Cash Payback Period, Net Present Value Method, and Analysis Elite Apparel Inc. is considering two investment projects. The estimated net cash flows from each project are as follows: Year Plant Expansion Retail Store Expansion 1 $162,000   $135,000   2 132,000   159,000   3 114,000   109,000   4 103,000   76,000   5 33,000   65,000   Total $544,000   $544,000     Each project requires an investment of $294,000. A rate of 20% has been selected for the net present value analysis. Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 2 0.890 0.826 0.797 0.756 0.694 3 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 5 0.747 0.621 0.567 0.497 0.402 6 0.705 0.564 0.507 0.432 0.335 7 0.665 0.513 0.452 0.376 0.279 8 0.627 0.467 0.404 0.327 0.233 9 0.592 0.424 0.361 0.284 0.194 10 0.558 0.386 0.322 0.247 0.162 Required: 1a.  Compute the cash payback period for each project.   1b.  Compute the net present value. Use the present value of $1 table above. If required, round to the nearest dollar.

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
100%

Cash Payback Period, Net Present Value Method, and Analysis

Elite Apparel Inc. is considering two investment projects. The estimated net cash flows from each project are as follows:

Year Plant Expansion Retail Store Expansion
1 $162,000   $135,000  
2 132,000   159,000  
3 114,000   109,000  
4 103,000   76,000  
5 33,000   65,000  
Total $544,000   $544,000  

 

Each project requires an investment of $294,000. A rate of 20% has been selected for the net present value analysis.

Present Value of $1 at Compound Interest
Year 6% 10% 12% 15% 20%
1 0.943 0.909 0.893 0.870 0.833
2 0.890 0.826 0.797 0.756 0.694
3 0.840 0.751 0.712 0.658 0.579
4 0.792 0.683 0.636 0.572 0.482
5 0.747 0.621 0.567 0.497 0.402
6 0.705 0.564 0.507 0.432 0.335
7 0.665 0.513 0.452 0.376 0.279
8 0.627 0.467 0.404 0.327 0.233
9 0.592 0.424 0.361 0.284 0.194
10 0.558 0.386 0.322 0.247 0.162

Required:

1a.  Compute the cash payback period for each project.

 

1b.  Compute the net present value. Use the present value of $1 table above. If required, round to the nearest dollar.

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education