a.
Compute the materials price and quantity variances.
a.

Explanation of Solution
Variance:
Variance refers to the difference level in the actual cost incurred and
Compute the materials price variances.
Compute the materials quantity variances.
Therefore, the materials price and quantity variances of Enterprise H are $34,000 and $30,000.
Working Notes:
Calculate the actual price per pound:
(1)
Calculate the standard quantity allowed:
(2)
b.
Compute the labor rate and efficiency variances.
b.

Explanation of Solution
Compute the labor rate variances.
Compute the labor efficiency variances.
Therefore, the labor rate and efficiency variances of Enterprise H are $625 and ($825).
Working Notes:
Calculate the actual rate per hour:
(3)
Calculate the standard hours allowed:
(4)
c.
Compute the manufacturing
c.

Explanation of Solution
Compute the manufacturing overhead spending variances.
Particulars | Amount in $ | Amount in $ |
Standard Overhead cost incurred: | ||
Fixed | 3,300 | |
Variable (5) | 1,600 | |
4,900 | ||
Actual Overhead cost incurred: | ||
Fixed | 3,100 | |
Variable | 1,100 | |
4,200 | ||
Overhead spending variance (favorable) | 700 |
(Table 1)
Compute the manufacturing overhead volume variances.
Particulars | Amount |
Overhead applied at standard cost ($32 × 160batches) | $ 5,120 |
Less: Standard overhead cost allowed | $4,900 |
Volume variance (favorable) | $ 220 |
(Table 2)
Therefore, the manufacturing overhead spending and volume variances of Enterprise H are $700 and $220.
Working note:
Calculate the standard variable overhead allowed:
(5)
d.
Prepare
d.

Explanation of Solution
Prepare journal entry to record to charge materials (at standard) to Work in Process.
Date | Accounts title and explanation |
Debit ($) |
Credit ($) |
Work in process inventory ( at Standard) (6) | 820,000 | ||
Materials quantity variance (favorable) | 30,000 | ||
Materials price variance (favorable) | 34,000 | ||
Direct materials inventory (Actual) | 816,000 | ||
(To record the cost of direct materials charged to production) |
(Table 3)
- Work in process inventory is an asset and there is an increase in the value of an asset. Hence, debit the work in process inventory by $820,000.
- Materials quantity variance is an asset and there is a decrease in the value of an asset. Hence, credit the materials quantity variance by $30,000.
- Materials price variance is an asset and there is a decrease in the value of an asset. Hence, credit the materials price variance by $34,000.
- Direct materials inventory is an asset and there is a decrease in the value of an asset. Hence, credit the direct materials inventory by $816,000
Working notes:
Calculate the work in process inventory for direct materials:
(6)
e.
Prepare journal entry to record to charge direct labor (at standard) to Work in Process.
e.

Explanation of Solution
Prepare journal entry to record to charge direct labor (at standard) to Work in Process.
Date | Accounts title and explanation |
Debit ($) |
Credit ($) |
Work in process inventory ( at Standard) (7) | 19,800 | ||
Labor efficiency variance (Unfavorable) | 825 | ||
Labor rate variance(Favorable) | 625 | ||
Direct Labor (Actual) | 20,000 | ||
(To record the cost of direct labor charged to production.) |
(Table 4)
- Work in process inventory is an asset and there is an increase in the value of an asset. Hence, debit the work in process inventory by $19,800.
- Labor efficiency variance is an asset and there is an increase in the value of an asset. Hence, debit the labor efficiency variance by $825.
- Labor rate variance is an asset and there is a decrease in the value of an asset. Hence, credit the labor rate variance by $625.
- Direct labor is an asset and there is a decrease in the value of an asset. Hence, credit the direct labor by $20,000.
Working notes:
Calculate the work in process inventory for direct labor cost:
(7)
f.
Prepare journal entry to record to charge manufacturing overhead (at standard) to Work in Process.
f.

