To determine: The number of Kanbans
Concept introduction:
The Japanese word for card is termed as Kanban and has critical application in the “Just in Time” concept. The JIT philosophy was developed to reduce the inventory holding costs at various levels of the production chain. The materials are supplied to the process area just when they are needed in a particular operation. Supplying the materials before they are actually needed, adds to inventory carrying costs. It also may result in more space being occupied, additional handling, spoilage, obsolescence and so on.
The Kanban system relies on visual or simple signals to indicate to production systems that the product is needed.
Want to see the full answer?
Check out a sample textbook solutionChapter 16 Solutions
Pearson eText Principles of Operations Management: Sustainability and Supply Chain Management -- Instant Access (Pearson+)
- Maggie Moylan Motorcycle Corp. uses kanbans tosupport its transmission assembly line. Determine the size of thekanban for the mainshaft assembly and the number of kanbansneeded. Setup cost = $20Annual holding costof mainshaft assembly = $250 per unitDaily production = 300 mainshaftsAnnual usage = 20,000 (= 50 weeks * 5 days each* daily usage of 80 mainshafts)Lead time = 3 daysSafety stock = 1 2 day>s production of mainshaftsarrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $100 per subassembly 30 subassemblies 3,000 (50 weeks x5 days each daily usage of 12 subassemblies) 16 days 3 days' production Kanban container size = 24 units (round your response to the nearest whole number).arrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $125 per subassembly 20 subassemblies 3,000 (50 weeks x5 days each x daily usage of 12 subassemblies) 12 days 3 days' production Kanban container size = units (round your response to the nearest whole number).arrow_forward
- Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $16 Annual holding cost subassembly $250 per subassembly 600 subassemblies Daily production Annual usage 62,500 (-50 weeks x5 days each x daily usage of 250 subassemblies) Lead time Safety stock The kanban size is (round your response to the nearest whole number). 2 days 1 day's production of subassembliesarrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $110 per subassembly 40 subassemblies 4,000 (50 weeks × 5 days each daily usage of 16 subassemblies) 12 days 3 days' production Kanban container size = ☐ units (round your response to the nearest whole number).arrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $100 per subassembly 20 subassemblies 2,500 (50 weeks x 5 days each x daily usage of 10 subassemblies) 12 days 3 days' production Kanban container size = 55 units (round your response to the nearest whole number).arrow_forward
- Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage Lead time Safety stock $30 $120 per subassembly 30 subassemblies 3,000 (50 weeks × 5 days each × daily usage of 12 subassemblies) 12 days 2 days' production Kanban container size = ☐ units (round your response to the nearest whole number).arrow_forwardIE Carol Cagle has a repetitive manufacturing plant producing trailer hitchos in Arlington, Texas. The plant has an average inventory tumover of only 12 times per year. He has therefore determined that he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip $25 per hour $13 per unit Setup labor cost Annual holding cost Daily production Annual demand Desired lot size 992 units/8 hour day 33.000 (275 days each daily demand of 120 units) 124 units (one hour of production) To obtain the desired lot size, the set-up time that should be achievedminutes pound your response to two decimal places)arrow_forwardPauline Found Manufacturing, Inc., is moving tokanbans to support its telephone switching-board assemblylines. Determine the size of the kanban for subassemblies and thenumber of kanbans needed.Setup cost = $30 Annual holding cost = $120 per subassemblyDaily production = 20 subassembliesAnnual usage = 2,500 (50 weeks * 5 days each* daily usage of 10 subassemblies)Lead time = 16 daysSafety stock = 4 days> production of subassembliesarrow_forward
- Pauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $125 per subassembly Daily production 30 subassemblies Annual usage 3,000 (50 weeks×5 days each×daily usage of 12 subassemblies) Lead time 12 days Safety stock 4 days' production Part 2 Kanban container size = enter your response here units (round your response to the nearest whole number).arrow_forwardKanban container size = Number of kanbans needed=arrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $30 Annual holding cost $120 per subassembly Daily production 25 subassemblies Annual usage 4,500 (50 weeks × 5 days each x daily usage of 18 subassemblies) 12 days Lead time Safety stock 4 days' production Kanban container size = units (round your response to the nearest whole number).arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.