Variance:
Variance is the difference between the actual cost and budgeted cost for particular level of activity. It is computed by deducting the budgeted cost from the actual cost of the production.
Direct Material Cost Variance:
The difference between the actual cost incurred on the direct material and the budgeted cost expected to be incurred is called the direct material cost variance. It can either calculated by deducting the budgeted cost from the actual cost or adding the direct material price variance and direct material quantity variance.
Direct Labor Cost Variance:
The variance between the actual labor cost incurred and the budgeted labor cost is termed as direct labor cost variance. It can be computed by deducting the budgeted labor cost from the actual cost. On the contrary, it can also be ascertained by adding the direct labor rate variance and direct labor efficiency variance.
Controllable Variance:
The overall variance which comprises of variable
Volume Variance:
The variance which arises due to difference in the budgeted level of activity and the actual level is called volume variance. The sole reason for this kind of variance is the variation in the level of activity.
Computation of these variances:
(a) Variable overhead spending and efficiency
(b) Fixed overhead spending and volume
(c) Total overhead controllable

Want to see the full answer?
Check out a sample textbook solution
Chapter 23 Solutions
FUND.ACCT.PRIN.
- Accurate Answerarrow_forwardCompany C had an estimated 185,000direct labor hours, $592,500 manufacturing overhead, and 32,500 machine hours. The actual were 178,900 direct labor hours, 34,200 machine hours, and $603,800manufacturing overhead. They determine overhead based upon machine hours. Calculate the predetermined overhead rate.arrow_forwardI am trying to find the accurate solution to this general accounting problem with appropriate explanations.arrow_forward
- Can you explain the correct approach to solve this financial accounting question?arrow_forwardAtlas Medical Clinic has fixed costs of$260,000. After 35,000 visits, its fixed costs increase by $42,000 because it must hire additional support staff. Variable costs are $6 per visit. If you are budgeting for 30,000 visits, what is your average cost per visit? Answerarrow_forwardI am searching for the accurate solution to this general accounting problem with the right approach.arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education