Question
Chapter 5, Problem 6P
Summary Introduction
Interpretation: Bottleneck activity for the process station and whether the bottleneck station is capable enough to produce all the toys demanded.
The number of C-843 unit that can be produced.
Whether the bottleneck process will change in this condition or not.
Concept Introduction:
Bottleneck activity is the activity that takes the longest time during the whole process to complete.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following is a factor that affects service capacity planning?
A) the need to be near customers
B) the inability to store services 7
C) the degree of volatility of demand
D) the customer's willingness to wait
E) all of the above
Jefferson Company’s demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units.
Actual run time this week
6,106
minutes
Machine time available per week
8,600
minutes
Actual run rate this week
4.32
units per minute
Ideal run rate
6.00
units per minute
Defect-free output this week
11,315
units
Total output this week (including defects)
15,500
units
1. Compute the utilization rate.2. Compute the efficiency rate. 3. Compute the quality rate. 4. Compute the overall equipment effectiveness (OEE).
Winchester Hospital is a privately owned institution. The hospital is at full capacity, but the governing board would like to see an increase in revenue. They’ve tasked you, the hospital administrator, with finding ways to accomplish this. If you are able to raise revenue, the board will provide you with a significant year-end bonus. Currently, 50% of Winchester’s rooms can be converted from having one bed to having two beds, allowing for more patients to be admitted. Doctors, nurses, and other hospital staff are firmly against this move, especially because additional hiring is not planned. These stakeholders make up the vast majority of the hospital workforce. Evaluate this situation using both the utilitarianism and individualistic (ethical egoism) approaches. Define each approach and describe how each would resolve the decision. What would you expect the outcome of each decision to be? Support your conclusions with facts from the situation.
Chapter 5 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 5 - Take a process that you encounter on a daily...Ch. 5 - Prob. 2DQCh. 5 - How could the efficiency of the redesigned process...Ch. 5 - Bill’s Barbershop has two barbers available to...Ch. 5 - Melissa’s Photo Studio offers both individual...Ch. 5 - Figure 5.11 details the process flow for two types...Ch. 5 - Prob. 4PCh. 5 - Super Fun Industries manufactures four top-selling...Ch. 5 - Prob. 6PCh. 5 - Yost-Perry Industries (YPI) manufactures a mix of...
Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - A.J.’s Wildlife Emporium manufactures two unique...Ch. 5 - Cooper River Glass Works (RGW) produces four...Ch. 5 - Quick Stop Pharmacy is a small family-owned,...Ch. 5 - Use the longest work element rule to balance the...Ch. 5 - Johnson Cogs wants to set up a line to serve 60...Ch. 5 - Refer back to Problem 16. Suppose that in addition...Ch. 5 - To meet holiday demand, Penny’s Pie Shop...Ch. 5 - A paced assembly line has been devised to...Ch. 5 - Prob. 20PCh. 5 - Greg Davis, a business major at the University of...Ch. 5 - Prob. 1VCCh. 5 - Which boarding scenario among the different ones...Ch. 5 - How should Southwest evaluate the gate boarding...Ch. 5 - How will Southwest know that the bottleneck had...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Sniparrow_forwardChange information to 95,000 to install, but will increase customer traffic in the store by 12,000 customers per year. Assume a discount rate of 7%arrow_forwardThe TechGuide Company produces and sells 7,500 modular computer desks per year at a selling price of $750 each. Its current production equipment, purchased for $1,800,000 and with a 5-year useful life, is only 2 years old. It has a terminal disposal value of $0 and is depreciated on a straight-line basis. The equipment has a current disposal price of $450,000. However, the emergence of a new molding technology has led TechGuide to consider either upgrading or replacing the production equipment. The following table presents data for the two alternatives: LOADING... (Click to view the data for the two alternatives.) Read the requirements LOADING... . Requirement 1. Should TechGuide upgrade its production line or replace it? Show your calculations. Determine the total relevant costs over 3 years. (If an input field is not used in the table, leave the input field empty; do not enter a zero. Use parentheses or a minus sign for numbers to be subtracted.)…arrow_forward
