Concept explainers
a.
Calculate the
a.
Explanation of Solution
Job order costing: Job order costing is one of the methods of cost accounting under which cost is collected and gathered for each job, work order, or project separately. It is a system by which a factory maintains a separate record of each particular quantity of product that passes through the factory. Job order costing is used when the products produced are significantly different from each other.
Calculate the plant wide overhead rate for job no. 110 using direct labor hours:
Given:
Budgeted Plant wide overhead cost is $250,000
Budgeted department overhead for Department A is $150,000
Budgeted department overhead for Department B is $600,000
Expected direct labor hours for Department A is 35,000 hours
Expected direct labor hours for Department B is 15,000 hours
Calculate the plant wide overhead rate:
Thus, the plant wide overhead rate is $20 per direct labor hour.
Calculate the
Particulars | Amount ($) | Amount ($) |
Direct materials | $25,000 | |
Direct labor for Department A (2,200 hours) | $45,000 | |
Direct labor for Department B | $10,000 | |
Manufacturing overhead | $60,000 | |
Total cost | $140,000 |
Table (1)
Hence, the manufacturing cost is $14 per unit
b.
Recalculate the projected manufacturing
b.
Explanation of Solution
Job order costing: Job order costing is one of the methods of cost accounting under which cost is collected and gathered for each job, work order, or project separately. It is a system by which a factory maintains a separate record of each particular quantity of product that passes through the factory. Job order costing is used when the products produced are significantly different from each other.
Overhead Rate: Overhead rate is a measure used to allocate the estimated overhead cost to the products or job orders during a particular period.
Compute the plant wide overhead rate.
The plant wide overhead rate is $5 per machine hour.
Compute two separate department overhead rates.
Particulars | Department A | Department B |
Budgeted department overhead (A) | $150,000 | $600,000 |
Expected machine hours (B) | 10,000 hours | 40,000 hours |
Overhead rate | $15 per machine hour | $15 per machine hour |
Table (2)
As per Table (2), the overhead rate for both the Departments is $15 per machine hour.
Recalculate the projected manufacturing costs for Job no. 110.
Particulars | Amount ($) | Amount ($) |
Direct materials | $25,000 | |
Direct labor for Department A | $45,000 | |
Direct labor for Department B | $10,000 | |
Manufacturing overhead – Plant | $7,000 | |
Manufacturing overhead – Plant | $3,000 | |
Manufacturing overhead – Plant | $18,000 | |
Total cost | $108,000 |
Table (3)
Hence, the total cost is $10.80 per unit
c.
Determine the bid for job no. 110 using (1) the overhead rate from part a, and (2) the overhead rate from part b and explain the reasons for the differences in bids. Identify the overhead allocation methods that should be recommended and explain the reasons.
c.
Explanation of Solution
Job order costing: Job order costing is one of the methods of cost accounting under which cost is collected and gathered for each job, work order, or project separately. It is a system by which a factory maintains a separate record of each particular quantity of product that passes through the factory. Job order costing is used when the products produced are significantly different from each other.
Overhead Rate: Overhead rate is a measure used to allocate the estimated overhead cost to the products or job orders during a particular period.
Determine the bid price for Job No. 110.
Particulars | Amount |
(1) Bid price using the overhead rate from part a | |
Total cost (Refer Table (1)) | $140,000 |
Add: Increase in percentage by 40% of total cost | $56,000 |
Bid price using the plant wide overhead rate | $196,000 |
(2) Bid price using the overhead rate from part b | |
Manufacturing cost (Refer Table (3)) | $108,000 |
Add: Increase in percentage by 40% of manufacturing cost | $43,200 |
Bid price using the plant wide overhead rate | $151,200 |
Table (4)
Thus, the bid for job no. 110 using (1) Bid price using the overhead rate from part a, and (2) Bid price using the overhead rate from part b is $196,000 and $151,200 respectively.
The bids prices vary due to differences in manufacturing overhead that are applied to the job using the two allocation methods. The two reasons for the changes in overhead are:
- Due to the difference in the time taken to complete by the labor vs. the machine hours.
