Long-term contract; revenue recognition over time; loss projected on entire project
• LO5–9
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000.
In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.
Required:
- 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
- 2. Prepare
journal entries for 2018 and 2019 to record the transactions described (credit “various accounts” for construction costs incurred). - 3. Prepare a partial
balance sheet to show the presentation of the project as of December 31, 2018 and 2019.
Requirement – 1
Contract
Contract is a written document that creates legal enforcement for buying and selling the property. It is committed by the parties to performing their obligation and enforcing their rights.
Revenue recognized point of long term contract
A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized by revenue mines cost of completion until date.
A contract does not meet the performance obligation norm. The seller cannot recognize the revenue till the project complete.
The revenue recognition principle
The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.
To calculate: The amount of revenue and gross profit or loss to be recognized in the year 2018, 2019, and 2020.
Explanation of Solution
Recognized revenue
In the year 2018:
Here,
Contract price is $8,000,000,
Actual cost to date is $2,000,000,
Total estimated cost is $6,000,000.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $2,666,667.
In the year 2019:
Here,
Contract price is $8,000,000,
Actual cost to date is $4,500,000,
Total estimated cost is $8,100,000,
Revenue recognition in 2018 is $2,666,667.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $1,777,778.
In the year 2020:
Here,
Contract price is $8,000,000,
Revenue recognition in 2018 is $2,666,667,
Revenue recognition in 2019 is $1,777,778.
Now, calculate the revenue recognition:
Hence, the calculated revenue recognition is $3,555,555.
Recognized gross profit
In the year 2018:
Here,
Revenue recognition in 2018 is $2,666,667
Actual cost to date is $2,000,000.
Now, calculate the gross profit recognition:
Hence, the calculated gross profit recognition is $666,667.
In the year 2019:
Here,
Revenue recognition in 2019 is ($100,000)
Gross profit recognition in 2018 is $666,667.
Now, calculate the gross profit recognition:
Hence, the calculated gross loss recognition is ($766,667).
In the year 2020:
Here,
Revenue recognition in 2020 is ($300,000)
Revenue recognition in 2019 is ($100,000).
Now, calculate the gross profit recognition:
Hence, the calculated gross loss recognition is ($200,000).
Working note:
Calculate the value of gross profit (in millions)
Particulars | 2018 | 2019 | 2020 | |||
Contract price | $8 | $8 | $8 | |||
Actual costs to date | $2 | $4.5 | $8.3 | |||
Estimated costs to complete | $4 | $3.6 | $0 | |||
Total estimated cost | $6 | $8.1 | $8.3 | |||
Estimated gross profit | $2 | ($0.1) | ($0.3) |
Table (1)
(1)
Requirement – 2
To record: The journal entry for the year 2018 and 2019.
Explanation of Solution
In the year 2018:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,000,000 | |||
Various accounts | $2,000,000 | |||
(To record construction cost) |
Table (2)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $2,500,000 | |||
Billings on construction contract | $2,500,000 | |||
(To record progress billings) |
Table (3)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $2,250,000 | |||
Account receivable | $2,250,000 | |||
(To record cash collection) |
Table (4)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $666,667 | |||
Cost of construction | $2,000,000 | |||
Revenue from long-term contracts | $2,666,667 | |||
(To record gross profit) |
Table (5)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
In the year 2019:
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Construction in progress | $2,500,000 | |||
Various accounts | $2,500,000 | |||
(To record construction cost) |
Table (6)
- Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
- Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Account receivable | $2,750,000 | |||
Billings on construction contract | $2,750,000 | |||
(To record progress billings) |
Table (7)
- Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
- Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cash | $2,475,000 | |||
Account receivable | $2,475,000 | |||
(To record cash collection) |
Table (8)
- Cash is an asset. There is an increase in asset value. Therefore, it is debited.
- Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
Date | Account Title and Explanation | Post Ref. | Debit | Credit |
Cost of construction (2) | $2,544,445 | |||
Revenue from long-term contracts | $1,777,778 | |||
Construction in progress | $766,667 | |||
(To record expected loss) |
Table (9)
- Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
- Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
- Construction in progress is an asset. There is a decrease in asset value. Therefore, it is credited.
Working note:
Calculate the cost of construction
Given,
Revenue recognition in 2019 is $1,777,778
Loss recognition in 2019 is $766,667.
Now, calculate the gross profit recognition:
(2)
Requirement – 3
To prepare: A partial balance sheet to show the presentation of the project as of December 31, 2018 and 2019.
Explanation of Solution
In the year ended 2018:
Balance sheet At December 31,2018 | |
Current assets | Amount |
Account receivable | $250,000 |
Cost and profit in excess of billings (3) | $166,667 |
Table (10)
Working note:
Calculate the costs and profit in excess of billings:
Given,
Profit is $2,666,667
Billing profit is $2,500,000.
Now, calculate the costs and profit in excess of billings:
(3)
In the year ended 2019:
Balance sheet At December 31,2019 | |
Current assets | Amount |
Account receivable | $525,000 |
Current liability | Amount |
Cost and profit in excess of billings (4) | $850,000 |
Table (11)
Working note:
Calculate the costs and profit in excess of billings:
Given,
Profit is $5,250,000
Billing profit is $4,400,000.
Now, calculate the costs and profit in excess of billings:
(4)
Want to see more full solutions like this?
Chapter 5 Solutions
INTERMEDIATE ACCOUNTING(LL)-W/CONNECT
- 21 Beck Construction Company began work on a new building project on January 1, 2023. The project is to be completed by December 31, 2025, for a fixed price of $131 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years Actual costs incurred in each year Estimated remaining costs to complete the project (measured atDecember 31 of each year) 2023 $ 36 million $ 72 million 2024 $ 57 million $ 57 million 2025 $ 41 million $ 0 million Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project?arrow_forward7arrow_forwardh6arrow_forward
- Required Information Problem 6-10 (Static) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2024 $ 2,400,000 5,600,000 2,000,000 1,800,000 2024 2025 Problem 6-10 (Static) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. 2026 2025 $ 3,600,000 2,000,000 Note: Do…arrow_forwardH1.arrow_forward5arrow_forward
- Hardevarrow_forwardRequired Information Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following Information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2025 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2024 2026 $ 2,490,000 5,810,000 2,030,000 $ 3,984,000 $ 2,008,600 1,826,000 в 4,444,000 3,900,000 3,526,000 4,285,000 1,815,000 Westgate recognizes revenue over time according to percentage of completion. Problem 6-10 (Algo) Part 4 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs Incurred and costs to complete Information. Note: Do not round Intermediate calculations and round your final…arrow_forward5arrow_forward
- P 6-10 Long-term ontract; venue cognition ver time .LO6-8, 06-9 In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The TODO was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Required: 2024 $2,400,000 5,600,000 2,000,000 1,800,000 Cost incurred during the year Estimated costs to complete as of year-end 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years. 2. Prepare all necessary journal entries for each of the years (credit "Cash, Materials, etc. for construction costs incurred). 3. Prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract. Indicate whether any of the amounts shown are contract assets or…arrow_forwardSM3arrow_forward3arrow_forward
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning