Chapter 48, Problem 61A
To determine

(a)

The pitch diameter of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The pitch diameter is 117 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  module=pitchdiameternumberofteeth

Calculation:

  module(m)=pitchdiameter(D)numberofteeth(N)pitchdiameter=mNpitchdiameter=18×6.5mmpitchdiameter=117mm

Conclusion:

The pitch diameter is 117 mm.

To determine

(b)

The circular pitch of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The circular pitch is 20.4204 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  Forspurgear,Circularpitch(PC)=3.1416×Pitchdiameter(D)Numberofteeth(N)

Calculation:

  Forspurgear,Circularpitch(PC)=3.1416DNPC=3.1416×11718PC=20.4204mm

Conclusion:

The circular pitch is 20.4204 mm.

To determine

(c)

The outside diameter of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The outside diameter is 130 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  Pitch(P)=Numberofteeth(N)Pitchdiameter(D)Outsidediameter(Do)=N+2P

Calculation:

  Pitch(P)=Numberofteeth(N)Pitchdiameter(D)P=18117P=0.1538Outsidediameter(Do)=N+2PDo=18+20.1538Do=130mm

Conclusion:

The outside diameter is 130 mm.

To determine

(d)

The addendum of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The addendum is 6.5 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  addendum=0.3183×Circularpitch(PC)

Calculation:

  addendum(a)=0.3183PCa=0.3183×20.4204mma=6.5mm

Conclusion:

The addendum is 6.5 mm.

To determine

(e)

The working depth of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The working depth is 13 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  Foraspurgear,Workingdepth(WD)=2.000Pitchofthegear(P)

Calculation:

  Foraspurgear,Workingdepth(WD)=2.000Pitchofthegear(P)WD=20.1538WD=13mm

Conclusion:

The working depth is 13 mm.

To determine

(f)

The tooth thickness of the spur gear.

Expert Solution
Check Mark

Answer to Problem 61A

The thickness of the tooth is 10.21 mm.

Explanation of Solution

Given:

Module (m) = 6.5mm

Number of teeth = 18

Concept Used:

  Foraspurgear,Thicknessofatooth(T)=1.5708Pitchofthegear(P)

Calculation:

  Foraspurgear,Thicknessofatooth(T)=1.5708Pitchofthegear(P)T=1.57080.1538T=10.21mm

Conclusion:

The thickness of the tooth is 10.21 mm.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Scoring: MATH 15 FILING /10 COMPARISON /10 RULER I 13 Express EMPLOYMENT PROFESSIONALS NAME: SKILLS EVALUATION TEST- Light Industrial MATH-Solve the following problems. (Feel free to use a calculator.) DATE: 1. If you were asked to load 225 boxes onto a truck, and the boxes are crated, with each crate containing nine boxes, how many crates would you need to load? 2. Imagine you live only one mile from work and you decide to walk. If you walk four miles per hour, how long will it take you to walk one mile? 3. Add 3 feet 6 inches + 8 feet 2 inches + 4 inches + 2 feet 5 inches. 4. In a grocery store, steak costs $3.85 per pound. If you buy a three-pound steak and pay for it with a $20 bill, how much change will you get? 5. Add 8 minutes 32 seconds + 37 minutes 18 seconds + 15 seconds. FILING - In the space provided, write the number of the file cabinet where the company should be filed. Example: File Cabinet #4 Elson Co. File Cabinets: 1. Aa-Bb 3. Cg-Dz 5. Ga-Hz 7. La-Md 9. Na-Oz 2. Bc-Cf…
If you were asked to load 225 boxes onto a truck, and the boxes are crated, with each crate containing nine boxes, how many crates would you need to load?
Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days) involved in the construction of a house that Habitat for Humanity is building. Activity Optimistic Most Probable Pessimistic A 6 7.0 8 B 7 8.0 9 C 7 7.5 11.5 D 7 9.0 10 E 6 7.0 9 F 3 4.0 5 (a) Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.) Activity Expected Times A B C D E F Variance (b) An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.) expected project completion time variance of projection completion time

Chapter 48 Solutions

EBK MATHEMATICS FOR MACHINE TECHNOLOGY

Knowledge Booster
Background pattern image
Advanced Math
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, advanced-math and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Mathematics For Machine Technology
Advanced Math
ISBN:9781337798310
Author:Peterson, John.
Publisher:Cengage Learning,
Text book image
Holt Mcdougal Larson Pre-algebra: Student Edition...
Algebra
ISBN:9780547587776
Author:HOLT MCDOUGAL
Publisher:HOLT MCDOUGAL
12. Searching and Sorting; Author: MIT OpenCourseWare;https://www.youtube.com/watch?v=6LOwPhPDwVc;License: Standard YouTube License, CC-BY
Algorithms and Data Structures - Full Course for Beginners from Treehouse; Author: freeCodeCamp.org;https://www.youtube.com/watch?v=8hly31xKli0;License: Standard Youtube License