State what minimum-size service is needed for a single family dwelling and also provide the NEC Code that states it.
Expert Solution & Answer

Answer to Problem 1R
The required minimum-size main service is 100 amperes and the Code is NEC 230.79(C).
Explanation of Solution
Discussion:
The National Electrical Code committee develops NEC – the standard electrical code. The main objective for the origin of the code is to protect and safeguard the person and elements from electrical hazards.
For a one family dwelling, according to National Electric Code NEC 230.79(C), the required minimum-size service is 100 amperes.
Conclusion:
Thus, the required minimum-size main service is 100 amperes and the Code is NEC 230.79(C).
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Q3a [3 points] Simplify the following Boolean function using K-map:
f= (0,2,8,9,10,12) & don't care X= (1,7,14)
Put each cell number in the cell left upper corner.
Put 1, O or X inside each cell.
Circle your groups
Write the simplified function f in terms of x, y, z and w
ESM
MZ
f=
Q3b [2 point] Design the above simplified Boolean function f after k-map using
iCircuit then post your design screenshot here:
Q1a [2 points] Convert the binary into octal and hexadecimal?
(10101111101)2 = (
)2 = (
)8
(10101111101) = (
)2 = (
)16
Q1b [2 points] Convert the decimal number 91.125 into binary?
91/2 =
91.25=(
)2
0.125x2 =
Q1c [1 point] Convert (101110), into decimal?
Q2 [5 points] Given the following Truth Table:
f
m
X
M
0
0
0
0
1
1
0
0
1
1
2
0
1
0
1
3
0
1
1
0
4
1
0
0
1
5
1
10
1
0
6
1
1
0
1
7
1
1
1
1
[1 point] Find the Boolean Function f in Minterms form:
f=m(
[1 point] Find the Boolean Function f in terms of x, y and z:
f=
[3 point] Simplify the above Boolean Function f in the sum form using k-map:
Put each cell number in the cell left upper corner.
Put 1's or 0's in each cell
Circle any group of 4 ones, if not, circle any group of 2 ones
Write the simplified function f in terms of x, y and z
N
Chapter 29 Solutions
Electrical Wiring Residential
Ch. 29 - Prob. 1RCh. 29 - a. What is the unit load per ft2 for the general...Ch. 29 - a. What is the ampere rating of the circuits that...Ch. 29 - Why is the air-conditioning load for this...Ch. 29 - What demand factor may be applied when four or...Ch. 29 - What load may be used for an electric range rated...Ch. 29 - What is the calculated load for an electric range...Ch. 29 - What is the calculated load when fixed electric...Ch. 29 - On what basis is the neutral conductor of a...Ch. 29 - Why is it permissible to omit an electric space...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.Similar questions
- Q4) A: Derive with the aid of diagrams the critical clearing angle for synchronous generator connected to infinite bus bar through parallel transmission line when fault occurs at the sending end of the lines.arrow_forwardQ3) A:A 60 Hz, 4 pole turbo-generator rated 10 MVA., 20 KV has stored energy in the rotor at synchronous speed of 90 MJ. (a) Find. M the anguler momentum. (b)If the generator supply 10 MW load at synchronous speed, find rotor acceleration in degrees/sec.² and in rpm/sec if the rotor drop to 5MW. (c) If the rotor acceleration calculated in part (b) is maintained for 12 cycles, find the change in torque angle and rotor speed in rpm at the end of this period.arrow_forwardChat gpt responses and ai responses are reported immediately reported please solve this question step by step handwritten solution thanksarrow_forward
- Q1. The three-phase half-wave converter in Figure shown is operated from a three phase Y-connected supply. Sketch the output voltages appeared at the load for firing angle 15°. a ia = is ΔΤ Vbn an b ib Ven 1T1 vi₁ = Ia T3 Ts T4 * T6 ΔΙ iT4 Load Highly inductive load On T5, T6 T6, T1 T1, T2 FLEC T2, T3 T3, T4 T4, T5 ཅ V 0 V. T₁₂ Ts T5, T6 wtarrow_forwardChat gpt responses and ai responses are reported immediately as im here paying my own money for expert solutions other than that please solve this question step by step handwritten solution thanks for understandingarrow_forwardA 4-cell reuse cellular system is being rolled out into an operation area and you are the engineer taking charge of this project. The subscriber density for the operation area is 600 people per km2. The average traffic load generated per subscriber is 0.2 Er. You are required to deploy 8 clusters of cells in the operation area and provide a Grade of Service of 0.5% to the subscribers using the blocked calls cleared model. You found out that the total number of trunk channels available to the system is 140. Assuming that fixed channel assignment is used, compute: a) The traffic load that can be offered to the operation area. b) The size of the operation area (in km2) that can be supported by the system. c) The proposed cell area and radius, based on the operation area determined in part (b). Having successfully implemented the first system above, you are now tasked to implement another system. The requirement is that, this second system must have a cluster size of 7 and provides a…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK ELECTRICAL WIRING RESIDENTIALElectrical EngineeringISBN:9781337516549Author:SimmonsPublisher:CENGAGE LEARNING - CONSIGNMENT

EBK ELECTRICAL WIRING RESIDENTIAL
Electrical Engineering
ISBN:9781337516549
Author:Simmons
Publisher:CENGAGE LEARNING - CONSIGNMENT