ACCT.PRINCIPLES-WILEYPLUS NEXTGEN
14th Edition
ISBN: 9781119709954
Author: Weygandt
Publisher: WILEY
expand_more
expand_more
format_list_bulleted
Question
Chapter 21, Problem 20E
To determine
Job order costing is a cost evaluation method that considers each job separate and assign cost to them. It is mostly applicable in the service industry wherein every job has a separate requirement.
To prepare: Production cost report of the company.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The assembly division of Quality Time Pieces, Inc. uses the FIFO method of process costing. Consider the following data for May 2020:
(Click the icon to view the data.)
Requirement
Compute equivalent units for direct materials and conversion costs. Show physical units in the first column of your schedule.
Enter the physical units in first, then calculate the equivalent units.
Flow of Production
Work in process, beginning
Started during current period
To account for
Completed and transferred out during current period:
From beginning work in process
Started and completed
Work in process, ending
Accounted for
Equivalent unts of work done in current period
Physical
Units
Data table
Beginning work in process (May 1)ª
Started in May 2020
Physical Units
(Watches)
100
510
450
160
Print
Completed during May 2020
Ending work in process (May 31)b
Total costs added during May 2020
a Degree of completion: direct materials, 80%; conversion costs, 35%.
Degree of completion: direct materials, 80%;…
The assembly division of Quality Time Pieces, Inc. uses the weighted-average method of process costing. Consider the following data for May 2020:
(Click the icon to view the data.)
Requirement
Compute equivalent units for direct materials and conversion costs. Show physical units in the first column of your schedule.
Enter the physical units first, then calculate the equivalent units.
Flow of Production
Work in process beginning
Started during current period
To account for
Completed and transferred out during current period
Work in process, ending
Accounted for
Equivalent units of work done to date
Physical
Units
Data table
Beginning work in process (May 1)ª
Started in May 2020
Completed during May 2020
Ending work in process (May 31)
Total costs added during May 2020
Physical Units
Direct
(Watches) Materials
100
$459,888
Print
510
450
160
$3,237,000
aDegree of completion: direct materials, 80%; conversion costs, 35%.
bDegree of completion: direct materials, 80%; conversion costs, 40%.…
In using FIFO method, Cruz Company produces a product that undergoes three processes and the completed items at end of process 3 are the items to be sold to customers. For December 2021, Cruz Company presented the following costs on three processes:
What is the equivalent units of production (EUP) on Materials in Department 1?
15,000
15,100
16,000
14,200
What is the equivalent units of production (EUP) on Materials in Department 2?
15,100
15,000
15,150
14,800
Chapter 21 Solutions
ACCT.PRINCIPLES-WILEYPLUS NEXTGEN
Ch. 21 - Prob. 1QCh. 21 - Prob. 2QCh. 21 - Prob. 3QCh. 21 - Prob. 4QCh. 21 - Prob. 5QCh. 21 - Prob. 6QCh. 21 - Prob. 7QCh. 21 - Prob. 8QCh. 21 - Prob. 9QCh. 21 - Prob. 10Q
Ch. 21 - Prob. 11QCh. 21 - Prob. 12QCh. 21 - Prob. 13QCh. 21 - Prob. 14QCh. 21 - Prob. 15QCh. 21 - Prob. 16QCh. 21 - Prob. 17QCh. 21 - Prob. 18QCh. 21 - Prob. 19QCh. 21 - Prob. 20QCh. 21 - Prob. 21QCh. 21 - Prob. 22QCh. 21 - Prob. 1BECh. 21 - Prob. 2BECh. 21 - Prob. 3BECh. 21 - Prob. 4BECh. 21 - Prob. 5BECh. 21 - Prob. 6BECh. 21 - Prob. 7BECh. 21 - Prob. 8BECh. 21 - Prob. 9BECh. 21 - Prob. 10BECh. 21 - Prob. 11BECh. 21 - Prob. 12BECh. 21 - Prob. 1DIECh. 21 - Prob. 2DIECh. 21 - Prob. 3DIECh. 21 - Prob. 4DIECh. 21 - Prob. 1ECh. 21 - Prob. 2ECh. 21 - Prob. 3ECh. 21 - Prob. 4ECh. 21 - Prob. 5ECh. 21 - Prob. 6ECh. 21 - Prob. 7ECh. 21 - Prob. 8ECh. 21 - Prob. 9ECh. 21 - Prob. 10ECh. 21 - Prob. 11ECh. 21 - Prob. 12ECh. 21 - Prob. 13ECh. 21 - Prob. 14ECh. 21 - Prob. 15ECh. 21 - Prob. 17ECh. 21 - Prob. 18ECh. 21 - Prob. 19ECh. 21 - Prob. 20ECh. 21 - Prob. 1PSACh. 21 - Prob. 2PSACh. 21 - Prob. 3PSACh. 21 - Prob. 4PSACh. 21 - Prob. 5PSACh. 21 - Prob. 6PSACh. 21 - Prob. 7PSACh. 21 - Prob. 2EYCTCh. 21 - Prob. 5EYCTCh. 21 - Prob. 6EYCT
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Please use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: It estimates there will be five orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardPlease use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: Box Springs estimates there will be four orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardThe cost accountant for River Rock Beverage Co. estimated that total factory overhead cost for the Blending Department for the coming fiscal year beginning February 1 would be 3,150,000, and total direct labor costs would be 1,800,000. During February, the actual direct labor cost totalled 160,000, and factory overhead cost incurred totaled 283,900. a. What is the predetermined factory overhead rate based on direct labor cost? b. Journalize the entry to apply factory overhead to production for February. c. What is the February 28 balance of the account Factory OverheadBlending Department? d. Does the balance in part (c) represent over- or underapplied factory overhead?arrow_forward
