Equity as an Option and
a. What is the value of the firm’s equity and debt if Project A is undertaken? If Project B is undertaken?
b. Which project would the stockholders prefer? Can you reconcile your answer with the NPV rule?
c. Suppose the stockholders and bondholders are in fact the same group of investors. Would this affect your answer to (b)?
d. What does this problem suggest to you about stockholder incentives?
a)
To compute: The value of company’s debt and equity for both the projects
Introduction:
Value of equity:
The value of equity is the amount comprised in the firm’s capital structure as equity shares. It is the total contribution of the equity shareholders to the firm.
Value of debt:
The value of debt is the amount comprised in the firm’s capital structure as debt. It is the total contribution of the debt holders to the firm.
Answer to Problem 17QP
The values of the company’s equity and debt for Project A are $6,416.10 and $14,583.90 and for Project B are $6,274.76 and $15,625.24.
Explanation of Solution
Given information:
Company SS is planning two mutually exclusive projects. The NPV of Project A is $1,900 and for Project B, it is $2,800. The return on the standard deviation on the assets of the firm will raise to 46% per year. If Project B is taken, the standard deviation will decrease to 29% per year.
Explanation:
Formula to calculate the delta of the call option:
Where,
S is the stock price
E is the exercise price
r is the risk-free rate
σ is the standard deviation
t is the period of maturity
Calculate the delta of the call option for Project A:
Hence, d1is $0.8198.
Note: The cumulative frequency distribution value for 0.8198 is 0.79383493.
Hence, the delta for the call option is $0.7938.
Formula to calculate the delta of the put option:
Calculate the delta of the put option for Project A:
Hence, d2 is $0.3598.
Note: The cumulative frequency distribution value for 0.3598 is 0.64050165.
Hence, the delta for the put option is $0.6405.
Formula to calculate the equity using the black-scholes model:
Where,
S is the stock price
E is the exercise price
C is the call price
R is the risk-free rate
t is the period of maturity
Calculate the equity for project A:
Hence, the equity for Project A is $6,416.10.
Formula to calculate the debt amount:
Calculate the debt amount for Project A:
Hence, the debt amount for Project A is $14,583.90.
Formula to calculate the delta of the call option:
Where,
S is the stock price
E is the exercise price
r is the risk-free rate
σ is the standard deviation
t is the period of maturity
Calculate the delta of the call option for Project B:
Hence, d1is $1.2253.
Note: The cumulative frequency distribution value for 1.2253 is 0.88976890.
Hence, the delta for the call option is $0.8898.
Formula to calculate the delta of the put option:
Calculate the delta of the put option for Project B:
Hence, d2 is $0.9353.
Note: The cumulative frequency distribution value for 0.9353 is 0.82518314.
Hence, the delta for the put option is $0.8252.
Formulae to calculate the equity using the black-scholes model:
Where,
S is the stock price
E is the exercise price
C is the call price
R is the risk-free rate
t is the period of maturity
Calculate the equity for project B:
Hence, the equity for Project B is $6,274.76.
Formula to calculate the debt amount:
Calculate the debt amount for Project B:
Hence, the debt amount for Project B is $15,625.24.
b)
To discuss: The project that the stockholders prefer, using the rule of NPV.
Introduction:
Value of equity:
The value of equity is the amount comprised in the firm’s capital structure as equity shares. It is the total contribution of the equity shareholders to the firm.
Value of debt:
The value of debt is the amount comprised in the firm’s capital structure as debt. It is the total contribution of the debt holders to the firm.
Explanation of Solution
Given information:
Company SS is planning two mutually exclusive projects. The NPV of Project A is $1,900 and for Project B, it is $2,800. The return on the standard deviation on the assets of the firm will raise to 46% per year. If Project B is taken, the standard deviation will decrease to 29% per year.
Explanation:
As per the rule of NPV (Net Present Value), project-B is more beneficial (higher value) than Project A. The selection of Project B would increase the value of firm rather than when selecting Project A. However, the firm is highly levered.
Hence, the selection of Project B is highly beneficial to debt-holders. This project selection creates only a small increase in the equity’s value. Therefore, the stockholders will select Project A, even if the NPV is lower.
c)
To discuss: The selection of the project if the stocks and bondholders are the same investors.
Introduction:
Value of equity:
The value of equity is the amount comprised in the firm’s capital structure as equity shares. It is the total contribution of the equity shareholders to the firm.
Value of debt:
The value of debt is the amount comprised in the firm’s capital structure as debt. It is the total contribution of the debt holders to the firm.
Explanation of Solution
Given information:
Company SS is planning two mutually exclusive projects. The NPV of Project A is $1,900 and for Project B, it is $2,800. The return on the standard deviation on the assets of the firm will raise to 46% per year. If Project B is taken, the standard deviation will decrease to 29% per year.
Explanation:
If the stockholders and bondholders are the same investors, then Project B must be selected. It increases the value of the firm from 21,000 to 21,900. This value addition increases the value of debt as well as equity kept by the same investors. Therefore, investors do not feel the leakage of earnings.
d)
To discuss: The impact of leverage on a stockholder’s incentive.
Introduction:
Value of equity:
The value of equity is the amount comprised in the firm’s capital structure as equity shares. It is the total contribution of the equity shareholders to the firm.
Value of debt:
The value of debt is the amount comprised in the firm’s capital structure as debt. It is the total contribution of the debt holders to the firm.
Explanation of Solution
Given information:
Company SS is planning two mutually exclusive projects. The NPV of Project A is $1,900 and for Project B, it is $2,800. The return on the standard deviation on the assets of the firm will raise to 46% per year. If Project B is taken, the standard deviation will decrease to 29% per year.
Explanation:
Stockholders are the “risk takers” of the company. The highly levered capital structure increases the risk of equity and dilutes the earnings of equity. Therefore, stockholders receive less incentive for taking a higher risk from highly levered firms.
Want to see more full solutions like this?
Chapter 25 Solutions
Fundamentals of Corporate Finance
- Says my answer is wrongarrow_forwardEquipment is worth $339,976. It is expected to produce regular cash flows of $50,424 per year for 18 years and a special cash flow of $75,500 in 18 years. The cost of capital is X percent per year and the first regular cash flow will be produced today. What is X? Input instructions: Input your answer as the number that appears before the percentage sign. For example, enter 9.86 for 9.86% (do not enter .0986 or 9.86%). Round your answer to at least 2 decimal places. percentarrow_forwardYou plan to retire in 8 years with $X. You plan to withdraw $114,200 per year for 21 years. The expected return is 17.92 percent per year and the first regular withdrawal is expected in 9 years. What is X? Input instructions: Round your answer to the nearest dollar. $ 523472 0arrow_forward
- You want to buy equipment that is available from 2 companies. The price of the equipment is the same for both companies. Orange Furniture would let you make quarterly payments of $12,540 for 6 years at an interest rate of 1.26 percent per quarter. Your first payment to Orange Furniture would be in 3 months. River Furniture would let you make X monthly payments of $41,035 at an interest rate of 0.73 percent per month. Your first payment to River Furniture would be today. What is X? Input instructions: Round your answer to at least 2 decimal places.arrow_forwardI keep getting it wrongarrow_forwardYou plan to retire in 5 years with $429,887. You plan to withdraw $67,100 per year for 12 years. The expected return is X percent per year and the first regular withdrawal is expected in 6 years. What is X? Input instructions: Input your answer as the number that appears before the percentage sign. For example, enter 9.86 for 9.86% (do not enter .0986 or 9.86%). Round your answer to at least 2 decimal places. percentarrow_forward
- You plan to retire in 10 years with $385,337. You plan to make X withdrawals of $59,856 per year. The expected return is 17.26 percent per year and the first regular withdrawal is expected in 10 years. What is X? Input instructions: Round your answer to at least 2 decimal places.arrow_forwardMy answer keeps having an x for incorrect what is the correct answerarrow_forwardYou plan to retire in 4 years with $659,371. You plan to withdraw $100,000 per year for 12 years. The expected return is X percent per year and the first regular withdrawal is expected in 4 years. What is X? Input instructions: Input your answer as the number that appears before the percentage sign. For example, enter 9.86 for 9.86% (do not enter .0986 or 9.86%). Round your answer to at least 2 decimal places. percentarrow_forward
- Answers wrongarrow_forwardYou plan to retire in 6 years with $1,124,632. You plan to make X withdrawals of $148,046 per year. The expected return is 10.81 percent per year and the first regular withdrawal is expected in 7 years. What is X? Input instructions: Round your answer to at least 2 decimal places.arrow_forwardEquipment is worth $206,286. It is expected to produce regular cash flows of $13,729 per year for 25 years and a special cash flow of $10,100 in 25 years. The cost of capital is X percent per year and the first regular cash flow will be produced in 1 year. What is X? Input instructions: Input your answer as the number that appears before the percentage sign. For example, enter 9.86 for 9.86% (do not enter .0986 or 9.86%). Round your answer to at least 2 decimal places. percentarrow_forward
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT