Textbook Question
Chapter 2, Problem 16P
PROBLEM 2—16 Plantwide Predetermined
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates:
Direct labor-hours required to support estimated production | 140,000 |
Machine-hours required to support estimated production | 70,000 |
Fixed manufacturing overhead cost | $784,000 |
Variable manufacturing overhead cost per direct labor-hour | $2.00 |
Variable manufacturing overhead cost per machine-hour | $4.00 |
During the year, Job 550 was started and completed. The following information is available with respect to this job:
Direct materials | $175 |
Direct labor cost | $225 |
Direct labor-hours | 15 |
Machine-hours | 5 |
Required:
- Assume that Landen has historically used a plantwide predetermined overhead rate with direct labor-hours as the allocation base. Under this approach:
- Compute the planide predetermined overhead rate.
- Compute the total
manufacturing cost of Job 550. - If Landen uses a markup percentage of 200% of its total manufacturing cost, what selling price would it establish for Job 550?
- Assume that Landen’s controller believes that machine-hours is a better allocation base than direct labor-hours. Under this approach:
- Compute the planPide predetermined overhead rate.
- Compute the total manufacturing cost of Job 550.
- If Landen uses a markup percentage of 200% of its total manufacturing cost, what selling price would it establish for Job 550?
- Assume that Landen’s controller is right about machine-hours being a more accurate overhead cost allocation base than direct labor-hours. If the company continues to use direct labor-hours as its only overhead cost allocation base what implications does this have for pricing jobs such as Job 550?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Problem 2-16 (Algo) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3]
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates:
Direct labor-hours required to support estimated production
60,000
Machine-hours required to support estimated production
30,000
Fixed manufacturing overhead cost
$ 180,000
Variable manufacturing overhead cost per direct labor-hour
$ 1.00
Variable manufacturing overhead cost per machine-hour
$ 2.00
During the year, Job 550 was started and completed. The following information is available with respect to this job:
Direct materials
$ 213
Direct labor cost
$ 323
Direct labor-hours
15
Machine-hours
5
Required:
1. Assume that Landen has historically used a plantwide predetermined overhead rate with direct labor-hours as the allocation base. Under this approach:
a. Compute the plantwide predetermined overhead rate.
b. Compute the total…
Question 8?
es
Problem 2-16 (Algo) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3]
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates:
Direct labor-hours required to support estimated production
Machine-hours required to support estimated production
Fixed manufacturing overhead cost
Variable manufacturing overhead cost per direct labor-hour
Variable manufacturing overhead cost per machine-hour
During the year, Job 550 was started and completed. The following information is available with respect to this job:
Direct materials
Direct labor cost
Direct labor-hours
Machine-hours
$187
$ 370
15
110,000
55,000
$ 308,000
5
$ 3.20
$ 6.40
Required:
1. Assume that Landen has historically used a plantwide predetermined overhead rate with direct labor-hours as the allocation base.
Under this approach:
a. Compute the plantwide predetermined overhead rate.
b. Compute the total manufacturing cost of Job 550.
c. If Landen…
Chapter 2 Solutions
Managerial Accounting
Ch. 2.A - EXERCISE 2A-1 Activity-Based Absorption Costing...Ch. 2.A - EXERCISE 2A-2 Activity-Based Absorption Costing as...Ch. 2.A - EXERCISE 2A-3 Activity-Based Absorption Costing as...Ch. 2.A - PROBLEM 2A-4 Activity-Based Absorption Costing as...Ch. 2.A - Prob. 5PCh. 2.A -
CASE 2A-6 Activity-Based Absorption Costing and...Ch. 2.B - EXERCISE 2B-1 Overhead Rate Based on Capacity...Ch. 2.B - EXERCISE 2B-2 Overhead Rates and Capacity Issues...Ch. 2.B - Prob. 3PCh. 2.B - Prob. 4C
Ch. 2 - Prob. 1QCh. 2 - What is absorption costing?Ch. 2 - What is normal costing?Ch. 2 - How is the unit product cost of a job calculated?
