Concept explainers
Concept Introduction:
Payback Period:
Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual
NPV:
Requirement-1:
To Calculate:
Payback period for the project

Answer to Problem 5APSA
Payback period for the project is 3.8 years
Explanation of Solution
Payback period for the project is calculated as follows;
Accumulated Cash Flows | ||
Period 1 | $47,000 | $ 47,000 |
Period 2 | $52,000 | $ 99,000 |
Period 3 | $75,000 | $ 174,000 |
Period 4 | $94,000 | $ 268,000 |
Period 5 | $ 125,000 | $ 393,000 |
Payback Period = 3 Years + (250000-174000)/94000 = | 3.8 Years |
Concept Introduction:
Payback Period:
Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:
NPV:
Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:
Requirement-2:
To Calculate:
Breakeven time for the investment

Answer to Problem 5APSA
Breakeven time for the investment is 4.6 Years
Explanation of Solution
Breakeven time for the investment is calculated as follows:
Cash Flows | PV of $1 (10%) | PV | Accumulated PV | |
A | B | C=A*B | ||
Period 1 | $47,000 | 0.9091 | $ 42,727.70 | $ 42,727.70 |
Period 2 | $52,000 | 0.8264 | $ 42,972.80 | $ 85,700.50 |
Period 3 | $75,000 | 0.7513 | $ 56,347.50 | $ 142,048.00 |
Period 4 | $94,000 | 0.6830 | $ 64,202.00 | $ 206,250.00 |
Period 5 | $ 125,000 | 0.6209 | $ 77,612.50 | $ 283,862.50 |
Breakeven Time = 4 Years +(250000-206250)/77612.5 = | 4.6 Years |
Concept Introduction:
Payback Period:
Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:
NPV:
Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:
Requirement-3:
To Calculate:
The Net Present Value of the investment

Answer to Problem 5APSA
The Net Present Value of the investment is $33,862.50
Explanation of Solution
The Net Present Value of the investment is calculated as follows:
Cash Flows | PV of $1 (10%) | PV | |
A | B | C=A*B | |
Period 1 | $47,000 | 0.9091 | $ 42,727.70 |
Period 2 | $52,000 | 0.8264 | $ 42,972.80 |
Period 3 | $75,000 | 0.7513 | $ 56,347.50 |
Period 4 | $94,000 | 0.6830 | $ 64,202.00 |
Period 5 | $ 125,000 | 0.6209 | $ 77,612.50 |
Total Present value | $ 283,862.50 | ||
Less: Initial investment | $ (250,000.00) | ||
Net Present value | $ 33,862.50 |
Concept Introduction:
Payback Period:
Payback period is the period in which the project recovers its initial cost of the investment. It can be calculated by dividing the initial investment by the annual cash inflow from the project. The formula to calculate the Payback period is as follows:
NPV:
Net present value (NPV) is the method to evaluate the project feasibility. This method calculates the present value of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:
Requirement-4:
If the management should invest in the project

Answer to Problem 5APSA
Yes, the management should invest in the project.
Explanation of Solution
The Net Present Value of the investment is calculated as follows:
Cash Flows | PV of $1 (10%) | PV | |
A | B | C=A*B | |
Period 1 | $47,000 | 0.9091 | $ 42,727.70 |
Period 2 | $52,000 | 0.8264 | $ 42,972.80 |
Period 3 | $75,000 | 0.7513 | $ 56,347.50 |
Period 4 | $94,000 | 0.6830 | $ 64,202.00 |
Period 5 | $ 125,000 | 0.6209 | $ 77,612.50 |
Total Present value | $ 283,862.50 | ||
Less: Initial investment | $ (250,000.00) | ||
Net Present value | $ 33,862.50 |
The Net Present Value of the investment is $33,862.50; hence the management should invest in the project.
Want to see more full solutions like this?
Chapter 26 Solutions
FUNDAMENTAL ACCOUNTING PRINCIPLES
- Choice best answer general accountingarrow_forwardKidman Manufacturing incurred the following costs in March: direct materials $142,000, direct labor $95,000, factory rent $28,000, factory utilities $12,000, factory supervisor salary $18,000, and administrative expenses $63,000. What is the total manufacturing overhead cost for March?arrow_forwardaccounting questionarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education