- Aero Aluminum Inc. uses a process cost system. The records for May show the following information: Required: Prepare a cost of production summary for each department. (Hint: When preparing the Converting production summary, refer to the Rolling production summary for the costs transferred in during the month.)arrow_forwardUsing the same data found in Exercise 6.22, assume the company uses the FIFO method. Required: Prepare a schedule of equivalent units, and compute the unit cost for the month of December. Fordman Company has a product that passes through two processes: Grinding and Polishing. During December, the Grinding Department transferred 20,000 units to the Polishing Department. The cost of the units transferred into the second department was 40,000. Direct materials are added uniformly in the second process. Units are measured the same way in both departments. The second department (Polishing) had the following physical flow schedule for December: Costs in beginning work in process for the Polishing Department were direct materials, 5,000; conversion costs, 6,000; and transferred in, 8,000. Costs added during the month: direct materials, 32,000; conversion costs, 50,000; and transferred in, 40,000.arrow_forwardKokomo Kayak Inc. uses the process cost system. The following data, taken from the organizations books, reflect the results of manufacturing operations during the month of March: Production Costs Work in process, beginning of period: Costs incurred during month: Production Data: 18,000 units finished and transferred to stockroom. Work in process, end of period, 3,000 units, two-thirds completed. Required: Prepare a cost of production summary for March.arrow_forward
- Holmes Products, Inc., produces plastic cases used for video cameras. The product passes through three departments. For April, the following equivalent units schedule was prepared for the first department: Costs assigned to beginning work in process: direct materials, 90,000; conversion costs, 33,750. Manufacturing costs incurred during April: direct materials, 75,000; conversion costs, 220,000. Holmes uses the weighted average method. Required: 1. Compute the unit cost for April. 2. Determine the cost of ending work in process and the cost of goods transferred out.arrow_forwardThe assembly division of Fenton Watches, Inc. uses the FIFO method of process costing. Consider the following data for May 2020: (Click the icon to view the data.) (Click the icon to view the equivalent unit computation.) Requirement Summarize total costs to account for, calculate cost per equivalent unit for direct materials and conversion costs, and assign costs to units completed (and transferred out) and to units in ending work-in-process inventory. Begin by summarizing total costs to account for. Total costs to account for Total CH Production Costs Direct Materials Conversion Costsarrow_forward. In Ramirez Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2020 are as follows. Beginning Work in Process Month Beginning Work in Process Units Transferred Out Units % Complete as to Conversion Cost September 0 2,000 7,000 60 December 0 3,000 12,000 30 Compute the equivalent units of production for (1) materials and (2) conversion costs for each month.arrow_forward
- Zoey Company produces a product that undergoes three processes and the completed items at end of process 3 are the items to be sold to customers.. For November 2021, Masipag Company presented the following costs on three processes: A. What is the total units to account for (TUTAF) in Department 1? 23,500 22,500 25,000 21,750 B. What is the equivalent units of production (EUP) on Materials in Department 1? 23,500 20,000 25,000 22,500arrow_forward1arrow_forwardIn using average method, Cruz Company produces a product that undergoes three processes and the completed items at end of process 3 are the items to be sold to customers. For October 2021, Cruz Company presented the following costs on three processes: What is the total costs of work in process at October 31, 2021 in Department C? P 43,900 P 50,980 P141,800 P 46,920arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeExcel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Job Cost Sheet - Job Cost Accounting System; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=ElD8nKNXE1I;License: Standard Youtube License