Practical Management Science, Loose-leaf Version
5th Edition
ISBN: 9781305631540
Author: WINSTON, Wayne L.; Albright, S. Christian
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 3, Problem 42P
a)
Summary Introduction
To determine: The way to reduce the total cost of producing the required drugs.
Introduction: In linear programming, unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints then it is said to be unfeasible solution.
b)
Summary Introduction
To determine: The amount that the company would pay to purchase an extra machine hours.
Introduction: In linear programming, unbounded solution would occur when the objective function is infinite. If no solution satisfied the constraints then it is said to be unfeasible solution.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Mechanical Engineering department has a student team that is designing a formula car for national competition. The time required for the team to assemble the first car is 100 hours. Their improvement (or learning rate) is 0.8, which means that as output is doubled, their time to assemble a car is reduced by 20%. Use this information to determine:
the time it will take the team to assemble the 10th car.
Create an excel spreadsheet having the following table. You must show the formula used in the excel sheets to calculate values in the columns.
Plot Number of Units vs Time (in hours) and Number of Units vs Cumulative Time (in hours) in the same plot.
N (no of Units)
Time to Produce Nth
Cumulative Time (1 to N)
1
2
3
4
5
6
7
8
9
10
green vehicule Inc. manufactures electric cars and small delivery trucks. it has just opened a new factory where the C1 car and the T1 truck can both be manufactured. to make either vehicle, processing in the assembly shop and the paint shop are required. It takes 1/40 of a day and 1/60 of a paint a truck of type T1 and a car of type C1 in the paint shop, respectively. it takes 1/50 of a day to assemble either type of vehicule in the assembly shop. A t1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicule sold
Show your step-by-step process using THE SPECIAL PURPOSE LINEAR PROGRAMMING: MODI TRANSPORTATION METHOD to solve this problem.
XYZ Incorporated has received a contract to supply gravel to three new road projects located at three different locations. Project A needs 174 truckloads, Project B needs 204 truckloads, and Project C needs 143 truckloads. The company has three gravel warehouses located in three different places. Warehouse 1 has 158 truckloads available, warehouse 2 has 184, and warehouse 3 has 179. The cost of transportation from the warehouse to the projects are: from warehouse 1 to Projects A, B, C = Php 4, Php 8, Php 8 per truckload respectively. From warehouse 2 to Projects A, B, C = Php 16, Php 24, Php 16 per truckload respectively. From warehouse 3 to Projects A, B, C = Php 8, Php 16, Php 24 per truckload respectively. The objective is to design a plan of distribution that will Minimize the cost of transportation.
Chapter 3 Solutions
Practical Management Science, Loose-leaf Version
Ch. 3.6 - Prob. 1PCh. 3.6 - Prob. 2PCh. 3.6 - Prob. 3PCh. 3.6 - Prob. 4PCh. 3.6 - Prob. 5PCh. 3.6 - Prob. 6PCh. 3.6 - Prob. 7PCh. 3.6 - Prob. 8PCh. 3.6 - Prob. 9PCh. 3.7 - Prob. 10P
Ch. 3.7 - Prob. 11PCh. 3.7 - Prob. 12PCh. 3.7 - Prob. 13PCh. 3.7 - Prob. 14PCh. 3.7 - Prob. 15PCh. 3.7 - Prob. 16PCh. 3.7 - Prob. 17PCh. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - The Pigskin Company produces footballs. Pigskin...Ch. 3.8 - Prob. 21PCh. 3.8 - Prob. 22PCh. 3.8 - Prob. 23PCh. 3.8 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Prob. 31PCh. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 34PCh. 3 - Prob. 35PCh. 3 - Prob. 36PCh. 3 - Prob. 37PCh. 3 - Prob. 38PCh. 3 - Prob. 39PCh. 3 - Prob. 40PCh. 3 - Prob. 41PCh. 3 - Prob. 42PCh. 3 - Prob. 43PCh. 3 - Prob. 44PCh. 3 - Prob. 45PCh. 3 - Prob. 46PCh. 3 - Prob. 47PCh. 3 - Prob. 48PCh. 3 - Prob. 49PCh. 3 - Prob. 50PCh. 3 - Prob. 51PCh. 3 - Prob. 52PCh. 3 - Prob. 1CCh. 3 - Prob. 2.1CCh. 3 - Prob. 2.2CCh. 3 - Prob. 2.3CCh. 3 - Prob. 2.4CCh. 3 - Prob. 2.5CCh. 3 - Prob. 2.6CCh. 3 - Prob. 2.7CCh. 3 - Prob. 2.8C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Seas Beginning sells clothing by mail order. An important question is when to strike a customer from the companys mailing list. At present, the company strikes a customer from its mailing list if a customer fails to order from six consecutive catalogs. The company wants to know whether striking a customer from its list after a customer fails to order from four consecutive catalogs results in a higher profit per customer. The following data are available: If a customer placed an order the last time she received a catalog, then there is a 20% chance she will order from the next catalog. If a customer last placed an order one catalog ago, there is a 16% chance she will order from the next catalog she receives. If a customer last placed an order two catalogs ago, there is a 12% chance she will order from the next catalog she receives. If a customer last placed an order three catalogs ago, there is an 8% chance she will order from the next catalog she receives. If a customer last placed an order four catalogs ago, there is a 4% chance she will order from the next catalog she receives. If a customer last placed an order five catalogs ago, there is a 2% chance she will order from the next catalog she receives. It costs 2 to send a catalog, and the average profit per order is 30. Assume a customer has just placed an order. To maximize expected profit per customer, would Seas Beginning make more money canceling such a customer after six nonorders or four nonorders?arrow_forwardConsider a manufacturing process depicted by the following flowchart. flowchart Station A has 3 parallel operators, A1, A2, and A3. Station C has 2 parallel operators, C1 and C2. Each unit only needs to be processed by one of the operators A1, A2 and A3. After being processed at Station B, a unit then needs to be processed by either C1 or C2. The process time of the individual operators are given as follows. A1, A2, and A3: 12 minutes B: 14 minutes C1 and C2: 6 minutes. The process initiates the production of a new unit every 18 minutes. What is the utilization of Operator C2 in percentage? Note: Provide a number without the % mark. Round your final answer to 2 decimal places if it is not a whole number.arrow_forwardShale Oil, located in the middle east, has a capacity of 1,500,000 bbl of crude oil per day. The final products fromthe refinery include three types of unleaded gasoline with different octane numbers (ON): regular with ON = 87,premium with ON = 89, and super with ON = 92. The refining process encompasses three stages: (1) a distillationtower that produces feedstock (ON = 82) at the rate of 0.2 bbl per bbl of crude oil, (2) a cracker unit that producesgasoline stock (ON = 98) by using a portion of the feedstock produced from the distillation tower at the rate of 0.5bbl per bbl of feedstock, and (3) a blender unit that blends the gasoline stock from the cracker unit and the feedstockfrom the distillation tower. The company estimates the net profit per barrel of the three types of gasoline to be $6.70,$7.20, and $8.10, respectively. The input capacity of the cracker unit is 200,000 bbl of feedstock a day. The demandlimits for regular, premium, and super gasoline are 50,000, 30,000, and…arrow_forward
- The Stratton Company produces two basic types of plastic pipe. Three resources are crucial to the output of pipe: extrusion hours, packaging hours, and a special additive to the plastic raw material. The following data represent next week’s situation. All data are expressed in units of 100 feet of pipe. Product Resource Type 1 Type 2 Resource Availability Extrusion Packaging Additive mix 4 hr 2 hr 2 lb 6 hr 2 hr 1 lb 48 hr 18 hr 16 lb The contribution to profits and overhead per 100 feet of pipe is $34 for type 1 and $40 for type 2. Formulate a linear programming model to determine how much of each type of pipe should be produced to maximize contribution to profits and to overhead, assuming that everything produced can be sold.arrow_forwardGreen Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/25 of a day and 1/75 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/50 of a day to assemble either type of vehicle in the assembly shop. AT1 truck and a C1 car yield profits of $325 and $250, respectively, per vehicle sold. The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value. The optimum solution is: Number of trucks to be produced per day = 12.50 (round your response to two decimal places). Number of cars to be produced per day = 37.50 (round your response to two decimal places). Optimal solution value =(round your response to two decimal places).arrow_forwardA company makes four products that have the following characteristics: Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 of materials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for $135 but needs $105 of materials to produce. The processing requirements for each product on each of the four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardless of how much the worker is used. Answer the following…arrow_forward
- The newly-established pediatric department of a local hospital is in need of full-time nurses who will work in 8-hour shift per day and part-time nurses who will work in 4-hour shifts per day. Each day is divided into 6 four-hours periods, which requires different number of nurses., as shown in the table below: Time Period Index Time Period Covered 7am - 11am. 11am-3pm 3pm - 7pm 7pm - 11pm 11pm-3am 3am - 7am 1 2 3 4 5 6 Required Number of Nurses 7 9 12 5 4 3 The shifts of full-time nurses can begin at the start of any of the four-hour periods. Hospital policy requires that there must be at least two full-time nurses at each time period. Also, the number of part-time nurses cannot exceed the number of full-time nurses in any time period. Full-time nurses get paid at $160 per shift, while the part-time nurses get paid at $50 per shift. Formulate a linear programming model that will determine the nursing schedule so as to minimize the total cost.arrow_forwardGreen Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/25 of a day and 1/60 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop. A T1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicle sold. The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value. Part 2 The optimum solution is: Number of trucks to be produced per day = ? enter your response herearrow_forwardGreen Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/25 of a day and 1/60 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop. A T1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicle sold. The optimum solution is: Number of trucks to be produced per day = ? (round your response to two decimal places).arrow_forward
- Three product types, Product I, Product II and Product III, require different processing intervals during production. Specifically, the following table depicts the processing time in hours for each product/process combination: Product I Process 1/ Unit Process 2/Unit Process 3/Unit Machine A 1,275 Machine B 56 Machine C 1,485 I Product II Process 1/Unit Process 2/ Unit Process 3/Unit Machine A 1,420 Machine B 64 Machine C 1,630 Product III Process 1/Unit Process 2/Unit Process 3/Unit Machine A 1,565 Machine B 76 Machine C 1,850 3. How many of each machine type is required to fulfill 54, 38 and 61 units of Product I, Product II and Product III, respectively?arrow_forwardAuthor: Leo A. Ruggle, Professor, Department of Accounting, Mankato State University Arnie Armstrong has been with Pierce Auto Parts Manufacturing Company for 23 years. Recently, he was appointed Director of Manufacturing Computer Services. In just six weeks in this new position, [he] has moved to reduce the amount of information provided to manufacturing department managers by 60 percent. He argues that excess data is distracting, unused, and expensive to provide. Willy McClean has been department manager for 12 years. During a coffee break with some of his department production supervisors, Willy is quite vocal about the change. “Who’s this guy Armstrong to tell us what data we need? He needs to be out here for a few weeks to find out what it’s like. Keep it quiet, but I’ve got a contact in Computer Services who’ll get me all the data analyses I want for just a $20 bill each month. It’s a good deal, and Armstrong will never know. How does he expect us to make good decisions about…arrow_forwardAt a manufacturing assembly line, 30 jobs arrive perhour. Each job must pass through two production stages:stage 1 and stage 2. Stage 1 takes an average of 1 minute tocomplete, and 1 worker is available to perform stage 1.After completing stage 1, the job immediately passes tostage 2. Stage 2 takes an average of 2 minutes to complete,and 2 workers are available to work on stage 2. Aftercompleting stage 2, each job is inspected. Inspection takesan average of 3 minutes, and 3 workers are available toperform inspection. After inspection, 10% of the jobs mustbe returned to stage 1, and they then repeat both stages 1and 2. After inspection, 20% of all jobs return to stage 2 andrepeat stage 2. Assume that interarrival times and servicetimes are exponential.a What is the average time a job spends in the systemfrom arrival to completion?b What percentage of the time is each worker busy?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,