Question
Book Icon
Chapter 26, Problem 9SP

a.

Summary Introduction

To determine: Expected present value, NPV and the coefficient of variation of the present value.

a.

Expert Solution
Check Mark

Explanation of Solution

Table that shows the calculation of the expected present values of the cash flow is as follows:

ConditionProbabilityCash Flows ($)Present value ($)
Good30%92.70
Medium40%41.60
Bad30%-1-0.30
Expected present value  4

Table (1)

Table that shows calculation of the Net present value is as follows:

ParticularsCash FlowPresent value factorPresent value
Initial Cost (A)414
Cash Flows: (B)   
Year 140.8933.572
Year 240.7973.188
Year 340.7112.844
NPV (A)(B)  0.396

Table (2)

b.

Summary Introduction

To decide: If the project should be accepted with the scrap value of $6 million and cash flow in first year only.

b.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the NPV with current scenario is as follows:

CostProbabilityFuture cash flowsNPVProbability×NPV
  1 ($)2 ($)3 ($)  
-$1030%99911.623.48
40%444-0.39-0.16
30%5  -5.54-1.66
Expected NPV of future Cash flows     1.67

Table (3)

With the abandonment factor, the expected NPV becomes positive but NPV of medium is negative but higher than the NPV of the medium factor if the project will be abandoned in the year 1 itself.

c.

Summary Introduction

Estimate: The value of the project.

c.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the Expected NPV is as follows:

Cost Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
-1030%999999278.10
40%444000-0.39-0.16
30%-1-1-1000-12.40-3.72
Expected NPV       4.22

Table (4)

Table that shows calculation of expected NPV after the implementation of additional project is as follows:

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
 30%00-10000-8.40-2.52
40%00000000
30%00000000
Expected NPV       -2.52

Table (5)

Total of the NPV of the future operating cash flows and NPV after the implementation of additional project is $1.70. 

Hence, as with the additional project the NPV gets positive, therefore, the project with additional projects should be accepted.

d.

Summary Introduction

Estimate: The value of the project if it is delayed for one year.

d.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of expected NPV of future cash flows with risk-free rate of 6% and WACC of 12% is as follows:

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)  
  Cost     
 30% 99921.626.48
40% 00000
30% 00000
Expected NPV     6.48

Table (6)

  Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)  
  Cost     
 30% 000-9.43-2.83
40% 00000
30% 00000
Expected NPV     -2.83

Table (7)

Total of both the expected NPV is $3.65, which is positive; hence, the project should be accepted without any delaying 1 year.

e.

Summary Introduction

Estimate: The value of the growth option using Black-Scholes model.

e.

Expert Solution
Check Mark

Explanation of Solution

Table that shows calculation of the expected NPV is as follows:

Cost Future operating cash flowsNPV ($)Probability×NPV ($)
0Probability1 ($)2 ($)3 ($)4 ($)5 ($)6 ($)  
 30%00099915.394.62
40%0004446.842.74
30%000-1-1-1-1.71-0.51
Expected NPV       6.84

Table (8)

Formula to calculate total value is as follows:

V=P[N(d1)]XerRFt[N(d2)]

Substituting the equation with $6.84 for P, 0.56 for N(d1), 0.26 for N(d2) and $10.00 for X to calculate value of growth option.

V=P[N(d1)]XerRFt[N(d2)]=$6.84(0.56)$10e0.06×3(0.26)=$1.71

Formula to calculate total value is as follows:

Total Value=Value of original project+Value of growth option

Substituting the Equation with -$0.39 for the value of original project and $1.71 for the value of growth option to calculate total value.

Total Value=$0.39+$1.71=$1.31

Hence, the project should be accepted even if the value of original project is negative; as the total value with the growth option is greater than 0.

Working Note:

d1={In(PX)+[rRF+σ22]t}σ(t12)=0.160

d2=d1σ(t12)=0.65

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A. What is the amount of the annuity purchase required if you wish to receive a fixed payment of $200,000 for 20 years? Assume that the annuity will earn 10 percent per year.B. Calculate the annual cash flows (annuity payments) from a fixed-payment annuity if the present value of the 20-year annuity is $1 million and the annuity earns a guaranteed annual return of 10 percent. The payments are to begin at the end of the current year.C. Calculate the annual cash flows (annuity payments) from a fixed-payment annuity if the present value of the 20-year annuity is $1 million and the annuity earns a guaranteed annual return of 10 percent. The payments are to begin at the end of five years. I need help solving question C on a financial calculator.
John wants to buy a property for $105,000 and wants an 80 percent loan for $84,000. A lenderindicates that a fully amortizing loan can be obtained for 30 years (360 months) at 6 percentinterest; however, a loan fee of $3,500 will also be necessary for John to obtain the loan.a. How much will the lender actually disburse?b. What is the APR for the borrower, assuming that the mortgage is paid off after 30 years (fullterm)?c. If John pays off the loan after five years, what is the effective interest rate? Why is it differ-ent from the effective interest rate in (b)?d. Assume the lender also imposes a prepayment penalty of 2 percent of the outstanding loanbalance if the loan is repaid within eight years of closing. If John repays the loan after fiveyears with the prepayment penalty, what is the effective interest rate?
It is now January 1. You plan to make a total of 5 deposits of $500 each, one every 6 months, with the first payment being made today. The bank pays a nominal interest rate of 14% but uses semiannual compounding. You plan to leave the money in the bank for 10 years. Round your answers to the nearest cent. 1. How much will be in your account after 10 years? 2. You must make a payment of $1,280.02 in 10 years. To get the money for this payment, you will make five equal deposits, beginning today and for the following 4 quarters, in a bank that pays a nominal interest rate of 14% with quarterly compounding. How large must each of the five payments be?
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License