ENGINEERING ECONOMIC ENHANCED EBOOK
ENGINEERING ECONOMIC ENHANCED EBOOK
14th Edition
ISBN: 9780190931940
Author: NEWNAN
Publisher: OXF
Question
Book Icon
Chapter 5, Problem 31P
To determine

(a)

Which of the two alternatives should be selected assuming a 10% rate of interest.

Expert Solution
Check Mark

Answer to Problem 31P

The Option to be implemented is Option 2, since it results in a lower cash outflow for a period of 30 years.

Explanation of Solution

Given information:

Option 1:

Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.

Option 2:

Install one cable for 2000 lines now and one cable for 2000 lines after 10 years. Installation cost $15,000 and annual maintenance costs would be $1,000.

Rate of interest for calculation: 10%.

Based on the above information, the following tables outlines the net present value calculation of the two options.

Option 1:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $20,000.00 1 $20,000.00
1 Operating costs $1,500.00 0.9091 $1,363.64
2 Operating costs $1,500.00 0.8264 $1,239.67
3 Operating costs $1,500.00 0.7513 $1,126.97
4 Operating costs $1,500.00 0.6830 $1,024.52
5 Operating costs $1,500.00 0.6209 $931.38
5 Operating costs $1,500.00 0.6209 $931.38
6 Operating costs $1,500.00 0.5645 $846.71
7 Operating costs $1,500.00 0.5132 $769.74
8 Operating costs $1,500.00 0.4665 $699.76
9 Operating costs $1,500.00 0.4241 $636.15
10 Operating costs $1,500.00 0.3855 $578.31
11 Operating costs $1,500.00 0.3505 $525.74
12 Operating costs $1,500.00 0.3186 $477.95
13 Operating costs $1,500.00 0.2897 $434.50
14 Operating costs $1,500.00 0.2633 $395.00
15 Operating costs $1,500.00 0.2394 $359.09
16 Operating costs $1,500.00 0.2176 $326.44
17 Operating costs $1,500.00 0.1978 $296.77
18 Operating costs $1,500.00 0.1799 $269.79
19 Operating costs $1,500.00 0.1635 $245.26
20 Operating costs $1,500.00 0.1486 $222.97
21 Operating costs $1,500.00 0.1351 $202.70
22 Operating costs $1,500.00 0.1228 $184.27
23 Operating costs $1,500.00 0.1117 $167.52
24 Operating costs $1,500.00 0.1015 $152.25
25 Operating costs $1,500.00 0.0923 $138.44
26 Operating costs $1,500.00 0.0839 $125.86
27 Operating costs $1,500.00 0.0763 $114.42
28 Operating costs $1,500.00 0.0693 $104.02
29 Operating costs $1,500.00 0.0630 $94.56
30 Operating costs $1,500.00 0.0573 $85.96
Net cash outflow $35,071.75

Option 2:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $15,000.00 1 $15,000.00
1 Operating costs $1,000.00 0.9091 $909.09
2 Operating costs $1,000.00 0.8264 $826.45
3 Operating costs $1,000.00 0.7513 $751.31
4 Operating costs $1,000.00 0.6830 $683.01
5 Operating costs $1,000.00 0.6209 $620.92
5 Operating costs $1,000.00 0.6209 $620.92
6 Operating costs $1,000.00 0.5645 $564.47
7 Operating costs $1,000.00 0.5132 $513.16
8 Operating costs $1,000.00 0.4665 $466.51
9 Operating costs $1,000.00 0.4241 $424.10
10 Operating costs $1,000.00 0.3855 $385.54
10 Installation Cost $15,000.00 0.3855 $5,783.15
11 Operating costs $2,000.00 0.3505 $700.99
12 Operating costs $2,000.00 0.3186 $637.26
13 Operating costs $2,000.00 0.2897 $579.33
14 Operating costs $2,000.00 0.2633 $526.66
15 Operating costs $2,000.00 0.2394 $478.78
16 Operating costs $2,000.00 0.2176 $435.26
17 Operating costs $2,000.00 0.1978 $395.69
18 Operating costs $2,000.00 0.1799 $359.72
19 Operating costs $2,000.00 0.1635 $327.02
20 Operating costs $2,000.00 0.1486 $297.29
21 Operating costs $2,000.00 0.1351 $270.26
22 Operating costs $2,000.00 0.1228 $245.69
23 Operating costs $2,000.00 0.1117 $223.36
24 Operating costs $2,000.00 0.1015 $203.05
25 Operating costs $2,000.00 0.0923 $184.59
26 Operating costs $2,000.00 0.0839 $167.81
27 Operating costs $2,000.00 0.0763 $152.56
28 Operating costs $2,000.00 0.0693 $138.69
29 Operating costs $2,000.00 0.0630 $126.08
30 Operating costs $2,000.00 0.0573 $114.62
Net cash outflow $34,113.33

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.

Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.

Deferment of capital expenditure to Year 10 in case of Option 2 results in a lower overall cash outflow despite increase in the annual operating costs from years 11-30. This is owing to the present value factor.

Conclusion:

Hence the Option to be implemented is Option 2 since it results in lower overall cash outflow.

To determine

(b)

Which of the two alternatives should be selected.

Expert Solution
Check Mark

Answer to Problem 31P

The Option to be implemented is Option 1, since it results in a lower cash outflow for a period of 30 years.

Explanation of Solution

Given information:

Option 1:

Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.

Option 2:

Install one cable for 2000 lines now and one cable for 2000 lines after 5 years. Installation cost $15,000 and annual maintenance costs would be $1,000.

Rate of interest for calculation: 10%.

Based on the above information, the following tables outlines the net present value calculation of the two options.

Option 1:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $ 20,000.00 1.00 $ 20,000.00
1 Operating costs $ 1,500.00 0.91 $ 1,363.64
2 Operating costs $ 1,500.00 0.83 $ 1,239.67
3 Operating costs $ 1,500.00 0.75 $ 1,126.97
4 Operating costs $ 1,500.00 0.68 $ 1,024.52
5 Operating costs $ 1,500.00 0.62 $ 931.38
5 Operating costs $ 1,500.00 0.62 $ 931.38
6 Operating costs $ 1,500.00 0.56 $ 846.71
7 Operating costs $ 1,500.00 0.51 $ 769.74
8 Operating costs $ 1,500.00 0.47 $ 699.76
9 Operating costs $ 1,500.00 0.42 $ 636.15
10 Operating costs $ 1,500.00 0.39 $ 578.31
11 Operating costs $ 1,500.00 0.35 $ 525.74
12 Operating costs $ 1,500.00 0.32 $ 477.95
13 Operating costs $ 1,500.00 0.29 $ 434.50
14 Operating costs $ 1,500.00 0.26 $ 395.00
15 Operating costs $ 1,500.00 0.24 $ 359.09
16 Operating costs $ 1,500.00 0.22 $ 326.44
17 Operating costs $ 1,500.00 0.20 $ 296.77
18 Operating costs $ 1,500.00 0.18 $ 269.79
19 Operating costs $ 1,500.00 0.16 $ 245.26
20 Operating costs $ 1,500.00 0.15 $ 222.97
21 Operating costs $ 1,500.00 0.14 $ 202.70
22 Operating costs $ 1,500.00 0.12 $ 184.27
23 Operating costs $ 1,500.00 0.11 $ 167.52
24 Operating costs $ 1,500.00 0.10 $ 152.29
25 Operating costs $ 1,500.00 0.09 $ 138.44
26 Operating costs $ 1,500.00 0.08 $ 125.86
27 Operating costs $ 1,500.00 0.08 $ 114.42
28 Operating costs $ 1,500.00 0.07 $ 104.02
29 Operating costs $ 1,500.00 0.06 $ 94.56
30 Operating costs $ 1,500.00 0.06 $ 85.96
Net cash outflow 35,071.75

Option 2:

