Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $8,800,000 and 2017 direct labor-hours to be 220,000.
At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017.
Laguna Model | Mission Model | |
Construction period | Feb–June 2017 | May–Oct 2017 |
Direct material costs | $106,550 | $127,450 |
Direct labor costs | $36,250 | $41,130 |
Direct labor-hours | 970 | 1,000 |
Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $8,400,000, and the actual direct labor-hours were 200,000.
- 1. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ?
Required
- 2. What are the
job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costing? - 3. Why might Atkinson Construction prefer normal costing over actual costing?
Learn your wayIncludes step-by-step video
Chapter 4 Solutions
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
Additional Business Textbook Solutions
Financial Accounting (12th Edition) (What's New in Accounting)
Foundations Of Finance
Horngren's Accounting (12th Edition)
Engineering Economy (17th Edition)
Financial Accounting, Student Value Edition (5th Edition)
Horngren's Financial & Managerial Accounting, The Financial Chapters (Book & Access Card)
- Kindly help me with accounting questionsarrow_forwardHii expert please given correct answer general Accounting questionarrow_forwardSUBJECT - GENERAL ACCOUNT Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $14,114. Of the $14,114, $8,395 was for material and $5,719 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $25,963. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of the process. Direct labor was $33,809 and factory overhead was $19,934. If the average cost method is used what would be the conversion cost per unit? a. $1.91 b. $5.31 c. $3.45 d. $1.73arrow_forward
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College