(1)
Compute the direct materials price variance and quantity variance and indicate whether it is favorable or unfavorable.
(1)

Explanation of Solution
Direct material price variance:
The variation in between actual price and estimated price paid for materials is called material price variance. It is used to determine difference in price paid for material the price that was supposed to be paid for material.
The following formula is used to calculate direct material price variance:
Compute the direct materials price variance and indicate whether it is favorable or unfavorable:
Step 1: Calculate the actual cost of direct materials used.
Step 2: Calculate the
Step 3: Calculate the direct materials price variance.
Direct material quantity variance:
The variance which is used to compare the actual quantity of materials utilized in production with estimated quantity of materials that is supposed to be used in production and helps to find variation is called material quantity variance.
The following formula is used to calculate direct material quantity variance:
Compute the direct materials quantity variance and indicate whether it is favorable or unfavorable:
Step 1: Calculate the actual quantity of materials used.
Step 2: Calculate the standard quantity of materials used.
Working note:
Calculate the standard quantity:
Step 3: Calculate the direct materials quantity variance.
Hence, the direct materials price variance is $34,500 (favorable) and direct materials quantity variance is $12,000 (unfavorable).
(2)
Calculate the direct labor rate variances and efficiency variances and indicate whether it is favorable or unfavorable.
(2)

Explanation of Solution
Total Direct Labor Variance
The total direct labor variance is a measure to determine the variation in the standard direct labor and the actual direct labor. This means that the difference between the cost which will be by the standard and the cost which is actually calculated.
Direct Labor Price Variance
The direct labor price variance is a measure that determines the variation in the estimated cost of the direct labor and the actual labor quantity used.
Compute the direct labor rate variances indicate whether it is favorable or unfavorable:
Direct labor efficiency variance is a measure that determines the difference between the estimated labor quantity and the actual labor quantity used.
Compute the direct labor efficiency variance:
Working note:
Calculate the standard direct labor hours used:
Hence, the direct labor rate variance is $3,100 (unfavorable) and the direct labor efficiency variance is $60,000 (unfavorable).
Want to see more full solutions like this?
Chapter 23 Solutions
Principles of Financial Accounting, Chapters 1-17 - With Access (Looseleaf)
- what is the cash flow cycle?arrow_forwardAssume that retained earnings increased by $62,850 from June 30 of year 1 to June 30 of year 2. A cash dividend of $13,500 was declared and paid during the year. Compute the net income for the year.arrow_forwardA company had net sales of $120,000 over the past year. 60% of the sales were credit sales. During that time, average receivables were $6,000. What was the average collection period? (Assume a 360-day year) a) 20 days b) 30 days c) 40 days d) 60 days e) 45 daysarrow_forward
- What is the firm's Return on Assets (ROA)?arrow_forwardGeneral accountingarrow_forwardBlake Enterprises purchased $350,000 worth of land by paying $35,000 cash and signing a $315,000 mortgage. Immediately prior to this transaction, the corporation had assets, liabilities, and owner's equity in the amounts of $200,000, $50,000, and $150,000, respectively. What is the total amount of Blake Enterprises' assets after this transaction has been recorded?arrow_forward
- When an accountant compiles a nonissuer's financial statements that omit substantially all disclosures required by U.S. GAAP, the accountant should indicate in the compilation report that the financial statements area. Restricted for internal use only by the entity's management.b. Not to be given to financial institutions for the purpose of obtaining credit.c. Compiled in conformity with a special purpose framework other than U.S. GAAP.d. Not designed for those who are uninformed about such matters.e. Including omissions not intended to mislead financial statement users. I'm not sure if ots d or e please need your helparrow_forwardwhat is the operation leverage?arrow_forwardNo Aiarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education