Question
Book Icon
Chapter 6, Problem 15DRQ
Summary Introduction

To compare: Theequipment management strategies for product and process layouts.

Introduction:

Product layouts:

Product layout is a production system where the equipment and workstations are placed along the production and assembly lines.  A conveyor is used to move the production units along the line. Product layouts have specialized labor to perform specific functions with the help of equipments (programmed to do a specific tasks in a repetitive manner). The layout is mostly based on the processing sequence.

Process layouts:

Process layout is a production system where the equipment is placed in a system based on their functions. The production line is planned to eliminate wastes.  In certain process layouts, the machineries and work settings are not arranged as per the standardized production sequence. However, there would be an assembly having similar machineries and operational activities depending on the requirement. For example, paint department.

Blurred answer
Students have asked these similar questions
Choose a specific cars company. E.g Toyota, Volkswagen, Hyundai, Mercedes-Benz, BMW, Honda, Ford, Audi, Tesla Define a list of required machinery, equipment, workstations, offices, rest areas, materials, etc. Develop and define the location of machinery, equipment, workstations, offices, rest areas, materials. Make the distribution in the manufacturing facility the most efficient way possible. Develop a process distribution for one specific product. Explain why you consider this is the most efficient distribution for this specific manufacturing facility. demonstrate the benefits of optimizing a production line with the best distribution of its equipment and spaces. To be more productive and profitable.
Provide a Synposis of the Article
The goal of understanding personality in negotiation is to better predict behavior, such as the counterparty's acceptance or rejection of a negotiation offer. One investigation used acoustic and visual cues to predict the likely behavior of a counterparty to a proposal. The best visual cue predictor of the counterparty (55%) was whether they _____. A. tilted their head B. had their arms and legs crossed C. steepled their fingers D. tapped a pen

Chapter 6 Solutions

CONNECT F/OPERATIONS MGMT

Ch. 6.3 - Prob. 3.1RQCh. 6.3 - Prob. 3.2RQCh. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
  • Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing