Chapter 6, Problem 4P
Summary Introduction

Interpretation:The number of containers that should be authorized for the gear replenishment system, if for instance the policy variable is decided at 5 percent owing to the unforeseen contingencies needs to be determined.

Concept Introduction:The replenishment system helps the firm in maintaining inventory flow through the supply chain by keeping resourceful order and fill rates of line item.

Blurred answer
Students have asked these similar questions
个 A fabrication cell at Spradley's Sprockets uses the pull method to supply gears to an assembly line. George Jitson is in charge of the assembly line, which requires 453 gears per day. Containers typically wait 1.2 day in the fabrication cell. Each container holds 35 gears, and one container requires 24 day in machine time. Setup times are negligible. If the policy variable for unforeseen contingencies is set at 0.03, how many containers should Jitson authorize for the gear replenishment system? Jitson should authorize containers. (Enter your response rounded up to the next whole number)
A fabrication cell at Spradley's Sprockets uses the pull method to supply gears to an assymbly line.  George Jitson is in charge of the assembly line, which requires 500 gears per day.  Containers typically wait .20 day in the fabrication cell.  Each container holds 20 gears, and one container requires 1.8 days in machine time.  Setup times are negligible. If the policy variable for unforseen contingencies is set at 5 percent, how many containers should Jitson authorize for the gear replenishment system?
A fabrication cell at Spradley’s Sprockets uses the pull method to supply gears to an assembly line. George Jitson is in charge of the assembly line, which requires 500 gears per day. Containers typically wait 0.20 day in the fabrication cell. Each container holds 20 gears, and one container requires 1.8 days in machine time. Setup times are negligible. If the policy variable for unforeseen contingencies is set at 5 percent, how many containers should Jitson authorize for the gear replenishment system?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.