Concept Introduction:
Variable overhead cost variance:
Variable overhead cost variance can be defined as difference in the standard variable
Variable overhead cost variance is calculated as under –
Variable overhead efficiency variance:
Variable overhead efficiency variance can be defined as difference between the standard hours or standard basis of use and actual hours or actual basis of use
Variable overhead efficiency variance is calculated as under –
Fixed overhead cost variance:
Fixed overhead cost variance can be defined as difference in the standard fixed overheads and actual fixed overheads.
Fixed overhead cost variance is calculated as under –
Fixed overhead volume variance:
Fixed overhead volume variance can be defined as difference between fixed overhead for standard output and fixed overhead for actual output.
Fixed overhead volume variance is calculated as under –
To compute:
1. Variable Overhead cost variance
2. Variable overhead efficiency variance
3. Fixed Overhead Cost variance
4. Fixed overhead volume variance
Requirement 2
To explain:
Why the variances are favourable or unfavourable
Want to see the full answer?
Check out a sample textbook solutionChapter 23 Solutions
ACCOUNTING PRINCIPLES 122 5/16 >C<
- Biological assets are measured atarrow_forwardA company has sales of $150 million, cost of goods sold of $100 million, and a before-tax profit of 8%. If purchasing was able to reduce the cost of goods sold by $5 million, how much additional sales would be required to achieve the same impact on profit? General Accountarrow_forwardgeneral accountingarrow_forward
- Consider the following project which costs $2,000 with a salvage value of zero in 4 years. The project will produce a new widget which will be sold for $140 and has variable costs of $110 per unit. The company has fixed costs of $3,050 and a required return on projects of 14.5%. If the company sells 210 units, what is the firm's degree of leverage? Dolarrow_forwardA company is considering whether to adopt a new accounting software system. Discuss the potential benefits and challenges of implementing new accounting software. What factors should the company consider when selecting a software system? How can the company ensure a successful implementation and minimize disruption to its operations?arrow_forwardA company has recently acquired another company and is in the process of integrating the two companies' accounting systems. Discuss the challenges associated with integrating accounting systems post-acquisition. What are the potential risks of not properly integrating the systems? How can the company ensure a smooth transition and maintain the integrity of its financial data?arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education