a. AOA network diagram:
Explanation of Solution
Draw an Activity on Arrow (AOA) network diagram representing the project given in Table 6.2 of the book. To accomplish the network diagram, follow the following steps:-
1. Put the node numbers 1 to 9 in circles.
2. Find all of the activities that start at node 1. Draw arrows between node 1 and those finish nodes. Put the activity letter and duration estimate on the associated arrow. In this case, Draw an edge from node 1 to 2 and label it as A=2. Label A=2 means activity A has a duration of 2 days.
3. Continue drawing the project network diagram until all activities are included on the diagrams that have dependencies.
4. Label each arrow with the activity letter and estimated time. The below network diagram has 11 arrows corresponding to 11 rows in the table.
- Draw second edge from node 2 to 3 and label it as B=2...
b. All paths on the network diagram:
Explanation of Solution
To identify all the paths on the network diagram, just follow the arrows to identify distinct routes from node 1 to node 9.
To find out length of each path, just add the duration for all activities on that path.
Path No | Route | Length / Total Duration |
c. Critical path for this project
Explanation of Solution
The longest path in the network diagram is the critical path...
d. Shortest possible time needed to complete this project:
Explanation of Solution
The critical path represents the shortest time requir...

Trending nowThis is a popular solution!

Chapter 6 Solutions
Information Technology Project Management
- Activity Time (days) Predecessors Earliest Expected Completion Time (TE) Latest Expected Completion Time (TE) 1 4 2 5 1 3456782222 6 1 7 1 4 4 6 2,3 5 3 5 5,7 9 4 7 10 3 6,9 11 5 8,9,10 12 4 11 Slack Critical Path? Yes or Noarrow_forwardI would like to know about the following concepts: 1. defragmentation 2. disk management 3. hardware RAIDarrow_forwardNode.js, Express, and Nunjucks Templates?arrow_forward
- CIT244 Program Project 3 Assignment As with any assigned program, do not wait until the last minute to start. Start early in the week the program is due so you can ask questions if you get stuck Node.js and Express and Nunjucks Templates We have gotten to the good stuff. There is a program similar to this assignment given as the last example in the lecture notes for the week that discusses node static files. This program will take more time that previous assignments. There are several examples you should study first, particularly the pizza order example program available in the examples programs folder for the week discussing static files. You should study and run the pizza order program before trying this program. The pseudo-company is called Sun or Fun, which offers cheap flights from Louisville to either Miami or Vegas. Here's a video of how it should work. NOTE: You will hear or see references to Handlebars in this video. We used to use Handlebars, but it will be Nunjucks that we…arrow_forwardhow to write the expression for the outputarrow_forwardPlease answer the exercise below(C programme)arrow_forward
- I need to list and know about some local storage options available in Windows Server 2019, thank youarrow_forwardPlease answer both Exercise 1 and2(these questions are not GRADED)arrow_forwardDiscussion 1. Comment on your results. 2. Compare between the practical and theoretical results. 3. Find VB, Vc on the figure below: 3V V₁₁ R₁ B IR, R, IR, R www ΙΚΩ www www I 1.5KQ 18₁ 82002 R₁ 3.3KQ R₂ 2.2KQ E Darrow_forward
- Agile1. a. Describe it and how it differs from other SDLC approachesb. List and describe the two primary terms for the agile processc. What are the three activities in the Construction phasearrow_forwardhow are youarrow_forwardneed help with thi Next, you are going to combine everything you've learned about HTML and CSS to make a static site portfolio piece. The page should first introduce yourself. The content is up to you, but should include a variety of HTML elements, not just text. This should be followed by an online (HTML-ified) version of your CV (Resume). The following is a minimum list of requirements you should have across all your content: Both pages should start with a CSS reset (imported into your CSS, not included in your HTML) Semantic use of HTML5 sectioning elements for page structure A variety other semantic HTML elements Meaningful use of Grid, Flexbox and the Box Model as appropriate for different layout components A table An image Good use of CSS Custom Properties (variables) Non-trivial use of CSS animation Use of pseudeo elements An accessible colour palette Use of media queries The focus of this course is development, not design. However, being able to replicate a provided design…arrow_forward
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningEnhanced Discovering Computers 2017 (Shelly Cashm...Computer ScienceISBN:9781305657458Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. CampbellPublisher:Cengage LearningSystems Analysis and Design (Shelly Cashman Serie...Computer ScienceISBN:9781305494602Author:Scott Tilley, Harry J. RosenblattPublisher:Cengage Learning
- Management Of Information SecurityComputer ScienceISBN:9781337405713Author:WHITMAN, Michael.Publisher:Cengage Learning,Principles of Information Systems (MindTap Course...Computer ScienceISBN:9781285867168Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningInformation Technology Project ManagementComputer ScienceISBN:9781285452340Author:Kathy SchwalbePublisher:Cengage Learning