Chapter 21, Problem 3AE
Summary Introduction

Case summary:

Person PH, the production control manager was interested in time-phased requirements schedule. The first step for his idea was to develop a master schedule for one engine type produced by Company BM. Person PH decided to develop a materials requirement planning for the product.

To develop: A better schedule by reducing the number of orders and carrying some amount of inventory and identify the cost savings with the new schedule.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given information:

Model 1000 Master Schedule

Operations and Supply Chain Management (Mcgraw-hill Education), Chapter 21, Problem 3AE , additional homework tip  1

Model 1000 Product Structure

Operations and Supply Chain Management (Mcgraw-hill Education), Chapter 21, Problem 3AE , additional homework tip  2

  • There are 17 gearboxes on-hand at the beginning of week 1. 5 gearboxes are on order and should be delivered at the beginning of week 2.
  • There are 40 input shafts present on-hand at the beginning of week 1, and 22 are scheduled to be delivered at the beginning of week 2.

Cost:

Gearbox:

Setup cost (S)             = $90 per order.

Inventory carrying cost (I)     = $2 per unit per week.

Input shaft:

Setup cost (S)             = $45 per order.

Inventory carrying cost (I)     = $1 per unit per week.

Existing schedule:

Operations and Supply Chain Management (Mcgraw-hill Education), Chapter 21, Problem 3AE , additional homework tip  3

Each gearbox will require two units of the input shaft. Hence, the planned order release of the gearbox is doubled when they become the gross requirements of the input shaft.

Calculation of cost of the schedule:

Gearbox:

There are 8 planned order releases. The inventory is 2 units in week 1 and 2 units in week 2. Therefore, the total cost would be:

Total cost=Setup cost+Inventory carrying cost=(8 orders×S)+((2+2)×I)=(8×$90)+((2+2)×$2)=$720+$8=$728

Input shaft:

There are 5 planned order releases. The inventory is 30 units in week 1, 32 units in week 2, 32 units in week 3, and 2 units in week 4. Therefore, the total cost would be:

Total cost=Setup cost+Inventory carrying cost=(5 orders×S)+((30+32+32+2)×I)=(5×$45)+((30+32+32+2)×$1)=$225+$96=$321

The total cost of the schedule would be:

Total cost of schedule=$728+$321=$1,049

The cost of the existing schedule is $1,049.

Calculation of net requirements and planned order release for the new schedule:

Operations and Supply Chain Management (Mcgraw-hill Education), Chapter 21, Problem 3AE , additional homework tip  4

In order to reduce the number of orders, the planned order releases of three weeks are combined together and released with a lead time of 2 weeks while carrying some amount of inventory.

Formula:

Operations and Supply Chain Management (Mcgraw-hill Education), Chapter 21, Problem 3AE , additional homework tip  5

Calculation of cost of the schedule:

Gearbox:

There are 3 planned order releases. The inventory is 2 units in week 1, 2 units in week 2, 10 units in week 3, 30 units in week 6, 10 units in week 7, 18 units in week 11, and 16 units in week 12. Therefore, the total cost would be:

Total cost=Setup cost+Inventory carrying cost=(3 orders×S)+((2+2+10+30+10+18+16)×I)=(3×$90)+((2+2+10+30+10+18+16)×$2)=$270+$176=$446

Input shaft:

There are 2 planned order releases. The inventory is 10 units in week 1, 32 units in week 2, and 32 units in week 3. Therefore, the total cost would be:

Total cost=Setup cost+Inventory carrying cost=(2 orders×S)+((10+32+32)×I)=(2×$45)+((10+32+32)×$1)=$90+$74=$164

The total cost of the schedule would be:

Total cost of schedule=$446+$164=$610

The cost of the new schedule is $610.

Calculation the cost difference between the two schedules:

Cost difference=$1,049+$610=$439

The cost savings with the new schedule is $439.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY