Question
Chapter 17, Problem 16RE
16 (a)
To determine
Compute the total estimated costs for the contract.
(b)
To determine
Compute the amount of revenue to date.
(c)
To determine
Compute the amount of gross profit recognized.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Topic: REVENUE FROM CONTRACTS WITH CUSTOMERS
Requirements:
a. Identify the performance obligations in the contracts.
b. How should the entity recognize revenue from the contract? (State also the timing of revenue recognition for each identified performance obligation.)
1. In 20x1, Electrified Construction Co. enters into a contract to construct a building for a customer. Electrified identifies its performance obligation to be satisfied over time. Electrified measures its progress on the contract based on costs incurred. The contract price is P20M. Electrified has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows:
20x1 20x2 20x3
a. contract cost incurred per yr. 8,160,000 7,320,000 1,920,000
b. billings per year 10,000,000 7,000,000 3,000,000
c. collections on billings per year 9,500,000 6,650,000 3,850,000
d. estimated costs to complete 8,840,000 1,720,000
(at each yr. end)
a. Compute for the gross profits, revenues and costs of construction in 20x1, 20x2 and 20x3, respectively.
b. Provide the journal entries under (i) traditional accounting and (ii) PFRS…
In 20x1, Electrified Construction Co. enters into a contract to construct a building for a customer. Electrified indentifies its performance obligation to be satisfied over time. Electrified measures its progress on the contrat based on costs incurred. The contract price is P20M. Electrified has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows:
20x1 20x2 20x3
a. Contract costs incurred per yr. 8,160,000 7,320,000 1,920,000
b. Billings per year 10,000,000 7,000,000 3,000,000
c. Collections on billings per year 9,500,000 6,650,000 3,850,000
Requirements:
a. Compute for the gross profits, revenues, and costs of construction in 20x1, 20x2 and 20x3, respectively.
b. Provide the journal entries under (i) traditional accounting…
Chapter 17 Solutions
Cengagenowv2, 1 Term Printed Access Card For Wahlen/jones/pagach’s Intermediate Accounting: Reporting And Analysis, 2017 Update, 2nd
Ch. 17 - Prob. 1GICh. 17 - Prob. 2GICh. 17 - When a company recognizes revenue during a period,...Ch. 17 - Prob. 4GICh. 17 - Prob. 5GICh. 17 - What is the proper accounting for a wholly...Ch. 17 - If a seller enters into more than one contract...Ch. 17 - Prob. 8GICh. 17 - Prob. 9GICh. 17 - Prob. 10GI
Ch. 17 - Prob. 11GICh. 17 - Prob. 12GICh. 17 - Prob. 13GICh. 17 - Prob. 14GICh. 17 - Prob. 15GICh. 17 - Prob. 16GICh. 17 - If the standalone selling price of a good or...Ch. 17 - Prob. 18GICh. 17 - Prob. 19GICh. 17 - If the sellers performance creates on asset (e.g.,...Ch. 17 - Describe input and output methods used to measure...Ch. 17 - Prob. 22GICh. 17 - Prob. 23GICh. 17 - Prob. 24GICh. 17 - Prob. 25GICh. 17 - A company should recognize revenue when a. the...Ch. 17 - A contract between one or more parties creates: a....Ch. 17 - Morgan Company and its customer agree to modify...Ch. 17 - Chlorine Corp. has a contract to deliver pool...Ch. 17 - Prob. 5MCCh. 17 - Prob. 6MCCh. 17 - In accounting for a long-term construction...Ch. 17 - Prob. 8MCCh. 17 - Prob. 9MCCh. 17 - Prob. 10MCCh. 17 - CustomTee Inc. contracts with various customers to...Ch. 17 - Yankee Corp. agrees to provide Albany Company 24...Ch. 17 - Prob. 3RECh. 17 - Prob. 4RECh. 17 - Prob. 5RECh. 17 - Prob. 6RECh. 17 - VolleyElite runs a volleyball program consisting...Ch. 17 - Enterprise Solutions Inc. licenses its...Ch. 17 - Prob. 9RECh. 17 - Magical Memories sells Florida theme park vacation...Ch. 17 - Prob. 11RECh. 17 - Robotics Inc. contracts with a customer to build a...Ch. 17 - CoolShoes sells its elite tennis shoes to sports...Ch. 17 - Using the information in RE17-13, what journal...Ch. 17 - GameDay sells recreational vehicles along with...Ch. 17 - Prob. 16RECh. 17 - Using the information provided in RE17-16, prepare...Ch. 17 - Prob. 18RECh. 17 - Prob. 19RECh. 17 - Prob. 1ECh. 17 - Prob. 2ECh. 17 - Prob. 3ECh. 17 - Prob. 4ECh. 17 - Prob. 5ECh. 17 - Assume the same facts as in E17-5. On July 1,...Ch. 17 - Prob. 7ECh. 17 - Prob. 8ECh. 17 - Prob. 9ECh. 17 - Prob. 10ECh. 17 - Prob. 11ECh. 17 - Jonas Consulting enters into a contract to provide...Ch. 17 - Prob. 13ECh. 17 - Prob. 14ECh. 17 - Prob. 15ECh. 17 - Prob. 16ECh. 17 - Prob. 17ECh. 17 - Prob. 18ECh. 17 - Prob. 19ECh. 17 - Prob. 20ECh. 17 - Crazy Computer Store sells a back-to-school bundle...Ch. 17 - Each of the following is an independent situation...Ch. 17 - Prob. 23ECh. 17 - Prob. 24ECh. 17 - Prob. 25ECh. 17 - Prob. 26ECh. 17 - Prob. 1PCh. 17 - Prob. 2PCh. 17 - Prob. 3PCh. 17 - Prob. 4PCh. 17 - Prob. 5PCh. 17 - Prob. 6PCh. 17 - Prob. 7PCh. 17 - SoccerHawk Merchandise Inc. enters into a 6-month...Ch. 17 - Prob. 9PCh. 17 - Prob. 10PCh. 17 - Prob. 11PCh. 17 - Prior to ASU 2014-09 changing the principles...Ch. 17 - The first step in the revenue recognition process...Ch. 17 - Prob. 3CCh. 17 - One of the more difficult issues that companies...Ch. 17 - Prob. 5CCh. 17 - Prob. 6CCh. 17 - Prob. 7CCh. 17 - Prob. 8CCh. 17 - Revenue for a company is recognized for accounting...Ch. 17 - Prob. 10C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- In 20x1, ABC Co. enters into a contract to construct a building for a customer. ABC identifies its performance obligation to be satisfied over time. ABC measures its progress on the contract based on costs incurred. The contract price is P20,000,000. ABC has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows: 20x1 20x2 20x3 Contract costs incurred per year Billings per year Collections on billings per year 1,920,000 3,000,000 5,650,000 3,850,000 8,160,000 7,320,000 10,000,000 500,000 6600,000 Estimated costs to complete (at each year-end) from the Student Ha8,840,000 1,720,000 ons, quizzes rection with any academic work, abetting of the same: 1st violation How much profit is recognized on the contract in 20x3?arrow_forwardIn 20x1, ABC Co. enters into a contract to construct a building for a customer. ABC identifies its performance obligation to be satisfied over time. ABC measures its progress on the contract based on costs incurred. The contract price is P20,000,000. ABC has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows: 20x1 20x2 20x3 Contract costs incurred per year Billings per year Collections on billings per year Estimated costs to 8,160,000 7,320,000 1,920,000 10,000,000 7,000,000 3,000,000 9,500,000 6,650,000 3,850,000 complete (at each year-end) 8,840,000 1,720,000 How much profit is recognized on the contract in 20x3?arrow_forward1. Determine the amount of construction in progress that will be reported. 2. How much revenue is recognized as of the end of the first year?arrow_forward
- In 20x1, Devin Co. enters into a contract to construct a building for a customer. Devin Co. identifies its peromance obligation to be satisfied over time. Devin CO. measures its progress on the contract based on ccosts incurred. The contract price is P10M. Devin has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is provided below: 20x1 20x2 20x3 a. Contract costs incurred to date 3,150,000 5,680,000 7,120,000 b. Biliings per year 4,000,000 5,000,000 1,000,000 c. Collections on billings per year 3,600,000 4,500,000 1,900,000 Requirements: a. Compute for the gross profits, revenues and costs of construction in 20x1, 20x2, 20x3, respectively. b. Provide the journal entries under (i) traditional accounting and (ii) PFRS 15. c.…arrow_forwardIn 20x1, Devin Co. enters into a contract to construct a building for a customer. Devin Co. identifies its peromance obligation to be satisfied over time. Devin CO. measures its progress on the contract based on ccosts incurred. The contract price is P10M. Devin has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is provided below: 20x1 20x2 20x3 a. Contract costs incurred to date 3,150,000 5,680,000 7,120,000 b. Biliings per year 4,000,000 5,000,000 1,000,000 c. Collections on billings per year 3,600,000 4,500,000 1,900,000 d. Estimated Costs to complete 3,850,000 1,420,000 Requirements: a. Compute for the gross profits, revenues and costs of construction in 20x1, 20x2, 20x3, respectively. b. Provide the journal…arrow_forwardIn 20x1, ABC Co. enters into a contract to construct a building for a customer. ABC identifies its performance obligation to be satisfied over time. ABC measures its progress on the contract based on costs incurred. The contract price is P20,000,000. ABC has an unconditional right to all billings made in accordance with the billing schedule stated in the contract. Information on the construction is as follows: 20x1 20x2 Contract costs incurred per year Billings per year Collections on billings 20x3 8,160,000 7,320,000 1,920,000 10,000,000 7,000,000 3,000,000 9,500,000 6,650,000 3,850,000 per year Estimated costs to 1911 complete (at each year-end)er from the Student Ha8,840,000 of 1,720,000 "Cheating during examinations, quizzes or plagiarism in connection with any academic work, abetting of the same: 1st violation- How much profit is recognized on the contract in 20x3? suspension with invalidation of grade; 3rd violation- suspensionarrow_forward
- A company is accounting for a long-term construction contract where revenue is recognized over time. The project is built to the customer's specifications, and the customer can make changes as construction is ongoing. It is a 3-year, fixed-fee contract that is presently in its first year. The latest reasonable estimates of total contract costs indicate that the contract will be completed at a profit. The company will submit progress billings to the customer and has reasonable assurance that collections on these billings will be received in each year of the contract. The contract can be canceled at any time by the customer who will retain control of any work done to date. Discuss the following: a. When should revenue from contracts be accounted for overtime versus at a point in time? b. How would the income recognized in each year of this long-term construction contract be determined using the cost-to-cost basis of determining progress toward satisfaction of the performance…arrow_forwardKindly answer this thank youarrow_forwardWidjaja Company is accounting for a long-term construction contract using the percentage-of-completion method. It is a 4-year contract that is currently in its second year. The latest estimates of total contract costs indicate that the contract will be completed at a profit to Widjaja Company. Instructions a. What theoretical justification is there for Widjaja Company's use of the percentage-of-completion method? b. How would progress billings be accounted for? Include in your discussion the classification of progress billings in Widjaja Company financial statements. c. How would the income recognized in the second year of the 4-year contract be determined using the cost-to-cost method of determining percentage of completion? d. What would be the effect on earnings per share in the second year of the 4-year contract of using the percentage-of-completion method instead of the completed-contract method? Discuss.arrow_forward
- Nance Network Consultants, Incorporated uses the percentage-of-completion method to account for its long-term contracts. It uses the cost-to-cost approach to measure progress. During the current year, Nance signed a contract to develop a computer network for an international accounting firm. Information related to the contract follows. Prepare the t-accounts for construction in progress, billings on construction in progress, and accounts receivable. Determine the net asset (liability) for each year of the contract on December 31.arrow_forwardOn July 1, 20x1, ABC Construction Co. enters into contract with a customers for the construction of a building. The contract prices is P6M, which is to be billed to the customers periodically based on ABC's progress on the construction . The estimated total contract cost is P4M. The actual costs incurred in 20x1 amounts to P1.2M. 1. The revenue to be recognized in 20x1arrow_forwardTo answer, please refer to the picture. Question: How much must be shown as current asset (cost of uncompleted contract in excess of billings) in the balance sheet of SM Development as of December 31, 2018?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage LearningIndividual Income TaxesAccountingISBN:9780357109731Author:HoffmanPublisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Individual Income Taxes
Accounting
ISBN:9780357109731
Author:Hoffman
Publisher:CENGAGE LEARNING - CONSIGNMENT