Concept explainers
List and explain the two fundamental types of competitively bid construction contracts.
Find the contract type that is mainly used for the construction of piers for supporting large suspension bridge and provide reason for the same.
Explanation of Solution
The two fundamental types of competitive bid construction contract are as follows:
1. Lump sum contract:
In this contract, a proprietor agrees to provide a fixed lump sum amount of money to the contractor for the complete execution of project.
The owner will know about the entire project cost only during the commencement of the project.
This contract type is used in small projects where the scope and responsibility of the owner and contractor are well defined.
2. Unit price contract:
This type of contract depends on the estimation of quantities of items involved in a project and their corresponding unit prices.
The contractor’s overhead and profit are incorporated in the unit price.
The resources involved in the construction project are recognized, but the total quantity of work involved in the project is unknown at the time of contract.
The unit price contract is mainly used for the construction of piers for supporting suspension bridge, as the bridge is supported by multiple units of similar piers and unit price contracts provide flexibility to the contractor to fix the price of unit pier and execute repeated work.
Want to see more full solutions like this?
- Who is responsible for contracting for subcontractor services for construction on a project? a. The owner b. The architect c. The engineer d. The constructor e. All of the abovearrow_forwardCan just a single kind of candidate system be used in a construction?arrow_forwardA bridge is to be constructed over river Indus by C&W department for which a construction firm needs to be selected. DISCUSS in your own words, whether the department should go for open competitive bidding or shall opt for pre-qualification for the selection of construction firm? Also explain the logic behind your suggestionarrow_forward
- . Describe the three types of authorities exercised in a construction contract?arrow_forwardIt is a well-known principle that the engineer should not tell the contractor how to do the work; but, if the engineer observes that the contractor’s construction methods appear to be unable to meet the specifications,what should the engineer do?arrow_forwardWhat are the concerns contractors should necessarily consider before tendering for projects?arrow_forward
- Are there new services that are derived from technologies that construction companies can take advantage of as new opportunities?arrow_forwardMany contracts require that the contractor prepare and present the construction schedule and receive the owner's approval before any contract payments are made.Explain in detail what are the three elements of the contractor 's schedule that the owner will typically be interested in?arrow_forwardEXPLAIN YOUR ANSWER COMPREHENSIVELY. Mr. Jobert commissioned you to estimate the construction of a certain structure. As Engineers, our job includes giving detailed estimate inclusive of labor and materials. If approved, the contract for building the structure will be awarded to you. However, Mr. Jobert already had a previous consultation with Prudencio, an independent foreman, who offered labor and services at a cheaper price. How will you convince Mr. Jobert to engage in your services instead of Prudencio's? Cite applicable provisions of the Code of Ethics for such situation.arrow_forward
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,