Year Particulars Cash flow Present value Factor @10% Present value
0 Installation Cost $ 15,000.00 1.00 $ 15,000.00
1 Operating costs $ 1,000.00 0.91 $ 909.09
2 Operating costs $ 1,000.00 0.83 $ 826.45
3 Operating costs $ 1,000.00 0.75 $ 751.31
4 Operating costs $ 1,000.00 0.68 $ 683.01
5 Operating costs $ 1,000.00 0.62 $ 620.92
5 Operating costs $ 1,000.00 0.62 $ 620.92
5 Installation Cost $ 15,000.00 0.62 $ 9,313.82
6 Operating costs $ 2,000.00 0.56 $ 1,128.95
7 Operating costs $ 2,000.00 0.51 $ 1,026.32
8 Operating costs $ 2,000.00 0.47 $ 933.01
9 Operating costs $ 2,000.00 0.42 $ 848.20
10 Operating costs $ 2,000.00 0.39 $ 771.09
11 Operating costs $ 2,000.00 0.35 $ 700.99
12 Operating costs $ 2,000.00 0.32 $ 637.26
13 Operating costs $ 2,000.00 0.29 $ 579.33
14 Operating costs $ 2,000.00 0.26 $ 526.66
15 Operating costs $ 2,000.00 0.24 $ 478.78
16 Operating costs $ 2,000.00 0.22 $ 435.26
17 Operating costs $ 2,000.00 0.20 $ 395.69
18 Operating costs $ 2,000.00 0.18 $ 359.72
19 Operating costs $ 2,000.00 0.16 $ 327.02
20 Operating costs $ 2,000.00 0.15 $ 297.29
21 Operating costs $ 2,000.00 0.14 $ 270.26
22 Operating costs $ 2,000.00 0.12 $ 245.69
23 Operating costs $ 2,000.00 0.11 $ 223.36
24 Operating costs $ 2,000.00 0.10 $ 203.05
25 Operating costs $ 2,000.00 0.09 $ 184.59
26 Operating costs $ 2,000.00 0.08 $ 167.81
27 Operating costs $ 2,000.00 0.08 $ 152.56
28 Operating costs $ 2,000.00 0.07 $ 138.69
29 Operating costs $ 2,000.00 0.06 $ 126.08
30 Operating costs $ 2,000.00 0.06 $ 114.62
Net cash outflow 39,997.78

Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.

In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.

Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.

Deferment of capital expenditure to Year 5 in case of Option 2 results in a higher overall cash outflow due to increase in the annual operating costs from years 6-30. This is owing to the present value factor.

Conclusion:

Hence the Option to be implemented is Option 1 since it results in lower overall cash outflow.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Problem 3 Stata Output Analysis Suppose a study investigates the causal effect of education on wages. Table 1 reports the results of an OLS regression of wages (wage per hour in dollars) on education (years in education). Table 1 Source SS df MS Number of obs = 3,017 F(1, 3015) = 298.39 Model Residual 18904467 191011981 1 18904467 3,015 63353.8909 Prob > F 0.0000 R-squared 0.0901 Adj R-squared 0.0898 Total 209916448 3,016 69600.9444 Root MSE 251.7 wage Coef. Std. Err. t P>|t| [95% Conf. Interval] education cons 29.56644 183.9342 1.711605 23.15976 17.27 0.000 7.94 0.000 26.21041 138.5237 32.92247 229.3447 a. How would you write this relationship using the Core Model? (5 points) b. What is the value for B₁, the coefficient on Education? (2 points) C. What is the standard error of ẞ₁? (2 points) d. What is the R squared for the model? (2 points) e. What is the t statistic for ₁at the 5% level of significance? (2 points) Λ f. What is the 95% confidence interval for B₁? (2 points) Λ g.…
Problem 2 Hypothesis Testing Suppose you are interested in the effect of neighborhood crime incidents on high school graduation rates. You run the following regression model: Graduation; ßo+ß₁Crime; +ɛ¿ = You would like to test whether the neighborhood crime incidents have a statistically significant effect on high school graduation rate at the 5% level of significance (α = 0.05). You estimate the model and find that B₁ = -0.04 and se (B₁) = 0.008. a. Write down the null hypothesis and alternative hypothesis. (4 points) b. Calculate thet statistic of B₁. (5 points) C. What is the critical value of thet statistic for the 5% level of significance? (2 points) d. Calculate the 95% confidence interval for the coefficient on Crime? (6 points) e. Based on your answers to the questions b, c, and d, do you reject or fail to reject the null hypothesis you defined in question a? Justify your answer. (5 points) Λ f. Isẞ₁ statistically significant at the 5% level? (3 points)
Problem 1 Endogeneity & Bias The ACT (an abbreviation of American College Testing) is a standardized test used for college admissions in the United States. Suppose you are interested in whether ACT preparation improves ACT scores. Consider the following model: ACT=B+B Preparation,+e; where Preparation measures the number of hours spent on ACT preparation and ACT is ACT scores. Each student is denoted by the subscript i. Suppose you estimate = - 21 andß₁ = 0.9. a. What is the dependent variable? What is the independent variable? (3 points) b. How do you interpret ẞ = 21 in this context? (4 points) 0 C. How do you interpretß₁ = 0.9 in this context? (4 points) 1 d. Describe a scenario which can cause the independent variable to be endogenous. (4 points)

