Question
Book Icon
Chapter 4, Problem 6PA

a)

Summary Introduction

To determine: The cost of direct labor for the bicycle.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  1

Identification of bottleneck:

Worker 1 performs Step 1 and Step 2 with a total time of 50 seconds.

Worker 2 performs Step 3 and Step 4 with a total time of 60 seconds.

Worker 3 performs Step 5 with a time of 50 seconds.

Worker 4 performs Step 6 with a time of 45 seconds.

Worker 5 performs Step 7 with a time of 40 seconds.

Therefore, the bottleneck is Worker 2 with 60 seconds.

Calculation of cost of direct labor for the bicycle:

Cost of direct labor=Number of workers×Wage rateBottleneck time=5×1560=7560=$1.25 per bicycle

The cost of direct labor per bicycle is $1.25.

b)

Summary Introduction

To determine: The profit per hour of the company.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  2

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$1)+$200]=360-[(75+60+200)]=360-335=$25 per hour

The profit per hour is $25.

c)

Summary Introduction

To determine: The profit per hour of the company if the sourcing cost is 10% cheaper.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  3

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$0.90)+$200]=360-[(75+54+200)]=360-329=$31 per hour

The profit per hour is $31.

d)

Summary Introduction

To determine: The profit per hour of the company if the fixed cost is 10% less.

d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  4

Calculation of profit per hour:

The bottleneck time is 60 seconds. Therefore, 60 units are produced every hour. Therefore, the flow rate is 60 units per hour.

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(60×$6)-[(5×$15)+(60×$1)+$180]=360-[(75+60+180)]=360-315=$45 per hour

The profit per hour is $45.

e)

Summary Introduction

To determine: The profit per hour of the company if the bottleneck time is reduced by 5 seconds per unit.

e)

Expert Solution
Check Mark

Explanation of Solution

Given information:

Operations Management, Chapter 4, Problem 6PA , additional homework tip  5

Calculation of profit per hour:

The bottleneck time is 55 seconds. Therefore, the flow rate is:

Flow rate=60 Minutes×60 SecondsBottleneck time=60×6055=3,60055=65.45 units per hour

Profit=Revenues-Cost=(Flow rate×Selling price)-[(Number of workers×Wage rate)+(Flow rate×Sourcing cost)+Fixed cost]=(65.45×$6)-[(5×$15)+(65.45×$1)+$200]=392.7-[(75+65.45+200)]=392.7-340.45=$52.25 per hour

The profit per hour is $52.25.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The forecast for each week of a four-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 35 20 12 Use a production lot size of 75 units and no beginning Inventory. Determine the available-to-promise (ATP) quantities for each period. Note: Leave no cells blank - be certain to enter "0" wherever required. Period ATP 1 2 3
Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 60 units. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 2 36 28 4 1 Use a production lot size of 85 units and no beginning inventory. Note: In the ATP row, enter a value of 0 (zero) in any periods where ATP should not be calculated. Leave no cells blank - be certain to enter "0" wherever required. June July 1 2 3 4 5 8 7 8 Forecast 60 60 60 60 60 60 60 60 Customer Orders 38 28 4 1 0 0 0 0 Projected On-Hand Inventory MPS ATP
Sales of tablet computers at Marika Gonzalez's electronics store in Washington, D.C., over the past 10 weeks are shown in the table below: Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 a) The forecast for weeks 2 through 10 using exponential smoothing with a = 0.50 and a week 1 initial forecast of 21.0 are (round your responses to two decimal places): Week 1 2 3 4 5 6 7 8 9 10 Demand 21 21 27 38 25 30 35 24 25 30 Forecast 21.0 21 21 24 31 28 29 32 28 26.50 b) For the forecast developed using exponential smoothing (a = 0.50 and initial forecast 21.0), the MAD = |||||sales (round your response to two decimal places).
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L