- Due to the application of single vs. multiple overhead rates.
The allocation method used in Part b would be recommended because the departmental overhead is due mostly to the machine-related expenses. Using multiple-overhead rates allows allocating the expenses that closely reflects the utilization of resources.
d.
Compute the under or over applied overhead for Company G plant during the year and explain the impact on net income of assigning the under or over applied overhead to cost of goods sold rather than prorating the amount between inventories and cost of goods sold.
d.
Explanation of Solution
Job order costing: Job order costing is one of the methods of cost accounting under which cost is collected and gathered for each job, work order, or project separately. It is a system by which a factory maintains a separate record of each particular quantity of product that passes through the factory. Job order costing is used when the products produced are significantly different from each other.
Overhead Rate: Overhead rate is a measure used to allocate the estimated overhead cost to the products or job orders during a particular period.
Determine the applied overhead using machine hours.
Particulars | Amount ($) | Amount ($) |
Plant wide | $262,500 | |
Department A | $157,500 | |
Department B | $630,000 | |
Total overhead applied | $1,050,000 |
Table (5)
Thus, the total overhead applied is $1,050,000. The actual overhead is $1,020,000
e.
Explain whether Company G located in Country SF should buy the $12 per unit part from the subcontractor or continue to make the parts for job no. 110 itself.
e.
Explanation of Solution
The cost per unit computed in part b is $10.80 per unit, which is less than the contractor’s price of $12.00 per unit. Company G should continue to make parts for Job No. 110 for themselves in the committed bid price.
f.
Identify the change required in Part e if the plant located in country SF could use the facilities necessary to produce parts for job no. 110 for another job that could earn an incremental profit of $20,000
f.
Explanation of Solution
If the parts are bought from the subcontractor, then the incremental cost would be $12,000
g.
Identify the additional international environmental issues, other than price that would be required to be evaluated by the management of Company G in Location SF.
g.
Explanation of Solution
The legal/political, economic, cultural, and technological environmental categories affect international operations. In the economic category, an important problem is the exchange rate transaction risk, which would be determined by whether the contracts are denominated in U.S. dollars or Mexican pesos.
In a legal/political category, issues include NAFTA regulations and the general risk that are undertaken by carrying out business in a politically less stable environment. The impact of import duties and possibly higher shipping costs on profits should also be taken into consideration.
Finally, the skill level of the labor force in terms of producing a high-quality product should also be a considered.
h.
Identify the types of changes that would be required to make the approach successful if Company G decides to undertake a target costing approach to pricing its jobs.
h.
Explanation of Solution
Target cost: In a competitive market, companies cannot set prices because the supply and demand factors affect the product price. The companies should therefore, control costs, in order to earn a desired profit.
To successfully implement target costing, Company G would need to adopt a more customer-oriented approach. The marketing department of Company G would need to determine the prices, the customers are willing to pay for the products of Company G. Under this approach, target returns would need to be determined so that the target costs can be calculated
Want to see more full solutions like this?
Chapter 21 Solutions
GEN COMBO FINANCIAL & MANAGERIAL ACCOUNTING; CONNECT ACCESS CARD
- Boss Corporation is a wholesaler that sells a single product. Management has provided the following cost data for two levels of monthly sales volume. The company sells the product for $197.80 per unit. Sales Volume (units) Cost of sales Selling and administrative costs 6000 7000 $ 4,86,600 $ 5,67,700 $ 6,12,600 $6,24,400 The best estimate of the total monthly fixed cost is: A. $541,800. B. $1,192,100. C. $1,099,200. D. $1,145,650.arrow_forwardThe output of a company assembly answer this general accounting questionarrow_forwardDomebo Corporation has entered into a 8 year lease for a piece of equipment. The annual payment under the lease will be $3,200, with payments being made at the beginning of each year. If the discount rate is 14%, the present value of the lease payments is closest to (Ignore income taxes.): view Exhibit 14B-1 and Exhibit 14B-2, to determine the appropriate discount factor(s) using the tables provided.Round your intermediate calculations to 3 decimal places.arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education