Ch. 2 - Explain the four-step process used to compute a...Ch. 2 - What is the purpose of the job cost sheet in a...Ch. 2 - Explain why some production costs must be assigned...Ch. 2 - Why do companies use predetermined overhead rates...Ch. 2 - What factors should be considered in selecting an...Ch. 2 - If a company fully allocates all of its overhead...Ch. 2 - Would you expect the amount of applied overhead...Ch. 2 - Prob. 12QCh. 2 - What is a plantwide overhead rate? Whyare multiple...Ch. 2 - This Excel worksheet relates to the Dickson...Ch. 2 - This Excel worksheet relates to the Dickson...Ch. 2 - Prob. 3AECh. 2 - This Excel worksheet relates to the Dickson...Ch. 2 - Prob. 1F15Ch. 2 - Prob. 2F15Ch. 2 - Prob. 3F15Ch. 2 - Prob. 4F15Ch. 2 - Prob. 5F15Ch. 2 - Prob. 6F15Ch. 2 - Prob. 7F15Ch. 2 - Prob. 8F15Ch. 2 - Prob. 9F15Ch. 2 - Prob. 10F15Ch. 2 - Prob. 11F15Ch. 2 - Sweeten Company had no jobs in progress at the...Ch. 2 - Prob. 13F15Ch. 2 - Prob. 14F15Ch. 2 - Prob. 15F15Ch. 2 - EXERCISE 2-1 Compute a Predetermined Overhead Rate...Ch. 2 - Prob. 2ECh. 2 - EXERCISE 2–3 Computing Total Job Costs and Unit...Ch. 2 - EXERCISE 24 Computing Total Job Costs and Unit...Ch. 2 - EXERCISE 2-5 Computing Total Job Costs and Unit...Ch. 2 - Prob. 6ECh. 2 - EXERCISE 2-7 Job-Order Costing; Working Backwards...Ch. 2 - EXERCISE 2-8 Applying Overhead Cost; Computing...Ch. 2 - EXERCISE 2–9 Job-Order Costing and Decision Making...Ch. 2 - Prob. 10ECh. 2 - Prob. 11ECh. 2 - Prob. 12ECh. 2 - EXERCISE 2—13 Departmental Predetermined Overhead...Ch. 2 - EXERCISE 214 Job-Orders Costing for a Service...Ch. 2 - Prob. 15ECh. 2 - PROBLEM 2—16 Plantwide Predetermined Overhead...Ch. 2 - PROBLEM 217 Plantwide and Departmental...Ch. 2 - Prob. 18PCh. 2 - Prob. 19PCh. 2 - Prob. 20PCh. 2 - PROBLEM 2-21 Plant wide Versus Multiple...Ch. 2 - CASE 2-22 Plantwide versus Departmental Overhead...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Overhead application rate Roll Tide Manufacturing Inc. uses a job order cost system and standard costs. It manufactures one product, whose standard cost follows: The standards are based on normal capacity of 2,700 direct labor hours. Actual activity for March follows: Required: 1. Compute the variable and fixed factory overhead rates per unit. 2. Compute the variable and fixed overhead rates per direct labor hour. 3. Determine the total fixed factory overhead based on normal capacity.arrow_forwardPREDETERMINED FACTORY OVERHEAD RATE Millerlile Enterprises calculates a predetermined factory overhead rate so that factory overhead may be applied to production during the month. It calculates the overhead using three different methods and then decides which one to use. Total estimated factory overhead costs are 540,000. Total estimated direct labor hours are 50,000. Total estimated direct labor costs are 900,000. Total machine hours are estimated to be 80,000. Calculate the predetermined overhead application rates based on (1) direct labor hours, (2) direct labor costs, and (3) machine hours.arrow_forwardOverhead application rate Creole Manufacturing Inc. uses a job order cost system and standard costs. It manufactures one product, whose standard cost follows: The standards are based on normal capacity of 2,400 direct labor hours. Actual activity for October follows: Required: 1. Compute the variable and fixed factory overhead rates per unit. 2. Compute the variable and fixed overhead rates per direct labor hour. 3. Determine the total fixed factory overhead based on normal capacity.arrow_forward
- PREDETERMINED FACTORY OVERHEAD RATE Marston Enterprises calculates a predetermined factory overhead rate so that factory overhead may be applied to production during the month. It calculates the overhead using three different methods and then decides which one to use. Total estimated factory overhead costs are 600,000. Total estimated direct labor hours are 30,000. Total estimated direct labor costs are 1,200,000. Total machine hours are estimated to be 200,000. Calculate the predetermined overhead application rates based on (1) direct labor hours, (2) direct labor costs, and (3) machine hours.arrow_forwardCost Flows Consider the following independent jobs. Overhead is applied in Department 1 at the rate of 6 per direct labor hour. Overhead is applied in Department 2 at the rate of 8 per machine hour. Direct labor wages average 10 per hour in each department. Required: Fill in the missing data for each job.arrow_forwardApplying factory overhead Bergan Company estimates that total factory overhead costs will be 620,000 for the year. Direct labor hours are estimated to be 80,000. For Bergan Company, (A) determine the predetermined factory overhead rate using direct labor hours as the activity base, (B) determine the amount of factory overhead applied to Jobs 200 and 305 in May using the data on direct labor hours from BE 16-2, and (C) prepare the journal entry to apply factory overhead to both jobs in May according to the predetermined overhead rate.arrow_forward
