Financial Management: Theory & Practice
Financial Management: Theory & Practice
16th Edition
ISBN: 9781337909730
Author: Brigham
Publisher: Cengage
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 26, Problem 9SP

a.

Summary Introduction

To determine: Expected present value, NPV and the coefficient of variation of the present value.

a.

Expert Solution
Check Mark

Explanation of Solution

Table that shows the calculation of the expected present values of the cash flow is as follows:

ConditionProbabilityCash Flows ($)Present value ($)
Good30%92.70
Medium40%41.60
Bad30%-1-0.30
Expected present value  4

Table (1)

Table that shows calculation of the Net present value is as follows:

ParticularsCash FlowPresent value factorPresent value
Initial Cost (A)414
Cash Flows: (B)   
Year 140.8933.572
Year 240.7973.188
Year 340.7112.844
NPV (A)(B)  0.396

Table (2)

b.

Summary Introduction

To decide: If the project should be accepted with the scrap value of $6 million and cash flow in first year only.

b.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the NPV with current scenario is as follows:

CostProbabilityFuture cash flowsNPVProbability×NPV
  1 ($)2 ($)3 ($)  
-$1030%99911.623.48
40%444-0.39-0.16
30%5  -5.54-1.66
Expected NPV of future Cash flows     1.67

Table (3)

With the abandonment factor, the expected NPV becomes positive but NPV of medium is negative but higher than the NPV of the medium factor if the project will be abandoned in the year 1 itself.

c.

Summary Introduction

Estimate: The value of the project.

c.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the Expected NPV is as follows:

Cost Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
-1030%999999278.10
40%444000-0.39-0.16
30%-1-1-1000-12.40-3.72
Expected NPV       4.22

Table (4)

Table that shows calculation of expected NPV after the implementation of additional project is as follows:

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
 30%00-10000-8.40-2.52
40%00000000
30%00000000
Expected NPV       -2.52

Table (5)

Total of the NPV of the future operating cash flows and NPV after the implementation of additional project is $1.70. 

Hence, as with the additional project the NPV gets positive, therefore, the project with additional projects should be accepted.

d.

Summary Introduction

Estimate: The value of the project if it is delayed for one year.

d.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of expected NPV of future cash flows with risk-free rate of 6% and WACC of 12% is as follows:

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)  
  Cost     
 30% 99921.626.48
40% 00000
30% 00000
Expected NPV     6.48

Table (6)

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)  
  Cost     
 30% 000-9.43-2.83
40% 00000
30% 00000
Expected NPV     -2.83

Table (7)

Total of both the expected NPV is $3.65, which is positive; hence, the project should be accepted without any delaying 1 year.

e.

Summary Introduction

Estimate: The value of the growth option using Black-Scholes model.

e.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the expected NPV is as follows:

Cost Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
 30%00099915.394.62
40%0004446.842.74
30%000-1-1-1-1.71-0.51
Expected NPV       6.84

Table (8)

Formula to calculate total value is as follows:

V=P[N(d1)]XerRFt[N(d2)]

Substituting the equation with $6.84 for P, 0.56 for N(d1), 0.26 for N(d2) and $10.00 for X to calculate value of growth option.

V=P[N(d1)]XerRFt[N(d2)]=$6.84(0.56)$10e0.06×3(0.26)=$1.71

Formula to calculate total value is as follows:

Total Value=Value of original project+Value of growth option

Substituting the Equation with -$0.39 for the value of original project and $1.71 for the value of growth option to calculate total value.

Total Value=$0.39+$1.71=$1.31

Hence, the project should be accepted even if the value of original project is negative; as the total value with the growth option is greater than 0.

Working Note:

d1={In(PX)+[rRF+σ22]t}σ(t12)=0.160

d2=d1σ(t12)=0.65

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Your firm is considering a project that will cost $4.719 million up front, generate cash flows of $3.55 million per year for 3 years, and then have a cleanup and shutdown cost of $5.96 million in the fourth year. a. How many IRRS does this project have? b. Create an NPV profile for this project (plot the NPV as a function of the discount rate-see the appendix). (NOTE: students will solve this question part using Excel only. A student response is not included in MyFinanceLab). c. Given a cost of capital of 9.9% should this project be accepted? a. The project has IRRS. (Select from the drop-down menu.) 2 3 4
Perform a financial analysis for an IT Project which requires an initial investment of $32,000, but it is expected to generate revenues of S10,000, $20,000 and $15,000 for the first, second and third years respectively. The target rate of return is 12%. Write the formula and calculate the Net Present Value (NPV). In addition, Justify your result. (For this question Write the answer on the paper and take photo and upload OR Type in the MS Word document and upload the file) tach File Browse My Computer
Suppose you have a project that will cost $800,000 last for ten years. The cash flows for each year have an expected value of $175,000 with a standard deviation of $20,000. The cost of capital is 10%. Use a Monte Carlo simulation with 1,000 replications to evaluate this project using the NPV and IRR approaches. USE EXCEL AND EXPLAIN EACH STEP
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License