Chapter 20, Problem 20.4P

Repeat Problem 20.2 based on LRFD using the following factors.

Load factor for dead load = 1.25

Load factor for live load = 1.75

Strength reduction factor on the ultimate bearing capacity = 0.50

20.2 A continuous foundation is required in a soil where c′ = 10 kN/m2, ϕ = 26 ° and γ = 19.0 kN/m3. The depth of the foundation will be 1.0 m. The dead load and the live load are 600 kN/m and 400 kN/m, respectively. Determine the required width for the foundation based on allowable stress design with FS = 3, using Eq. (16.3) and Table 16.1.

Blurred answer
Students have asked these similar questions
subject
In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m3 by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m3, ma a decision about choosing the economical equipment to use in the project.
/ An irrigation project requires digging and paving an irrigation canal with alength of (30 km) and a semi-circular section with a diameter of (8 m). The work mustmbe completed within one year, and in the event of delay, a fine delay of $200/day. You have two options for work: 1st Option: using standard equipment (excavators, graders and hand labor) had a cost of $10/m3, the job will be finish without delay. 2nd Option: Use a channel trimmer machine with the following specifications: Purchase price ($70,000), it can be sold after its economic life of (5 years) for ($30,000), its speed (10m/hr), engine diesel with (250 hp) and its work 48 minutes/hr, capacity of crankcase is (50 liters), the number of hours between changing the oil (100 hr), the maintenance cost is (80%) of its depreciation, the price of one liter of fuel ($0.5/liter) and of oil ($1/liter), the operators' wages ($15,000/year), annual operating hours (2000 hr), and the owner must pay taxes of 10% of the average value of…
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Types of Foundation in building construction in detail - Civil Engineering Videos; Author: Civil Engineers;https://www.youtube.com/watch?v=7sl4KuM4UIE;License: Standard YouTube License, CC-BY
Types of Foundation || Foundation Engineering; Author: Civil Engineering;https://www.youtube.com/watch?v=AFLuAKGhanw;License: Standard Youtube License