Concept explainers
Flexible Budget:
A flexible budget is prepared for more than one level of production and it is flexible in nature. Flexible budget can vary according to the actual level of production. It eliminates the volume variance between the budgeted values and actual result of production.
Material Price Variance:
At the actual quantity, the difference between the actual
Material Quantity Variance:
The material quantity variance measures the efficiency of a production in terms of material utilization. It is computed by determining the difference between the standard quantity to used and actual quantity of material used in the production at the standard rate.
Labor Rate Variance:
At the actual direct labor hours, the variance between the actual direct labor cost based on actual rate incurred and the budgeted direct labor cost based on standard rate is called direct labor cost variance.
Direct Labor Efficiency Variance:
Direct labor efficiency variance measures the efficiency in utilization of direct labor costs by determining the difference between the actual labor hours and the direct labor hours allowed at the standard rate.
1. Determine the cost per unit of each variable
2. Preparing flexible budgets showing the amounts of each variable and fixed cost at the 65%, 75% and 85% capacity levels.
3. Computation of direct materials cost variance, showing price and quantity variances.
4. Computation of direct labor cost variance, showing rate and efficiency variances.
5. Preparation of overhead variance report that shows the variances for individual items of overhead.

Explanation of Solution
1. The total per unit costs is $12 and the total fixed cost per month is $180,000.
2. The total overhead cost at 65%, 75%, and 85% is $336,000, $360,000, and $384,000 respectively.
3. The direct material cost variance is $15,900 (U) with unfavorable price variance of $6,900 and quantity variance of $9,000.
4. Direct labor cost variance is $10,440 (U) with unfavorable rate variance of $6,840 and efficiency variance of $3,600.
5. Suncoast Company has favorable overhead volume variance of $48,000 and unfavorable controllable variance of $4,740.
Overhead items | Variable cost per unit | Fixed cost per month |
Variable overhead costs | ||
Indirect materials | $1.50 | |
Indirect labor | $6.00 | |
Power | $1.50 | |
Repairs and maintenance | $3.00 | |
Total variable overhead costs | $12.00 | |
Fixed overhead costs | ||
| $24,000 | |
Depreciation − Machinery | $72,000 | |
Taxes and insurance | $18,000 | |
Supervision | $66,000 | |
Total fixed overhead costs | $180,000 |
SUNCOAST COMPANY Flexible Overhead Budgets For the Month Ended December 31. | |||||
Flexible Budget | Flexible Budget at Capacity Level of | ||||
Variable cost per unit | Fixed cost per month | 65% | 75% | 85% | |
Production (in units) | 1 unit | 13,000 | 15,000 | 17,000 | |
Variable overhead costs | |||||
Indirect materials | $1.50 | $19,500 | $22,500 | $25,500 | |
Indirect labor | $6.00 | $78,000 | $90,000 | $102,000 | |
Power | $1.50 | $19,500 | $22,500 | $25,500 | |
Repairs and maintenance | $3.00 | $39,000 | $45,000 | $51,000 | |
Total variable overhead costs | $12.00 | $156,000 | $180,000 | $204,000 | |
Fixed overhead costs | |||||
Depreciation − Building | $24,000 | $24,000 | $24,000 | $24,000 | |
Depreciation − Machinery | $72,000 | $72,000 | $72,000 | $72,000 | |
Taxes and insurance | $18,000 | $18,000 | $18,000 | $18,000 | |
Supervision | $66,000 | $66,000 | $66,000 | $66,000 | |
Total fixed overhead costs | $180,000 | $180,000 | $180,000 | $180,000 | |
Total Overhead Costs | $336,000 | $360,000 | $384,000 | ||
Predetermined overhead rate per standard direct labor hour | $16.00 |
3. Computation of direct materials cost variance, including its price and quantity variances
4. Computation of direct labor cost variance, including its rate and efficiency variances
5.
SUNCOAST COMPANY Overhead Variance Report For the Month Ended December 31. | |||
Overhead Volume Variance | |||
Expected production level | 75% of capacity 15,000 units | ||
Production level achieved | 85% of capacity 17,000 units | ||
Budgeted fixed overhead (22,500 hrs. X $16.00) | $360,000 | ||
Fixed overhead applied (25,500 hrs. X $16.00) | $408,000 | ||
Volume Variance | $48,000 F | ||
Overhead Controllable Variance | Flexible Budget | Actual Results | Variances |
Variable overhead costs | |||
Indirect materials | $22,500 | $21,600 | $900F |
Indirect labor | $90,000 | $82,260 | $7,740 F |
Power | $22,500 | $23,100 | $600 U |
Repairs and maintenance | $45,000 | $46,800 | $1,800 U |
Total variable overhead costs | $180,000 | $173,760 | $6,240 F |
Fixed overhead costs | |||
Depreciation − Building | $24,000 | $24,000 | 0 |
Depreciation − Machinery | $72,000 | $75,000 | $3,000 U |
Taxes and insurance | $18,000 | $16,500 | $1,500 F |
Supervision | $66,000 | $66,000 | 0 |
Total fixed overhead costs | $180,000 | $181,500 | $1,500 U |
Total Overhead costs | $360,000 | $355,260 | $4,740 U |
The direct material pro=ice variance is $6,900 Unfavorable
The direct material quantity variance is $9,000 Unfavorable
The direct material cost variance is $15,900 Unfavorable
Want to see more full solutions like this?
Chapter 23 Solutions
FUNDAMENTAL ACCOUNTING PRINCIPLES
- Tikki's problemarrow_forwardAccounting 41arrow_forwardRobertson Corp. expects to sell 32,500 units. Each unit requires 5 pounds of direct materials at $18 per pound and 2.5 direct labor hours at $14 per direct labor hour. The overhead rate is $10 per direct labor hour. The beginning inventories are as follows: direct materials, 3,200 pounds; finished goods, 4,000 units. The planned ending inventories are as follows: direct materials, 5,500 pounds; finished goods, 4,200 units. What is the planned production?arrow_forward
- Moti Bakery produces various baked goods. Utility costs are allocated to the products based on the baking time required for each product. Total utility costs of $270,000 are budgeted in a period when 540,000 total minutes of baking time are anticipated. If a batch of bagels bakes for 25 minutes, what amount of utility cost will be allocated to the bagels?arrow_forwardhe following is a December 31, 2024, post-dosing trial balance for Almway Corporation. Account Title Debits Credits Cash 45,000 Investments 110,000 Accounts receivable 60,000 Inventories 200,000 Prepaid insurance (for the next 9 months) 9,000 Land 90,000 Buildings 420,000 Accumulated depreciation-buildings $ 100,000 Equipment 110,000 60,000 10,000 75.000 130.000 20.000 240,000 300.000 129.000 Accumulated depreciation-equipment Patents (net of amorization) Accounts payable Notes payable Interest payable Bonds Payable Common stock Retained eamings Totals Additional information: $ 1,054,000 $ 1,054,000 1. The investment account includes an investment in common stock of another corporation of $30,000 which management intends to hold for at least three years. The balance of these investments is intended to be sold in the coming year. 2. The land account includes land which cost $25,000 that the company has not used and is currently listed for sale. 3. The cash account includes $15,000…arrow_forwardWhich is not a Risk Assessment Procedure?a. Ratio Analysisb. Observation of Activitiesc. Account Receivable confirmationsd. Inspection of Documentse. Inquiry of Internal Auditors Is it a or c ???arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education