- The staff training center at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 1800 employees per year. Since the training center was first put in use, the program has become more complex, so that 1400 now represents the most employees that can be trained per year. In the past year, 1350 employees were trained. Calculate the efficiency and the utilization of this system. An executive conference center has the physical ability to handle 1,100 participants. However, conference management personnel believe that only 1,000 participants can be handled effectively for most events. The last event, although forecasted to have 1,000 participants, resulted in the attendance of only 950 participants. What are the utilization and efficiency of the conference facility? . A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled maintenance of their…arrow_forwardSoutheastern Airlines's daily flight from Atlanta toCharlotte uses a Boeing 737, with all-coach seating for 120 people.In the past, the airline has priced every seat at $140 for theone-way flight. An average of 80 passengers are on each flight.The variable cost of a filled seat is $25. Aysajan Eziz, the newoperations manager, has decided to try a yield revenue approach,with seats priced at $80 for early bookings and at $190 for bookingswithin 1 week of the flight. He estimates that the airline willsell65 seats at the lower price and 35 at the higher price. Variablecost will not change. Which approach is preferable to Mr. Eziz?arrow_forwardMgt-314 (Operations Management) MCQ:arrow_forward
- Save Charles Lackey operates a bakery in Idaho Falls, Idaho Because of its excellent product and excellent location, demand has increased by 25% in the last year. On far too many occasions, customers have not been able to purchase the bread of their choice. Because of the size of the store, no new ovens can be added At a staff meeting, one employee suggested ways to load the ovens differently so that more loaves of bread can be boked at one time. This new process will require that the overs Employees are paid $8 per hour. In addition to the labor cost, Charles also has a constant utility cost per month of $550 and a per loaf ingredient cost of $0.50 loaded by hand, requiring additional manpower. This is the only production change that will be made in order to meet the increased demand. The bakery cuently makes 1,500 loaves per month Cument multifactor productivity for 640 work hours per month-loavesidolar (round your response to three decimal placesarrow_forwardA graphic design studio is considering three new computers. The first model, A, costs $5000. Model B and C cost $3000 and $1000 respectively. Each customer provides $50 of revenue and variable costs are $20/customer. a) What is the number of customers required for each model to break even? b) What is the break-even point in dollars?arrow_forwardAsaparrow_forward
- Spartan Castings must implement a manufacturing process that reduces the amount of particulates emitted into the atmosphere. Two processes have been identified that provide the same level of particulate reduction. The first process is expected to incur $350,000 of fixed cost and add $50 of variable cost to each casting Spartan produces. The second process has fixed costs of $150,000 and adds $90 of variable cost per casting.a. What is the break-even quantity beyond which the first process is more attractive?b. What is the difference in total cost if the quantity produced is 10,000?arrow_forwardThe staff training centre at a large regional hospital provides training sessions in CPR to all employees. Assume that the capacity of this training system was designed to be 2100 employees per year. Since the training centre was first put in use, the program has become more complex, so that 1500 now represents the most employees that can be trained per year. In the past year, 1350 employees were trained. a) Calculate the efficiency and the utilization of this system. b) If the number of employees who signed up for training next year is 1475, what is the efficiency and utilization rate for next year?arrow_forwardMotorking Corporation, a market leader in the production of specialized engine additives, is considering introducing a new "gas extender" product. This product is added to an automobile’s gasoline to extend mileage and reduce exhasut emissions. Motorking's manufacturing facility can produce 50,000 cases of the new product per year with a set-up cost of $100,000. The average variable cost per case would be $5. Large orders, (i.e., above 50,000 cases) will be subcontracted to a local refining company. Motorking has signed a secrecy agreement with the vendor that guards the basic process. The variable cost per case, if the new product is produced outside, is $9. Whether the product is manufactured by Motorking or by the vendor, there is a $12 per case cost for marketing and overhead. Motorking's production manager is considering three production levels for the new product: 50,000 cases, 75,000 cases, and 100,000 cases. The level of sales will depend on the state of the economy. Sales…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY