The graph of average individual delay versus the repair period and use this graph to discuss the effect of the expected repair time on the average delay.
Explanation of Solution
Given:
We have been given the following information:
We have been given the following information:
Total number of lanes = 3,
Mean free flow speed of the highway
Jam density
Following is the lay out of the given highway section:
Calculation:For the expected repair period of 1 hour.
We have the following formula for the determination of maximum queue length that will be formed:
Where,
Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h
Substituting the values in the following equation, we have
Themaximum queue length that will be formed is
Now, the total delay, we have the following formula
Where,
And C is the total capacity and can be found as
Now, substituting the values in the required equation, we have
The total delay is
The number of vehicles that will be affected by the incident.
To calculate the number of vehicles that will be affected by the incident can be foundusing the following formula:
Number of vehicles affected =
Substituting the values, we have
The number of vehicles that will be affected by the incident is
To calculate the average individual delay, we have the following formula:
Average individual delay
Substituting the values, we have
The average individual is
For the expected repair period of 1.5 hour.
We have the following formula for the determination of maximum queue length that will be formed:
Where,
Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h
Substituting the values in the following equation, we have
Themaximum queue length that will be formed is
Now, the total delay, we have the following formula
Where,
And C is the total capacity and can be found as
Now, substituting the values in the required equation, we have
The total delay is
The number of vehicles that will be affected by the incident.
To calculate the number of vehicles that will be affected by the incident can be found using the following formula:
Number of vehicles affected =
Substituting the values, we have
The number of vehicles that will be affected by the incident is
To calculate the average individual delay, we have the following formula:
Average individual delay
Substituting the values, we have
Theaverage individualdelay is
For the expected repair period of 2.5 hour.
We have the following formula for the determination of maximum queue length that will be formed:
Where,
Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h
Substituting the values in the following equation, we have
The maximum queue length that will be formed is
Now, the total delay, we have the following formula
Where,
And C is the total capacity and can be found as
Now, substituting the values in the required equation, we have
The total delay is
The number of vehicles that will be affected by the incident.
To calculate the number of vehicles that will be affected by the incident can be found using the following formula:
Number of vehicles affected =
Substituting the values, we have
Therefore, the number of vehicles that will be affected by the incident is
To calculate the average individual delay, we have the following formula:
Average individual delay
Substituting the values, we have
The average individualdelay is
For the expected repair period of 2.75 hour.
We have the following formula for the determination of maximum queue length that will be formed:
Where,
Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h
Substituting the values in the following equation, we have
Therefore, the maximum queue length that will be formed is
Now, the total delay, we have the following formula
Where,
And C is the total capacity and can be found as
Now, substituting the values in the required equation, we have
Therefore, the total delay is
The number of vehicles that will be affected by the incident.
To calculate the number of vehicles that will be affected by the incident can be found using the following formula:
Number of vehicles affected =
Substituting the values, we have
The number of vehicles that will be affected by the incident is
To calculate the average individual delay, we have the following formula:
Average individual delay
Substituting the values, we have
the average individual delay is
For the expected repair period of 3.0 hour.
We have the following formula for the determination of maximum queue length that will be formed:
Where,
Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h
Substituting the values in the following equation, we have
The maximum queue length that will be formed is
Now, the total delay, we have the following formula
Where,
And C is the total capacity and can be found as
Now, substituting the values in the required equation, we have
The total delay is
The number of vehicles that will be affected by the incident.
To calculate the number of vehicles that will be affected by the incident can be found using the following formula:
Number of vehicles affected =
Substituting the values, we have
The number of vehicles that will be affected by the incident is
To calculate the average individual delay, we have the following formula:
Average individual delay
Substituting the values, we have
The average individual delay is
Plot the graph of average individual delay versus the repair period is as follows:
Conclusion:
Therefore, for 1.0 hour : Themaximum queue length that will be formed is
For 1.5hour:
Themaximum queue length that will be formed is
For 2.50hour:
Themaximum queue length that will be formed is
The total delay is
The number of vehicles that will be affected by the incident is
The average individual delayis
For 2.75hour:
Themaximum queue length that will be formed is
The total delay is
The number of vehicles that will be affected by the incident is
The average individual delay is
For 3.0 hour:
Themaximum queue length that will be formed is
The total delay is
The number of vehicles that will be affected by the incident is
The average individual delay is
Want to see more full solutions like this?
Chapter 6 Solutions
Traffic And Highway Engineering
- Find the maximum distributed load can be applied to the two fixed ends beam shown below. Use Virtual work method Wu L=6marrow_forwardCalculate the collapse load (P) for the two fixed ended beam shown below. Use virtual work method P 2 m 4 m L=6marrow_forwardQuestion 1 (Approximate Method - Superposition). Using Superposition determine the displacement at C of this beam. El is constant. (Note - you must use the PE Handbook Shears, Moments and Deflection Tables. The FE handbook does not have one of these conditions) (On an exam I will make sure it is found in both the FE and the PE handbook). 60 kN 30 kN/m A C 3 m 3 m B Question 2 (Slope and Deflection - virtual work - statically determinate beam) Using virtual work determine the slope at A and the displacement at C of this beam. El is constant. Same beam as question #1arrow_forward
- Question 4 (Force Method). Determine the reaction at the supports. Assume A is a pin and B and C are rollers. El is constant. 1.5 k A A 10 ft 10 ft B C - 20 ftarrow_forwardFind the maximum load (collapse load) that can be carried by the simply supported beam shown below. P ↓ 3 m 3 marrow_forwardFind the maximum distributed load can be applied to the two fixed ends beam shown below. Wu L=6marrow_forward
- In excavation for a wall footing, the water table level was lowered from a depth of 1.0 m to a depth of 3.0 m in a clayey soil deposit. Considering that the soil has a water content of 28% when it is fully saturated, and above the water table the (dry) unit weight of the soil is 17 kN/m³. Assuming initially that all of the soil above the water table is dry, then compute the following: 1. The effective stress at a depth of 4.0 m after the lowering of the water table. Take Gs = 2.68. (Hints: w*Gs=Sr*e) 2. The increase in effective stress at a depth of 5 m. (You also need to plot the values of total vertical stress and effective vertical stress against depth before and after lowering the water table.)arrow_forwardCalculate the collapse load (P) for the two fixed ended beam shown below. P 2 m 4 m L=6marrow_forwardThe vertical stress at a point in soil is σx =400 kN/m², Txz = 50kN/m² while the horizontal stress at the same point is σ =100 kN/m², Tzx = -50kN/m². (a) Draw the Mohr circle that describes the 2D stress state at the point. (b) Find the maximum shear stress that acts at the point and its orientation angle from the horizontal plane. (c) Find the principal stress (σ₁ and σ3) that acts at the point and locate the major principal stress plane and its orientation angle from the horizontal plane (Use the pole method). (d) Determine both the normal and shear stress at a plane that orientates from the major principal stress plane with an angle of 30° (counterclockwise direction) and verify your results with the stress transformation equations.arrow_forward
- 2: A billboard 2 m high x 4 m wide is supported on each end by a pin jointed assembly (bracing not shown for simplification). Total weight of billboard is 32 kN. Given: H = 1m; Angle φ = 60⁰; q = 2.4 kPa.1. Determine the normal stress (MPa) in strut AB with crosssectional dimension 6 mm x 50 mm.2. Determine the normal stress (MPa) in strut BC with crosssectional dimension 8 mm x 40 mm.3. Determine the required diameter (mm) of pin (under double shear) to be used in A or C if the allowable shear stress of the pin is 120 MPa.arrow_forwardA total load of 900 kN is uniformly distributed over a rectangular footing of size 2 mx3 m. Find the vertical stress at a depth of 1.0 m below the footing at point C, under one corner, and D, under the center. If another footing of size 1 m × 3 m with a total load of 450 kN is constructed adjoining the previous footing, what is the vertical stress at the corner point E at the same depth due to the construction of these two footings. k 3 m 1m 2m E 3 marrow_forwardA soil profile is shown below. If a uniformly distributed load Aσ is applied at the ground surface, what is the settlement of the clay layer caused by primary consolidation if a. The clay is normally consolidated b. The clay is over-consolidated with σzc=200 kPa c. The clay is over-consolidated with σzc=150 kPa (Take Cr 0.03 and Cc = 0.15) Ao 100 kN/m² 2 m 4 m 3.5 m Sand Clay Xtry 14 kN/m³ Groundwater table Yat 18 kN/m³ Yat 19 kN/m³ Void ratio, e 0.8arrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningEngineering Fundamentals: An Introduction to Engi...Civil EngineeringISBN:9781305084766Author:Saeed MoaveniPublisher:Cengage LearningSolid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,
- Residential Construction Academy: House Wiring (M...Civil EngineeringISBN:9781285852225Author:Gregory W FletcherPublisher:Cengage Learning