Explanation of Solution
Prepare journal entry to record to charge manufacturing overhead (at standard) to Work in Process.
Date | Accounts title and explanation |
Debit ($) |
Credit ($) |
Work in process inventory ( at Standard) | 5,120 | ||
Overhead spending variance | 700 | ||
Overhead volume variance | 220 | ||
Manufacturing Overhead (Actual) | 4,200 | ||
(To apply overhead to production.) |
(Table 5)
- Work in process inventory is an asset and there is an increase in the value of an asset. Hence, debit the work in process inventory by $5,120.
- Overhead spending variance (Expense) is a component of
stockholder’s equity and there is an increase in the value of expense. Hence, debit the overhead spending variance by $700. - Overhead volume variance (Expense) is a component of stockholder’s equity and there is a decrease in the value of expense. Hence, credit the overhead volume variance by $220.
- Manufacturing overhead (Expense) is a component of stockholder’s equity and there is a decrease in the value of expense. Hence, credit the manufacturing expense by $4,200.
g.
Prepare journal entry to record the transfer of 160 batches of puppy meal produced in June to Finished Goods.
g.

Explanation of Solution
Prepare journal entry to record the transfer of 160 batches of puppy meal produced in June to Finished Goods
Date | Accounts title and explanation |
Debit ($) |
Credit ($) |
Finished goods inventory (at standard cost) | 844,920 | ||
Work in process inventory (at standard cost) (8) | 844,920 | ||
(To transfer 160 batches of puppy meal to finished goods in April.) |
(Table 6)
- Finished goods inventory is an asset and there is an increase in the value of an asset. Hence, debit the finished goods inventory by $844,920.
- Work in process inventory is an asset and there is a decrease in the value of an asset. Hence, credit the work in process inventory by $844,920.
Working Notes:
Calculate the work in process inventory at standard cost:
(8)
h.
Prepare journal entry to record to close any over- or underapplied overhead to Cost of Goods Sold.
h.

Explanation of Solution
Prepare journal entry to record to close any over- or underapplied overhead to Cost of Goods Sold.
Date | Accounts title and explanation |
Debit ($) |
Credit ($) |
Overhead spending variance (favorable) | 700 | ||
Overhead volume variance (favorable) | 220 | ||
Cost of goods sold | 920 | ||
(To close overhead variances to cost of goods sold.) |
(Table 7)
- Overhead spending variance (Expense) is a component of stockholder’s equity and there is an increase in the value of expense. Hence, debit the overhead spending variance by $700.
- Overhead volume variance (Expense) is a component of stockholder’s equity and there is an increase in the value of expense. Hence, debit the overhead volume variance by $220.
- Cost of goods sold (expense) is component of stockholder’s equity and there is a decrease in the value of expense. Hence, credit the cost of goods sold by $920.
Want to see more full solutions like this?
Chapter 24 Solutions
Financial Accounting
- Please don't use AI And give correct answer .arrow_forwardLouisa Pharmaceutical Company is a maker of drugs for high blood pressure and uses a process costing system. The following information pertains to the final department of Goodheart's blockbuster drug called Mintia. Beginning work-in-process (40% completed) 1,025 units Transferred-in 4,900 units Normal spoilage 445 units Abnormal spoilage 245 units Good units transferred out 4,500 units Ending work-in-process (1/3 completed) 735 units Conversion costs in beginning inventory $ 3,250 Current conversion costs $ 7,800 Louisa calculates separate costs of spoilage by computing both normal and abnormal spoiled units. Normal spoilage costs are reallocated to good units and abnormal spoilage costs are charged as a loss. The units of Mintia that are spoiled are the result of defects not discovered before inspection of finished units. Materials are added at the beginning of the process. Using the weighted-average method, answer the following question: What are the…arrow_forwardQuick answerarrow_forward
- Financial accounting questionarrow_forwardOn November 30, Sullivan Enterprises had Accounts Receivable of $145,600. During the month of December, the company received total payments of $175,000 from credit customers. The Accounts Receivable on December 31 was $98,200. What was the number of credit sales during December?arrow_forwardPaterson Manufacturing uses both standards and budgets. For the year, estimated production of Product Z is 620,000 units. The total estimated cost for materials and labor are $1,512,000 and $1,984,000, respectively. Compute the estimates for: (a) a standard cost per unit (b) a budgeted cost for total production (Round standard costs to 2 decimal places, e.g., $1.25.)arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education