1.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing
To calculate: Predetermined overhead rate
1.

Answer to Problem 1TF15
Predetermined overhead rate is $7.95
Explanation of Solution
Total manufacturing overhead cost Y
The total manufacturing overhead is $31800
Predetermined overhead rate is $7.95
2.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Manufacturing overhead applied to Job P and Q
2.

Answer to Problem 1TF15
Manufacturing overhead applied to Job P is $18,285 and Q is $13,515
Explanation of Solution
Manufacturing overhead applied to job P and Q
Particular | Job P | Job Q | |
a. | Predetermined overhead rate | $7.95 | $7.95 |
b. | Actual machine hour used | 2300 | 1700 |
Manufacturing overhead applied | $18,285 | $13,515 |
Manufacturing overhead applied to Job P is $18,285 and Q is $13,515
3.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Total
3.

Answer to Problem 1TF15
Total manufacturing cost applied to Job P
Explanation of Solution
Total manufacturing cost assigned to job P
Particular | Amount $ |
Direct materials | 13,000 |
Direct labor | 21,000 |
Manufacturing overhead | 18,285 |
Total manufacturing cost | 52,285 |
Total manufacturing cost applied to Job P is $52,285
4.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: The unit product cost for job P
4.

Answer to Problem 1TF15
The unit product cost for job P is $2614.25
Explanation of Solution
Unit product cost:
The unit product cost for job P is $2614.25
5.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Total manufacturing cost applied to Job Q
5.

Answer to Problem 1TF15
Total manufacturing cost applied to Job Q is $29,015
Explanation of Solution
Total manufacturing cost assigned to job Q
Particular | Amount $ |
Direct materials | 8,000 |
Direct labor | 7500 |
Manufacturing overhead | 13,515 |
Total manufacturing cost | 29,015 |
Total manufacturing cost applied to Job Q is $29,015
6.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: The unit product cost for job Q is $967.167
6.

Answer to Problem 1TF15
The unit product cost for job Q
Explanation of Solution
Unit product cost:
The unit product cost for job Q is $967.167
7.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Selling price per unit of job P and Job Q.
7.

Answer to Problem 1TF15
Selling price per unit of job P is $7705.65 and Job Q is $1740.90
Explanation of Solution
Selling price of Job P and Job Q
Particular | Job P ($) | Job Q ($) |
Total manufacturing cost | 52,285 | 29,015 |
Markup (80% of total manufacturing cost) | 41,828 | 23,212 |
Selling price of job 550 | 94,113 | 52,227 |
Selling price of job P is $94,113 and Q is $52,227
Selling price of P:
Selling price of Q:
Selling price per unit of job P is $7705.65 and Job Q is $1740.90
8.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Cost of goods sold.
8.

Answer to Problem 1TF15
Cost of goods sold is $81,300
Explanation of Solution
Particular | Amount $ |
Manufacturing cost of Job P | 52,285 |
Manufacturing cost of Job Q | 29,015 |
Cost of goods sold | 81,300 |
Thus, Cost of goods sold is $81,300
9.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Predetermined overhead rate in the molding department.
9.

Answer to Problem 1TF15
Predetermined overhead rate in the molding department is $12.20
Explanation of Solution
Total manufacturing overhead cost Y
The total manufacturing overhead for molding is $13,500
Predetermined overhead rate in the molding department is $5.40
For fabrication department:
Total manufacturing overhead cost Y
The total manufacturing overhead for molding is $18,300
Predetermined overhead rate in the molding department is $12.20
10.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Manufacturing overhead applied to Job P and Q
10.

Answer to Problem 1TF15
Manufacturing overhead applied to Job P is $9180 and Q is $4320
Explanation of Solution
Manufacturing overhead applied to job P and Q from molding department
Particular | Job P | Job Q | |
a. | Predetermined overhead rate | $5.40 | $5.40 |
b. | Actual machine hour used | 2700 | 800 |
Manufacturing overhead applied | $9180 | $4320 |
Manufacturing overhead applied to Job P is $9180 and Q is $4320
11.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Manufacturing overhead applied to Job P and Q
11.

Answer to Problem 1TF15
Manufacturing overhead applied to Job P is $7320 and Q is $$10,980
Explanation of Solution
Manufacturing overhead applied to job P and Q from fabrication
Particular | Job P | Job Q | |
a. | Predetermined overhead rate | $12.20 | $12.20 |
b. | Actual machine hour used | 600 | 900 |
Manufacturing overhead applied | $7320 | $10980 |
Manufacturing overhead applied to Job P is $7320 and Q is $$10,980
12.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Unit product
12.

Answer to Problem 1TF15
Unit product cost job P is $2,525
Explanation of Solution
Unit product cost of job P
Particular | Amount $ |
Direct materials | 13000 |
Direct labor | 21000 |
Manufacturing overhead | |
Molding department | 9180 |
Fabrication department | 7320 |
Total manufacturing cost | 50500 |
Number of units | 20 |
Unit product cost | 2525 |
Unit product cost job P is $2,525
13.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Unit product cost job Q
13.

Answer to Problem 1TF15
Unit product cost job Q is $1027
Explanation of Solution
Unit product cost of job Q
Particular | Amount $ |
Direct materials | 8000 |
Direct labor | 7500 |
Manufacturing overhead | |
Molding department | 4320 |
Fabrication department | 10980 |
Total manufacturing cost | 30800 |
Number of units | 39 |
Unit product cost | 1027 |
Unit product cost job Q is $1027
14.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Selling price for Job P and Job Q
14.

Answer to Problem 1TF15
Selling price for Job P is $4545 and Job Q is $1848
Explanation of Solution
Selling price of job P and Q
Particular | Job P $ | Job Q $ |
Total manufacturing cost | 50,500 | 30,800 |
Markup (80% of Total manufacturing cost) | 40,400 | 24,640 |
Selling price | 90,900 | 55,440 |
Selling price for Job P is $90,900 and Job Q is $55,440
Selling price per unit
Particular | Job P $ | Job Q $ |
Selling price | 90,900 | 55,440 |
Number of units | 20 | 30 |
Selling price per unit | 4545 | 1848 |
Selling price for Job P is $4545 and Job Q is $1848
15.
Introduction: Job costing is a technique of determine the cost of a manufacturing job rather than the process of the job. Manufacturing overhead is applied to product or job order is determined as predetermined overhead.
To calculate: Cost of goods sold.
15.

Answer to Problem 1TF15
Cost of goods sold is 81,300
Explanation of Solution
Cost of goods sold
Particular | Amount $ |
Manufacturing cost of job P | 50,500 |
Manufacturing cost of job Q | 30,800 |
Cost of goods sold | 81,300 |
Cost of goods sold is 81,300
Want to see more full solutions like this?
Chapter 3 Solutions
MANAG ACCT F/MGRS-CONNECT+PROCTORIO PLUS
- I need help with this problem and accounting questionarrow_forwardJackson's Automotive has total assets of $300,000, a debt-equity ratio of 0.50, and net income of $24,000. What is the return on equity? A) 8.70 percent B) 9.50 percent C) 12.80 percent D) 11.30 percent E) 10.20 percentarrow_forwardProvide correct solution and accountingarrow_forward
- I want the correct answer with accounting questionarrow_forwardDo fast answer of this accounting questionsarrow_forwardWhich of the following is the most appropriate way to display liabilities on the balance sheet? a. alphabetically by payee b. relative likelihood of payment c. nearness to maturity d. All of these answer choices are correct.arrow_forward
- Can you help me with accounting questionsarrow_forwardFor which of the following would year-end accrual of a current liability be optional? a. Current portion of a long-term lease obligation that comes due next year b. A declared property dividend c. Sick pay benefits that accumulate but do not vest d. Short-term debt that is being refinanced on a long-term basisarrow_forwardQuick answer of this accounting questionsarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education