Chapter 5 Solutions

ENGINEERING ECONOMIC ENHANCED EBOOK

Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - Prob. 10PCh. 5 - Prob. 11PCh. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Prob. 20PCh. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 26PCh. 5 - Prob. 27PCh. 5 - Prob. 28PCh. 5 - Prob. 29PCh. 5 - Prob. 31PCh. 5 - Prob. 32PCh. 5 - Prob. 33PCh. 5 - Prob. 34PCh. 5 - Prob. 35PCh. 5 - Prob. 36PCh. 5 - Prob. 37PCh. 5 - Prob. 38PCh. 5 - Prob. 39PCh. 5 - Prob. 40PCh. 5 - Prob. 41PCh. 5 - Prob. 42PCh. 5 - Prob. 43PCh. 5 - Prob. 44PCh. 5 - Prob. 45PCh. 5 - Prob. 46PCh. 5 - Prob. 47PCh. 5 - Prob. 48PCh. 5 - Prob. 49PCh. 5 - Prob. 50PCh. 5 - Prob. 51PCh. 5 - Prob. 52PCh. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Prob. 55PCh. 5 - Prob. 56PCh. 5 - Prob. 57PCh. 5 - Prob. 58PCh. 5 - Prob. 59PCh. 5 - Prob. 60PCh. 5 - Prob. 61PCh. 5 - Prob. 62PCh. 5 - Prob. 63PCh. 5 - Prob. 64PCh. 5 - Prob. 65PCh. 5 - Prob. 66PCh. 5 - Prob. 67PCh. 5 - Prob. 68PCh. 5 - Prob. 69PCh. 5 - Prob. 70PCh. 5 - Prob. 71PCh. 5 - Prob. 72PCh. 5 - Prob. 73PCh. 5 - Prob. 74PCh. 5 - Prob. 75PCh. 5 - Prob. 76PCh. 5 - Prob. 77PCh. 5 - Prob. 78PCh. 5 - Prob. 79PCh. 5 - Prob. 80PCh. 5 - Prob. 81PCh. 5 - Prob. 82PCh. 5 - Prob. 83PCh. 5 - Prob. 84PCh. 5 - Prob. 85PCh. 5 - Prob. 86PCh. 5 - Prob. 87PCh. 5 - Prob. 88PCh. 5 - Prob. 89PCh. 5 - Prob. 90PCh. 5 - Prob. 91PCh. 5 - Prob. 92PCh. 5 - Prob. 93PCh. 5 - Prob. 94PCh. 5 - Prob. 95PCh. 5 - Prob. 96PCh. 5 - Prob. 97PCh. 5 - Prob. 98PCh. 5 - Prob. 99PCh. 5 - Prob. 100PCh. 5 - Prob. 101P
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education