Question
Book Icon
Chapter 5, Problem 21P

(a):

To determine

Compare the projects based on the present worth.

(a):

Expert Solution
Check Mark

Explanation of Solution

Table -1 shows the cash flow of different projects.

Table -1

ProjectsBC
First cost (C)203,000396,000
Operating cost (MO) per year85,000119,000
Replacement cost (O) per year5,500 
Sludge hauling cost (S) per year less 37,000
Salvage value (SV)10% at C10% at C
Time period (n)510

MARR (i) is 6%.

The time period for project B should equate with project time period C. Thus, all the cash flows are repeated for other five years. The time period (n1) is 10 years and time period 2 (n2) is five years.

The present worth of project B (PWA) can be calculated as follows:

PWB=C(MO+O)((1+i)n11i(1+i)n1)+C+(C×0.1)(1+i)n2+(C×0.1)(1+i)n1=(203,000(85,000+5,500)((1+0.06)1010.06(1+0.06)10)+203,000+(203,000×0.1)(1+0.06)5+(203,000×0.1)(1+0.06)10)=(203,000(90,500)(1.79084810.06(1.790848))+203,000+20,3001.338226+20,3001.790848)=203,000(90,500)(0.7908480.107451)136,524.03+11,335.42=203,000(90,500)(7.36008)136,524.03+11,335.42=203,000666,087.24136,524.03+11,335.42=994,275.85

The present worth of project B is -$994,275.85.

The present worth of the project C (PWC) can be calculated as follows:

PWC=C(MOS)((1+i)n1i(1+i)n)+(C×0.1)(1+i)n=(396,000(119,00037,000)((1+0.06)1010.06(1+0.06)10)+(396,000×0.1)(1+0.06)10)=(396,00082,000(1.79084810.06(1.790848))+39,6001.790848)=396,00082,000(0.7908480.107451)+22,112.43=396,00082,000(7.36008)+22,112.43=396,000603,526.56+22,112.43=977,414.13

The present worth of project C is -$977,141.13. Since the present worth of project C is greater than project B, select project C.

(b):

To determine

Compare the projects based on the present worth.

(b):

Expert Solution
Check Mark

Explanation of Solution

The time period for project B should equate with project time period C. Thus, all the cash flows are repeated for other three years. The time period (n1) is eight years and time period 2 (n2) is five years.

The present worth of the project B (PWA) can be calculated as follows:

PWB=C(MO+O)((1+i)n11i(1+i)n1)+C+(C×0.1)(1+i)n2+(C×0.1)(1+i)n1=(203,000(85,000+5,500)((1+0.06)810.06(1+0.06)8)+203,000+(203,000×0.1)(1+0.06)5+(203,000×0.1)(1+0.06)8)=(203,000(90,500)(1.59384810.06(1.593848))+203,000+20,3001.338226+20,3001.593848)=203,000(90,500)(0.5938480.095631)136,524.03+12,736.4717=203,000(90,500)(6.209786)136,524.03+12,736.4717=203,000561,985.633136,524.03+12,736.4717=888,773.25

The present worth of project B is -$888,773.2513.

Time period (n) is eight years. The present worth of the project C (PWC) can be calculated as follows:

PWC=C(MOS)((1+i)n1i(1+i)n)+(C×0.1)(1+i)n=(396,000(119,00037,000)((1+0.06)810.06(1+0.06)8)+(396,000×0.1)(1+0.06)8)=(396,00082,000(1.59384810.06(1.593848))+39,6001.593848)=396,00082,000(1.59384810.06(1.593848))+24,845.5311=396,00082,000(6.209786)+24,845.5311=396,000509,202.452+24,845.5311=880,356.92

The present worth of project C is -$880.356.92. Since the present worth of project C is greater than project B, select project C.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Published in 1980, the book Free to Choose discusses how economists Milton Friedman and Rose Friedman proposed a one-sided view of the benefits of a voucher system. However, there are other economists who disagree about the potential effects of a voucher system.
The following diagram illustrates the demand and marginal revenue curves facing a monopoly in an industry with no economies or diseconomies of scale. In the short and long run, MC = ATC. a. Calculate the values of profit, consumer surplus, and deadweight loss, and illustrate these on the graph. b. Repeat the calculations in part a, but now assume the monopoly is able to practice perfect price discrimination.
The projects under the 'Build, Build, Build' program: how these projects improve connectivity and ease of doing business in the Philippines?
Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education