FUNDAMENTAL ACCT PRIN CONNECT ACCESS
24th Edition
ISBN: 9781266494604
Author: Wild
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 23, Problem 22E
To determine
The difference between the total actual and budgeted overhead is known as Overhead Controllable Variance. It is the combination of both fixed and variable overhead variances.
Overhead Volume Variance
The difference between the total fixed overhead applied and total budgeted overhead is known as Overhead Volume Variance.
- The overhead controllable variance and find whether it is favorable or unfavorable
- The overhead volume variance and find whether it is favorable or unfavorable.
- Make a report on overhead variance with 9,000 units of activity level.
Expert Solution & Answer
Answer to Problem 22E
Solution:
- The overhead controllable variance is $2,300 and it is favorable
- The overhead volume variance is $6,000 and it is Favorable.
- Overhead variance report at the actual activity level of 9000 units
BLAZE CORP. Overhead Variance Report for the month ended March 31st. | ||
Planned production volume | 80% capacity | |
Actual production volume | 90% capacity | |
Volume variance | $ 6,000 | Favorable |
Controllable Variance | Flexible budget | Actual result | Variance | Favorable / Unfavorable |
Variable overhead cost | ||||
Indirect materials | $11,250 | $10,000 | $1,250 | Favorable |
Indirect labor | $18,000 | $16,000 | 2,000 | Favorable |
Power | $4,500 | $4,500 | 0 | No Variance |
Maintenance | $2,250 | $3,000 | $750 | Unfavorable |
Total variable cost | $36,000 | $33,500 | $2,500 | Favorable |
Fixed overhead cost | ||||
Rent of factory building | $12,000 | $12,000 | 0 | No variance |
$20,000 | $19,200 | $800 | Favorable | |
Taxes and insurance | $2,400 | $3,000 | $600 | Unfavorable |
Supervisory salary | $13,600 | $14,000 | $400 | Unfavorable |
Total fixed cost | $48,000 | 48,200 | $200 | Unfavorable |
Total Overhead cost | $84,000 | 99,250 | $2,300 | Favorable |
Explanation of Solution
Controllable Variance | |||
Actual overhead total | $ 81,700 | ||
Flexible budget overhead total | |||
Variable | $36,000 | ||
Fixed | $48,000 | ||
Total | $ 84,000 | ||
Overhead controllable variance | $ 2,300 | Favorable |
Volume Variance | ||
Budgeted fixed overhead cost (32,000 X $1.50) | $48,000 | |
Applied Fixed overhead cost (36,000 X $1.50) | $54,000 | |
Volume variance | $ 6,000 | Favorable |
Computation of applied fixed overhead cost
3. Flexible budget at 90% capacity (9,000 units)
JAMES CORP. Flexible Overhead Budget for the month ended May 31st. | |||
Variable overhead per unit | Fixed overhead per month | Flexible Budget at 90% capacity (9,000 units) | |
Variable overhead cost | |||
Indirect materials | $1.25 | $11,250 | |
Indirect labor | $2.00 | $18,000 | |
Power | $0.50 | $4,500 | |
Maintenance | $0.25 | $2,250 | |
Total variable cost | $4.00 | $36,000 | |
Fixed overhead cost | |||
Rent of factory building | $12,000 | $12,000 | |
Depreciation- Machinery | $20,000 | $20,000 | |
Taxes and insurance | $2,400 | $2,400 | |
Supervisory salary | $13,600 | $13,600 | |
Total fixed cost | $48,000 | $48,000 | |
Total Overhead cost | $84,000 |
Conclusion
From the above it is clear with the following;-
The overhead controllable variance is favorable with $ 2,300
The volume variance is favorable with $ 6,000
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Chapter 23 Solutions
FUNDAMENTAL ACCT PRIN CONNECT ACCESS
Ch. 23 - Prob. 1DQCh. 23 - Prob. 2DQCh. 23 - Prob. 3DQCh. 23 - Prob. 4DQCh. 23 - Prob. 5DQCh. 23 - Prob. 6DQCh. 23 - Prob. 7DQCh. 23 - Prob. 8DQCh. 23 - Prob. 9DQCh. 23 - Prob. 10DQ
Ch. 23 - Prob. 11DQCh. 23 - Prob. 12DQCh. 23 - Prob. 13DQCh. 23 - How can the manager of advertising sales at Google...Ch. 23 - Prob. 15DQCh. 23 - Prob. 16DQCh. 23 - Is it possible to evaluate a cost center’s...Ch. 23 - Prob. 18DQCh. 23 - Prob. 1QSCh. 23 - Prob. 2QSCh. 23 - Prob. 3QSCh. 23 - Prob. 4QSCh. 23 - Prob. 5QSCh. 23 - Prob. 6QSCh. 23 - Prob. 7QSCh. 23 - Prob. 8QSCh. 23 - Prob. 9QSCh. 23 - Prob. 10QSCh. 23 - Prob. 11QSCh. 23 - Prob. 12QSCh. 23 - Prob. 13QSCh. 23 - Prob. 14QSCh. 23 - Volume variance P3 Refer to information in QS...Ch. 23 - Prob. 16QSCh. 23 - Prob. 17QSCh. 23 - Prob. 18QSCh. 23 - Prob. 19QSCh. 23 - Prob. 20QSCh. 23 - Prob. 21QSCh. 23 - Prob. 22QSCh. 23 - Prob. 23QSCh. 23 - Prob. 24QSCh. 23 - Exercise 23-1 Management by exception C1 Resset...Ch. 23 - Prob. 2ECh. 23 - Exercise 23-2 Preparing flexible budgets P1 Tempo...Ch. 23 - Prob. 4ECh. 23 - Prob. 5ECh. 23 - Prob. 6ECh. 23 - Prob. 7ECh. 23 - Prob. 8ECh. 23 - Prob. 9ECh. 23 - Prob. 10ECh. 23 - Prob. 11ECh. 23 - Prob. 12ECh. 23 - Exercise 23-13 Computing and interpreting...Ch. 23 - Prob. 14ECh. 23 - Exercise 23-15
Direct materials and direct labor...Ch. 23 - Prob. 16ECh. 23 - Prob. 17ECh. 23 - Exercise 23-18A Detailed overhead variances P5...Ch. 23 - Prob. 19ECh. 23 - Prob. 20ECh. 23 - Prob. 21ECh. 23 - Prob. 22ECh. 23 - Prob. 23ECh. 23 - Prob. 1APSACh. 23 - Prob. 2APSACh. 23 - Prob. 3APSACh. 23 - Prob. 4APSACh. 23 - Prob. 5APSACh. 23 - Prob. 6APSACh. 23 - Prob. 2BPSBCh. 23 - Prob. 3BPSBCh. 23 - Prob. 4BPSBCh. 23 - Prob. 5BPSBCh. 23 - Prob. 6BPSBCh. 23 - Prob. 23SPCh. 23 - Flexible budgets and standard costs emphasize the...Ch. 23 - Prob. 2AACh. 23 - Prob. 3AACh. 23 - Prob. 1BTNCh. 23 - Prob. 2BTNCh. 23 - Prob. 3BTNCh. 23 - Prob. 4BTNCh. 23 - Prob. 5BTNCh. 23 - Training employees to use standard amounts of...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY