Concept explainers
a.
Prepare a schedule showing the estimated increase in annual net income from the planned manufactured and sale of toys.
a.

Explanation of Solution
Capital budgeting:
Capital budgeting is a process by which the management can plan and evaluate the investment proposal of plant assets.
Prepare a schedule showing the estimated increase in annual net income from the planned manufactured and sale of toys as follows:
Company M | ||
Schedule of Estimated Net Income | ||
Particulars | $ | $ |
Estimated sales (1) | 800,000 | |
Less: Estimated incremental costs | ||
Variable | 300,000 | |
Fixed manufacturing costs (except | 60,000 | |
Depreciation expense (3) | 130,000 | |
Selling and general expenses | 40,000 | 530,000 |
Income before income taxes | 270,000 | |
Less: Income taxes expense (4) | 81,000 | |
Estimated increase in annual net income | 189,000 |
Table (1)
Therefore, the estimated increase in the annual net income is $189,000.
Working note:
Calculate the amount of estimated sales
Calculate the variable manufacturing cost
Calculate the depreciation expense
Calculate the income tax expense
b.
Ascertain the annual net
b.

Explanation of Solution
Ascertain the annual net cash flows expected from the give project as follows:
Particulars | $ | $ |
Cash receipts | 800,000 | |
Less: cash outlays | ||
Variable manufacturing costs | 300,000 | |
Fixed costs (other than depreciation) | 60,000 | |
Selling and general expenses | 40,000 | |
Income taxes expense | 81,000 | 481,000 |
Annual net cash flow from sale of new product | 319,000 |
Table (2)
Therefore, the annual net cash flow from sale of new product is $319,000.
c.
Ascertain the (1) payback period, (2) return on average investment, and (3)
c.

Explanation of Solution
Payback period: Payback period is the expected time period which is required to recover the cost of investment. It is one of the capital investment method used by the management to evaluate the proposal of long-term investment (fixed assets) of the business.
Present value: This is the amount of future value reduced or discounted at a rate of interest till particular current date.
Ascertain the (1) payback period, (2) return on average investment, and (3) net present value, and assume annual discount rate is 12 percent as follows:
(1) Payback period:
When the estimated annual net cash is equal, the cash payback period is calculated as below:
Therefore, the payback period of the equipment is 1.25 years.
(2) Return on average investment:
Therefore, the return on average investment is 92.2%.
(3) Net present value:
Particulars | $ |
Total present value of annual net cash flows (5) | 766,238 |
Add: Present value of salvage, due in three years (6) | 7,120 |
Total present value | 773,358 |
Less: Amount to be invested | 400,000 |
Net present value of the project | 373,358 |
Table (3)
Therefore, the net present value of the project is $373,358.
Working note:
Calculate the present value of cash flow at the end of the 3rd year
Particulars | Amount ($) |
Cash flow of the investment (a) | $319,000 |
PV at $1 annuity at discount rate of 12% for 3 years (b) | 2.402 |
Present value of cash flow after 3 years | $766,238 |
Table (4)
(5)
Note: The Present value of an ordinary annuity of $1 for 3 years at 12% is 2.4023 refer present value table in Exhibit 4).
Calculate the present value of salvage value
Particulars | Amount ($) |
Salvage value (a) | $10,000 |
PV factor at an annual discount rate of 12% for 3rd year (b) | 0.712 |
Present value of cash flow | $7,120 |
Table (5)
(6)
Note: The present value of $1 for 3rd year at 15% is 0.712 (refer present value table in Exhibit 3).
Want to see more full solutions like this?
Chapter 26 Solutions
GEN COMBO FINANCIAL & MANAGERIAL ACCOUNTING; CONNECT ACCESS CARD
- Morris Corporation applies manufacturing overhead at the rate of $40 per machine hour. Budgeted machine hours for the current period were anticipated to be 200,000; however, higher than expected production resulted in actual machine hours worked of 225,000. Budgeted and actual manufacturing overhead figures for the year were $8,000,000 and $8,750,000, respectively. On the basis of this information, the company's year-end overhead was: A. overapplied by $250,000 B. underapplied by $250,000 C. overapplied by $750,000 D. underapplied by $750,000arrow_forwardAt the beginning of the year, manufacturing overhead for the year was estimated to be $560,000. At the end of the year, actual labor hours for the year were 35,000 hours, the actual manufacturing overhead for the year was $590,000, and the manufacturing overhead for the year was underapplied by $30,000. If the predetermined overhead rate is based on direct labor hours, then the estimated labor hours at the beginning of the year used in the predetermined overhead rate must have been ___ hours.arrow_forwardGive me Answerarrow_forward
- Lyndon Advisory Group, a consulting firm, had accounts receivable of $22,000 on May 31. During June, payments from customers on account totaled $13,500. At the end of June, Lyndon had accounts receivable amounting to $25,000. What was the amount of consulting services provided to customers on credit during the month of June?arrow_forwardGrant Corporation owns 20% of the common stock of Tanner Industries and uses the fair-value method to account for this investment. Tanner reported net income of $175,000 for 2023 and paid dividends of $95,000 on October 15, 2023. How much income should Grant recognize on this investment in 2023? a. $35,000 b. $19,000 c. $54,000 d. $11,500 e. $70,000arrow_forwardWhat was the direct labor cost on the job?arrow_forward
- What is the answer??arrow_forwardOrville Manufacturing Company's work-in-process inventory on August 1 has a balance of $32,400, representing Job No. 527. During August, $61,500 of direct materials were requisitioned for Job No. 527, and $42,800 of direct labor cost was incurred on Job No. 527. Manufacturing overhead is allocated at 125% of direct labor cost. Actual manufacturing overhead costs incurred in August amounted to $52,500. No new jobs were started during August. Job No. 527 is completed on August 28. Is manufacturing overhead overallocated or underallocated for the month of August and by how much? Correct answerarrow_forwardSolve This Financial Accounting Problemarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education