Question
Book Icon
Chapter 2, Problem 1RQ
To determine

The main objectives of the estimating department in a construction company.

Expert Solution & Answer
Check Mark

Explanation of Solution

Introduction:

Developing an estimateincludes interactions with large number of people and dealing with a vast data. The estimating team will be able to produce efficient estimate by following well organized estimating procedures.

The main objectives of estimating department in a construction company are as follows.

  • To prepare construction cost estimates that allow the contractor to choose profitable work by competitive bidding process.
  • To check and verify the work which maximizes the accuracy of the estimate.
  • To generate the highest volume of the estimating work with the available resources to maximize the productivity.
  • To ensure that the project is most likelihood of success.
  • To provide a good atmosphere and a cooperative approach to the team within the estimating area that benefits the entire organization.

Conclusion:

Thus, the main objectives of the estimating department in a construction company are described above.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
5-1. Determine the force in each member of the truss, and state if the members are in tension or compression.
I have the correct answer provided, just lookng for a more detailed breadown of how the answer was obtained thanks.
Q1. Statically indeterminate beam analysis. a) Calculate the BMs (bending moments) at all the joints of the beam shown in Fig.1 using the moment distribution method. The beam is subjected to an UDL of w kN/m. L1= 0.4L. Assume the support at C is pinned, and A and B are roller supports. E = 200 GPa, I=250x106 mm². Use the values of w = 50 kN/m and L = 6 b) Draw the shear force and bending diagrams for the entire beam. c) Calculate the BMs at all the joints of the same beam shown in Fig.1 using the slope deflection method. d) Compare the values of BMs obtained using the two methods a) and c) and comment. w kN/m £1m Lm m Fig 1. Beam for Q1
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning
Text book image
Residential Construction Academy: House Wiring (M...
Civil Engineering
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Cengage Learning
Text book image
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning