Concept explainers
A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project?
- a. 3 days, because this is the minimum time
- b. 7 days, because this is the maximum time
- c. 20 days, because this is the sum of the times
- d. It is not possible to determine the total completion time from the given information.
To determine: The total completion time for the project.
Answer to Problem 1CQ
D. It is not possible to determine the total completion time from the given information.
Explanation of Solution
Given information:
Four activities of a project take 4, 3, 6 and 7 days respectively.
The given scenario lacks basic information to find the completion time of the project. Details like precedence relationship is not given which makes it impossible to find the sequence of activities in which the project must be done.
Want to see more full solutions like this?
Chapter 19 Solutions
Operations Management
Additional Business Textbook Solutions
Horngren's Accounting (12th Edition)
Financial Accounting, Student Value Edition (5th Edition)
Marketing: An Introduction (13th Edition)
Engineering Economy (17th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
- Given a project with three paths and their corresponding path lengths: A-B-C: 25 days, A-D-F: 15 days, and B-C-D-E: 20 days; which of the following statements is TRUE? * Activity B has the most slack The expected duration of the project is 60 days The earliest project completion time is 15 days The critical activities are A, B and Carrow_forwardWhat is the relationship between the earliest start time (EST) of an activity and the earliest completion time (ECT) of the activity? a. EST + Activity time = ECT b. EST × Activity time = ECTc. EST = ECT d. None of these statements is correct.arrow_forwardConsider a project to produce custom door moldings for GMC Acadia cross-over vehicles, described in Tablea. If you start the project immediately, when will it be finished?b. You are interested in completing your project as soon as possible. You have only one option. Suppose you could assign Employee A, currently assigned to activity G, to help Employee B, currently assigned to activity F. Each week that Employee A helps Employee B will result in activity G increasing its time by one week and activity F reducing its time by one week. How many weeks should Employee A work on activity F?arrow_forward
- Key: A is optimist time, M is the most likely time and B is the pessimistic time. i). Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information above iii. State the critical path and the maximum number of weeks the project will take to be completed. iv. Discuss the pros and cons of using the Gantt chart as a planning and scheduling tool?arrow_forward1.What’s the maximum amount of time that activity F can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value). 2. What’s the maximum amount of time that activity D can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value). 3.What’s the maximum amount of time that activity C can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value). 4. What’s the earliest expected time, in months, to finish the project? (Whole number, no space, no commas, no decimal value).arrow_forwardNormal completion time and accelerated completion time Steps that can be taken to crash the project to the shortest time at the lowest cost. Hint: Determine each step's cost and the duration of the project at that stage.arrow_forward
- 2:30 PM ě 4G+ 0.6KB/s l 54 00:15:19 Remaining Multiple Choice PERT is different from CPM in 'that unlike CPM, PERT is a network technique PERT uses probabilities on the activity times, whereas CPM uses deterministic time and cost estimates. PERT considers crash efforts and costs, while CPM does not PERT may be thought of as a mere subset of CPM. 12 of 20arrow_forward1. What’s the maximum amount of time that activity G can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value). 2.What’s the maximum amount of time that activity A can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value) 3. What’s the maximum amount of time that activity H can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value)arrow_forwardA project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(4, 8, 12 ), B( 3, 6, 9 ), C( 1, 2, 3 ), D( 6, 12, 18 ) weeks. What probability would you assign to a project duration of more than 14 weeks? O a. 0.402 O b. 0.949 O c. 0.75 O d. 0.5arrow_forward
- . True/False Statements (Tick the correct option) Selection of the critical path in network activity diagram for any project, is always focused onresult of the minimum time duration of the critical activities [ True / False ] Suppose, we have total 03 activities in the project “X”; namely L, M and N respectively. An activity “M” is the immediate successor of the activity “L”, while the activity “M” is the immediate predecessor for the activity “N”. According to this scenario, an activity “M” will be the last activity of the project “X” in the network activity diagram [True / False ] The dummy activity consumes both time and resources [True / False ] Towards the optimal solution through stepping stone method, when degeneracy problem is occurred, the next step is to focus on searching lowest value on the independent position in a non-allocated cells [True / False ] Hungarian algorithm, first convert any given assignment matrix into row reduction matrix [True / Falsearrow_forwardJohn, Jack and Jill are project managers for Jusco Company. All three of them lead their own team, with two supervisors working under them. John’s team has 10 members, Jack has 8 members in his team and Jill has 11 members under his care. Both John and Jack completed their projects on time with the same amount of allocated budgets from top managers. But Jill didn’t manage to complete the project on time this time round. (i) Assuming all three projects have the same scale in terms of size, quality,and complexity, what can we conclude about the effectiveness and efficiency of these three project managers based on the informationabove? Justify your answers PLEASE PROVIDE CLEAR EXPLANATION THANK YOU , THIS TOPIC IS UNDER EVOLUTION OF FUNDAMENTAL MANAGEMENT THEORIESarrow_forwardWhat is the least expensive method of halting some tasks in order to keep the project's (estimated) duration within the set range ?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.