Question
Book Icon
Chapter 4, Problem 6PA

a)

Summary Introduction

To determine: The cost of direct labor for the bicycle.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  1

Identification of bottleneck:

Worker 1 performs Step 1 and Step 2 with a total time of 50 seconds.

Worker 2 performs Step 3 and Step 4 with a total time of 60 seconds.

Worker 3 performs Step 5 with a time of 50 seconds.

Worker 4 performs Step 6 with a time of 45 seconds.

Worker 5 performs Step 7 with a time of 40 seconds.

Therefore, the bottleneck is Worker 2 with 60 seconds.

Calculation of cost of direct labor for the bicycle:

Cost of direct labor=Number of workers×Wage rateBottleneck time=5×1560=7560=$1.25 per bicycle

The cost of direct labor per bicycle is $1.25.

b)

Summary Introduction

To determine: The profit per hour of the company.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  2

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$1)+$200]=360-[(75+60+200)]=360-335=$25 per hour

The profit per hour is $25.

c)

Summary Introduction

To determine: The profit per hour of the company if the sourcing cost is 10% cheaper.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  3

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$0.90)+$200]=360-[(75+54+200)]=360-329=$31 per hour

The profit per hour is $31.

d)

Summary Introduction

To determine: The profit per hour of the company if the fixed cost is 10% less.

d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  4

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$1)+$180]=360-[(75+60+180)]=360-315=$45 per hour

The profit per hour is $45.

e)

Summary Introduction

To determine: The profit per hour of the company if the bottleneck time is reduced by 5 seconds per unit.

e)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  5

Calculation of profit per hour:

The bottleneck time is 55 seconds. Therefore, the flow rate is:

Flow rate=60 Minutes×60 SecondsBottleneck time=60×6055=3,60055=65.45 units per hour

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(65.45×$6)-[(5×$15)+(65.45×$1)+$200]=392.7-[(75+65.45+200)]=392.7-340.45=$52.25 per hour

The profit per hour is $52.25.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Not use ai please
The Business Development Bank of Canada. (2023). Canadian economic outlook for 2024: Shifting into neutral. https://www.bdc.ca/en/articles-tools/blog/canadian-economic-outlook-for-2024-shifting-into-neutral “Despite persistently high inflation and rising interest rates, the news was generally better than expected for the Canadian economy in 2023” (BDC Blog 2024). Discussion Question: In your view, what are the most pressing problems for Canadian companies or consumers in 2024? Explain your answer using current examples of companies or consumer concerns.
how have idividual objectives led to the current situation at TeraCog? what should Emaa do?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L