" for construction costs incurred).2-c. In the journal below, complete the necessary journal entries for the year 2023 (credit "Various accounts" for construction costs incurred).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning