Long-term contract; revenue recognized over time; loss projected on entire project
• LO5–9
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows:
Required:
1. For each of the three years, prepare a schedule to compute total gross profit or loss to be recognized as a result of this contract.
2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years.
3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the
(AICPA adapted)
Want to see the full answer?
Check out a sample textbook solutionChapter 5 Solutions
SPICELAND GEN CMB LL INTRM ACCTG; CNCT
- The standard materials cost of a product is $40 per unit, based on 10 pounds of raw materials at a standard cost of $4 per pound. During January 20X9, 1,000 units of product were produced, using 10,200 pounds of raw material at a cost of $4.20 per pound. a) The standard cost for materials for January is b) The total materials variance for the month is c) The materials quantity variance is d) The materials price variance isarrow_forwardFinancial accounting questionarrow_forwardWhat is the nominal cost of trade credit if the terms are 4/10, net 45 assuming that customers forego the discount and pay on the 45th day? (365 in year)arrow_forward
- When would a variance be labeled as favorable? (a) When standard costs are less than actual costs (b) When estimated costs are greater than actual costs (c) When actual costs are less than standard costs (d) When standard costs are equal to actual costs.arrow_forwardGeneral accountingarrow_forwardWhat was juniper natural dyes gross profit percentage for this period?arrow_forward
- Please given answer general accountingarrow_forwardA fixture company manufactures products brass products in a small manufacturing facility that has 40 employees. Each employee provides 36 hours of labor per week. Determine the direct materials price variance using the information given in the table. Standard wage per hour Standard labor time per unit Standard number of lbs. of brass $14.4 20 minutes Standard price per lb. of brass Actual price per lb. of brass Actual lbs. of brass used during the weel Number of units produced during the week Actual wage per hour Actual hours for the week 1.3 lbs. $ 10.75 $ 11 12,051 lbs. 9,000 $ 14.83 1,440 hoursarrow_forwardNot use ai solution given correct answer general Accounting questionarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education