Concept introduction:
Profit margin:
The profit margin is the percentage charged by the seller on the sale of the goods. The difference between the sales price and the cost price of the product is known as the profit margin.
Requirement 1:
Calculate the product margin using the traditional costing system.

Answer to Problem 5.17P
The product margin for the X and P is $220,000 and $1,400,000, respectively.
Explanation of Solution
Calculate the product margin using the traditional costing system:
Traditional Costing System | |||
Product Margin | |||
Particulars | X | P | Total |
Sales (1) | $2,800,000 | $7,920,000 | $10,720,000 |
Less: Costs | |||
Direct materials | $1,440,000 | $4,240,000 | $5,680,000 |
Direct labor | $480,000 | $960,000 | $1,440,000 |
Manufacturing | $660,000 | $1,320,000 | $1,980,000 |
Product Margin | $220,000 | $1,400,000 | $1,620,000 |
Table: (1)
Thus, the product margin for the X and P is $220,000 and $1,400,000, respectively.
Working note 1:
Calculate the sales:
Particulars | X | P |
Units sold | 20,000 | 80,000 |
Sales price per unit | $140 | $99 |
Total sales | $2,800,000 | $7,920,000 |
Table: (2)
Working note 2:
Calculate the manufacturing overhead:
X:
P:
Concept introduction:
Activity rate:
The activity rate is determined by dividing the net activity cost, with the total number of activities. The calculation of the activity rate is the second step in the implementation of activity-based costing. After establishing the relationship between the overheads and the activity, the management has to ascertain the activity rate for that specific activity.
Requirement 2:
Calculate the product margin using the activity-based costing system.

Answer to Problem 5.17P
The product margin for X and P is ($12,400) and $1,731,400, respectively.
Explanation of Solution
Calculate the product margin using the activity-based costing system:
Activity-based Costing System | |||
Product Margin | |||
Particulars | X | P | Total |
Sales | $2,800,000 | $7,920,000 | $10,720,000 |
Less: Costs | |||
Direct materials | $1,440,000 | $4,240,000 | $5,680,000 |
Direct labor | $480,000 | $960,000 | $1,440,000 |
Manufacturing overhead (3) | $892,400 | $988,600 | $1,881,000 |
Product Margin | ($12,400) | $1,731,400 | $1,719,000 |
Table: (3)
Thus, the product margin for X and P is ($12,400) and $1,731,400, respectively.
Working note 3:
Calculate the manufacturing overhead:
Particulars | ManufacturingOverhead(a) | Activity | Total cost | |||
X (b) | P (c) | Total(d) | X
| P
| ||
Supporting direct labor | $783,600 | 40,000 | 80,000 | 120,000 | $261,200 | $522,400 |
Batch setups | $495,000 | 200 | 100 | 300 | $330,000 | $165,000 |
Product-sustaining | $602,400 | 1 | 1 | 2 | $301,200 | $301,200 |
Total | $892,400 | $988,600 |
Table: (4)
Concept introduction:
Activity-based costing (ABC):
Activity-based costing refers to the method of costing where the overhead cost is assigned to various products. This costing method identifies the relationship between the manufacturing overhead costs and the activities. After establishing the relationship, the indirect cost is allocated to the products.
Requirement 3:
Prepare a report stating the comparison of the traditional and activity-based cost assignments.

Answer to Problem 5.17P
Traditional Cost System | |||||
Particulars | X (a) | % (a/c) | P (b) | % (b/c) | Total (c) |
Direct materials | $1,440,000 | 25.35% | $4,240,000 | 74.65% | $5,680,000 |
Direct labor | $480,000 | 33.33% | $960,000 | 66.67% | $1,440,000 |
Manufacturing overhead | $660,000 | 33.33% | $988,600 | 66.67% | $1,980,000 |
Total cost | $2,580,000 | 28.35% | $6,520,000 | 71.65% | $9,100,000 |
Activity-based costing system | |||||
Direct materials | $1,440,000 | 25.35% | $4,240,000 | 74.65% | $5,680,000 |
Direct labor | $480,000 | 33.33% | $960,000 | 66.67% | $1,440,000 |
Supporting direct labor | $261,200 | 33.33% | $522,400 | 66.67% | $783,600 |
Batch setups | $330,000 | 66.67% | $165,000 | 33.33% | $495,000 |
Product-sustaining | $301,200 | 50.00% | $301,200 | 50.00% | $602,400 |
Total product cost | $2,812,400 | 31.25% | $6,188,600 | 68.75% | $9,001,000 |
Others | $99,000 | ||||
Total cost | $9,100,000 |
Table: (5)
- The main reason behind the difference is the allocation of the manufacturing overheads in two different methods.
Explanation of Solution
Prepare a report stating the comparison of the traditional and activity-based cost assignments:
Traditional Cost System | |||||
Particulars | X (a) | % (a/c) | P (b) | % (b/c) | Total (c) |
Direct materials | $1,440,000 | 25.35% | $4,240,000 | 74.65% | $5,680,000 |
Direct labor | $480,000 | 33.33% | $960,000 | 66.67% | $1,440,000 |
Manufacturing overhead | $660,000 | 33.33% | $988,600 | 66.67% | $1,980,000 |
Total cost | $2,580,000 | 28.35% | $6,520,000 | 71.65% | $9,100,000 |
Activity-based costing system | |||||
Direct materials | $1,440,000 | 25.35% | $4,240,000 | 74.65% | $5,680,000 |
Direct labor | $480,000 | 33.33% | $960,000 | 66.67% | $1,440,000 |
Supporting direct labor | $261,200 | 33.33% | $522,400 | 66.67% | $783,600 |
Batch setups | $330,000 | 66.67% | $165,000 | 33.33% | $495,000 |
Product-sustaining | $301,200 | 50.00% | $301,200 | 50.00% | $602,400 |
Total product cost | $2,812,400 | 31.25% | $6,188,600 | 68.75% | $9,001,000 |
Others | $99,000 | ||||
Total cost | $9,100,000 |
Table: (6)
Explain the reason behind the difference between traditional and activity-based cost assignments:
The product margin for X and P is $220,000 and $1,400,000 under the traditional costing system. The product margin for X and P is ($12,400) and $1,731,400 under activity-based costing system. The reason behind the change in the allocation of the manufacturing overhead. The overheads are allocated on the basis of the direct labor hours in the traditional costing system, and they are allocated on the basis of different cost activity under activity-based costing system.
Therefore, the main reason behind the difference is the allocation of the manufacturing overheads in two different methods.
Want to see more full solutions like this?
Chapter 5 Solutions
MANAG ACCT F/MGRS-CONNECT+PROCTORIO PLUS
- FILL ALL CELLS. NOTICE THE DROPDOWN OPTIONSarrow_forwardABF's metal spare parts manufacturing company uses the customised production method by attributing the GST to the products it produces with the help of predetermined attribution coefficients. The processing of metal parts is carried out in two production departments: the Cutting and Drilling department, and the Assembly department. The GIS attribution coefficients for the two departments are based on the operating hours of machines and the cost of direct work respectively. At the beginning of the year, the following budgets were implemented: Cutting and Drilling Department Assembly Department Direct Labor Costs (in euros) 1.320.000 2.000.000 G.B.E. (in euros) 4.800.000 2.400.000 Machinery Operating Hours 80.000 5.000 Direct Work Hours 27.000 12.000 Requested: To calculate the coefficient of attribution of the General Secretariat that will be used in each department. (4 units) To determine the production cost per unit for order 158 which…arrow_forwardPLEASE HELP. I HAVE PROVIDED THE DROPDOWN OPTIONSarrow_forward
- The difference between the balance in a company's cash account and its bank statement is documented in the __________ of the bank statement.arrow_forwardLarge corporations should report revenues on their income statements when the __________. Cash Is Received Revenues Are Earnedarrow_forwardPLEASE HELP WITH THIS PROBLEMarrow_forward
- The KLM Medical Clinic has two auxiliary departments: the Building Maintenance Department and the Energy Production Department as well as three main production departments: the Department of Paediatrics, the Department of Internal Medicine and the Department of Surgery. The CLM allocates the cost of the building maintenance department based on the area occupied by the departments in square meters and the cost of the energy department based on the days of hospitalization of patients. No distinction is made between variable and fixed cost elements. The budgeted operating figures for the previous year were as follows: Auxiliary sections Main production departments Building maintenance Energy production Pediatrics Department of Internal Medicine Surgical Estimated cost before allocation 18.000,00 8.000,00 80.000,00 50.000,00 90.000,00 Area (in sq.m) 1.000,00 4.000,00 6.000,00 18.000,00 12.000,00 Patient Hospitalization…arrow_forwardwhat is financial accounting? explain its parts and all things.arrow_forwardSystematic relationship quarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education