- (Appendix 3A) Method of Least Squares Using Computer Spreadsheet Program The controller for Beckham Company believes that the number of direct labor hours is associated with overhead cost. He collected the following data on the number of direct labor hours and associated factory overhead cost for the months of January through August. Required: 1. Using a computer spreadsheet program such as Excel, run a regression on these data. Print out your results. 2. Using your results from Requirement 1, write the cost formula for overhead cost. (Note: Round the fixed cost to the nearest dollar and the variable rate to the nearest cent.) 3. CONCEPTUAL CONNECTION What is R2 based on your results? Do you think that the number of direct labor hours is a good predictor of factory overhead cost? 4. Assuming that expected September direct labor hours are 700, what is expected factory overhead cost using the cost formula in Requirement 2?arrow_forwardFactory overhead rate Fabricator Inc., a specialized equipment manufacturer, uses a job order cost system. The overhead is allocated to jobs on the basis of direct labor hours. The overhead rate is now $3,000 per direct labor hour. The design engineer thinks that this is illogical. The design engineer has stated the following: Our accounting system doesn't make any sense to me. It tells me that every labor hour carries an additional burden of $3,000. This means that while direct labor makes up only 5% of our total product cost, it drives all our costs. In addition, these rates give my design engineers incentives to "design out" direct labor by using machine technology. Yet, over the past years as we have had less and less direct labor, the overhead rate keeps going up and up. I won't be surprised if next year the rate is $4,000 per direct labor hour. I'm also concerned because small errors in our estimates of the direct labor content can have a large impact on our estimated costs. Just a 30~minute error in our estimate of assembly time is worth $ 1,500. Small mistakes in our direct labor time estimates really swing our bids around. I think this puts us at a disadvantage when we are going after business. What did the engineer mean about the large overhead rate being a disadvantage when plating bids and seeking new business?arrow_forwardFactory overhead rate Fabricator Inc., a specialized equipment manufacturer, uses a job order cost system. The overhead is allocated to jobs on the basis of direct labor hours. The overhead rate is now $3,000 per direct labor hour. The design engineer thinks that this is illogical. The design engineer has stated the following: Our accounting system doesn't make any sense to me. It tells me that every labor hour carries an additional burden of $3,000. This means that while direct labor makes up only 5% of our total product cost, it drives all our costs. In addition, these rates give my design engineers incentives to "design out" direct labor by using machine technology. Yet, over the past years as we have had less and less direct labor, the overhead rate keeps going up and up. I won't be surprised if next year the rate is $4,000 per direct labor hour. I'm also concerned because small errors in our estimates of the direct labor content can have a large impact on our estimated costs. Just a 30~minute error in our estimate of assembly time is worth $ 1,500. Small mistakes in our direct labor time estimates really swing our bids around. I think this puts us at a disadvantage when we are going after business. What do you think is a possible solution?arrow_forward
- Problem 2-18 (Algo) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses job-order costing. At the beginning of the year, it made the following estimates: Direct labor-hours required to support estimated production Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per direct labor-hour Variable manufacturing overhead cost per machine-hour During the year, Job 550 was started and completed. The following information pertains to this job: Direct materials Direct labor cost Direct labor-hours. Machine-hours $ 195 $288 150,000 75,000 $ 420,000 15 5 $ 4.60 $ 9.20 Required: 1. Assume Landen has historically used a plantwide predetermined overhead rate with direct labor-hours as the allocation base. Under this approach: a. Compute the plantwide predetermined overhead rate. b. Compute the total manufacturing cost of Job 550. c. If Landen uses a markup percentage of 200% of its…arrow_forwardQUESTION 1 Richards Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 50,000 direct labor-hours, total fixed manufacturing overhead cost of $390,000, and a variable manufacturing overhead rate of $4.40 per direct labor-hour. Job X941, which was for 50 units of a custom product, was recently completed. The job cost sheet for the job contained the following data: Total direct labor-hours Direct materials Direct labor cost Required: Show your calculations to get full credit. Calculate the total budgeted overhead for the year. la 1b 1c 1d Calculate the predetermined overhead rate for the year. Calculate the total manufacturing cost of job X941 Calculate the total selling price for Job X941 if the company marks up its unit product costs by 20%. 300 $600 $7,000 Darrow_forwardChapter 8 Accounting for Factory Overhead 253 Hackers Corp. accumulated the following information for its two products, A and B. Product A Product B Total Production volume Total direct labor hours Setup cost per batch Batch size 2,000 5,000 P 1,000 100 P20,000 2. A traditional costing system would allocate set-up costs on the basis of direct labor hours. An ABC system would trace costs by spreading the cost per batch over the 1,000 20,000 P 2,000 50 P40,000 1 25,000 Total set-up cost incurred Direct labor hour-per unit P60,000 units in a batch. 19. What is the set-up cost per unit.of Product A under each costing system? Traditional ABC System a.. P4.80 P10.00 b. 2.40 10.00 C. 40.00 200.00 d. 4.80 20.00arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- College Accounting, Chapters 1-27AccountingISBN:9781337794756Author:HEINTZ, James A.Publisher:Cengage Learning,Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningFinancial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
College Accounting, Chapters 1-27
Accounting
ISBN:9781337794756
Author:HEINTZ, James A.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License