A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. Given the information shown, do the following:
a. Determine the processing sequence using (1) FCFS, (2) SPT, (3) EDD, and (4) CR. For each sequence, compute the average job tardiness, the average flow time, and the average number of jobs at the work center. The list is in FCFS order.
b. Using the results of your calculations in part a, show that the ratio of average flow time and the average number of jobs measures are equivalent for all four sequencing rules.
c. Determine the processing sequence that would result using the S/O rule.
a)
1)

To determine: The processing sequence based on First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e-f.
Determine average flow time, average tardiness, and average number of jobs for FCFS:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
b | 6 | 10.5 | 17 | 0 |
c | 5.2 | 15.7 | 12 | 3.7 |
d | 1.6 | 17.3 | 27 | 0 |
e | 2.8 | 20.1 | 18 | 2.1 |
f | 3.3 | 23.4 | 19 | 4.4 |
Total | 23.4 | 91.5 | 10.2 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job b:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 3.7.
Note: The procedure continues for all the jobs.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.25 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 1.7 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 3.9 jobs.
1)

To determine: The processing sequence based on First Come First Served (FCFS).
Introduction: First Come First Served is the scheduling rule, which helps to arrange the sequence in the order. Here, the first come would be served first.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using FCFS:
According to FCFS, the first come would be served first. Hence, the jobs should be sequenced in the order as per its arrival.
Hence, the sequence of jobs using FCFS is a-b-c-d-e-f.
Determine average flow time, average tardiness, and average number of jobs for FCFS:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
b | 6 | 10.5 | 17 | 0 |
c | 5.2 | 15.7 | 12 | 3.7 |
d | 1.6 | 17.3 | 27 | 0 |
e | 2.8 | 20.1 | 18 | 2.1 |
f | 3.3 | 23.4 | 19 | 4.4 |
Total | 23.4 | 91.5 | 10.2 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job b:
Flowtime is less than the due date. Hence, there would be tardiness.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 3.7.
Note: The procedure continues for all the jobs.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.25 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 1.7 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 3.9 jobs.
2)

To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using SPT:
According to SPT, the job that has the shortest processing would be served first and it goes on as the processing time increase. Duration should be assembled in the ascending order
Hence, the sequence of jobs using SPT is d-e-f-a-c-b.
Determine average flow time, average tardiness, and average number of jobs for SPT:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
d | 1.6 | 1.6 | 27 | |
e | 2.8 | 4.4 | 18 | |
f | 3.3 | 7.7 | 19 | |
a | 4.5 | 12.2 | 10 | 2.2 |
c | 5.2 | 17.4 | 12 | 5.4 |
b | 6 | 23.4 | 17 | 6.4 |
Total | 23.4 | 66.7 | 14 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job d, Job e, and Job f:
Flow time of Job d, Job e, and Job f is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job a:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job a is 2.2.
Tardiness of Job c:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job c is 5.4.
Tardiness of Job b:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job b is 6.4.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 11.12 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 2.33 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 2.85 jobs.
3)

To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, job with the earliest due date would be served first. Then, the process would be going on from earliest due date to latest due date.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using EDD:
According to EDD, the job that has the earliest due date would be served first and it goes on as the due date increases. The job should be arranged based on due date. Due date should be assembled in the ascending order
Hence, the sequence of jobs using EDD is a-c-b-e-f-d.
Determine average flow time, average tardiness, and average number of jobs for EDD:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
c | 5.2 | 9.7 | 12 | 0 |
b | 6 | 15.7 | 17 | 0 |
e | 2.8 | 18.5 | 18 | 0.5 |
f | 3.3 | 21.8 | 19 | 2.8 |
d | 1.6 | 23.4 | 27 | 0 |
Total | 23.4 | 93.6 | 3.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job c, Job b, and Job d:
Flow time of Job a, Job c, Job b, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 2.8.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.6 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.55 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 4 jobs.
4)

To determine: Sequence of jobs based on decision rule critical ratio.
Introduction: Critical ratio is kind of scheduling rule that helps to identify that, the task or job is on the correct track. It would help to identify if the task is behind or ahead of the schedule.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine the sequence using critical ratio:
Initial critical ratio should be determined at day 0:
Job | Processing time (days) | Due date (days) | Critical ratio |
a | 4.5 | 10 | 2.22 |
b | 6 | 17 | 2.83 |
c | 5.2 | 12 | 2.31 |
d | 1.6 | 27 | 16.88 |
e | 2.8 | 18 | 6.43 |
f | 3.3 | 19 | 5.76 |
Critical ratio for Job a:
It is can be determined by dividing the value attained by subtracting the completion day of previous job from the due date of current job with the processing time.
Note: Process continues for all the jobs.
Job a has the lowest critical ratio. Thus, it will be completed first. Hence, Job a would be completed first in the sequence of jobs.
Determine the critical ratio after the completion of Job a:
As the processing time of job a is 4.5 days, completion day of completed day would be 4.5.
Job | Processing time (days) | Due date (days) | Critical ratio |
a | |||
b | 6 | 17 | 2.08 |
c | 5.2 | 12 | 1.44 |
d | 1.6 | 27 | 14.06 |
e | 2.8 | 18 | 4.82 |
f | 3.3 | 19 | 4.39 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Note: Process continues for all the jobs.
Job c has the lowest critical ratio. Hence, Job c would be completed next in the sequence of jobs.
Determine the critical ratio after the completion of Job a and Job c:
As the processing time of job a is 4.5 days and Job c is 5.2, completion day of completed day would be 9.7 (4.5+5.2).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | 6 | 17 | 1.22 |
c | |||
d | 1.6 | 27 | 10.81 |
e | 2.8 | 18 | 2.96 |
f | 3.3 | 19 | 2.82 |
Critical ratio for Job b:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job b has the lowest critical ratio. Hence, Job b would be completed next in the sequence of jobs after Job a and Job c.
Determine the critical ratio after the completion of Job a, Job c and Job b:
As the processing time of job a is 4.5 days, Job b is 6.0, and Job c is 5.2 days. Completion day of completed day would be 15.7 (4.5+5.2+6).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | |||
c | |||
d | 1.6 | 27 | 7.06 |
e | 2.8 | 18 | 0.82 |
f | 3.3 | 19 | 1 |
Critical ratio for Job d:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job e has the lowest critical ratio. Hence, Job e would be completed next in the sequence of jobs after Job a, Job c, and Job b.
Determine the critical ratio after the completion of Job a, Job c, Job b, and job e:
As the processing time of job a is 4.5 days, Job b is 6.0, Job c is 5.2 days, and job e is 2.8. Completion day of completed day would be 18.5 (4.5+5.2+6+2.8).
Job | Processing time (days) | Due date (days) | Ratio |
a | |||
b | |||
c | |||
d | 1.6 | 27 | 5.31 |
e | |||
f | 3.3 | 19 | 0.15 |
Critical ratio for Job d:
It is can be determined by dividing the value attained by subtracting the completion day of completed job from the due date of current job with the processing time.
Job f has the lowest critical ratio. Hence, Job f would be completed next in the sequence of jobs after Job a, Job c, Job b, and Job e.
As Job d is the remaining job, it will be completed next.
Hence, the sequence of jobs using critical ratio is a-c-b-e-f-d.
Determine average flow time, average tardiness, and average number of jobs for critical ratio:
Job | Processing time (days) | Flow time (days) | Due date (days) | Tardiness |
a | 4.5 | 4.5 | 10 | 0 |
c | 5.2 | 9.7 | 12 | 0 |
b | 6 | 15.7 | 17 | 0 |
e | 2.8 | 18.5 | 18 | 0.5 |
f | 3.3 | 21.8 | 19 | 2.8 |
d | 1.6 | 23.4 | 27 | 0 |
Total | 23.4 | 93.6 | 3.3 |
Supporting calculation:
Processing time and due date are given for each job. Flow time is the cumulative of the processing time.
Tardiness of Job a, Job c, Job b, and Job d:
Flow time of Job a, Job c, Job b, and Job d is less than its respective due date. Hence, there would be no tardiness.
Tardiness of Job e:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job e is 0.5.
Tardiness of Job f:
It is calculated by subtracting the flow time of the job from the due date of the project. Hence, the lateness of Job f is 2.8.
Average flow time:
It is calculated by dividing the total flow time and number of jobs.
Hence, average flow time is 15.6 days.
Average tardiness:
It is calculated by dividing the total tardiness and number of jobs.
Hence, average tardiness is 0.55 days.
Average number of jobs:
It can be determined by dividing the total flow time and total processing time.
Hence, average number of jobs is 4 jobs.
b)

To determine: Whether the average flow time and average number of jobs are equivalent for four sequencing rules.
Introduction: Sequencing is the process of arranging the jobs in certain order in which it should be performed.
Answer to Problem 15P
Explanation of Solution
Given information:
Job | Processing time (days) | Due date (days) | Remaining number of operations |
a | 4.5 | 10 | 3 |
b | 6 | 17 | 4 |
c | 5.2 | 12 | 3 |
d | 1.6 | 27 | 5 |
e | 2.8 | 18 | 3 |
f | 3.3 | 19 | 1 |
Determine whether the average flow time and average number of jobs are equivalent for four sequencing rules:
Rule | Average flow time | Average number of jobs | Ratio |
FCFS | 15.25 | 3.91 | 3.9 |
SPT | 11.12 | 2.85 | 3.9 |
EDD | 15.6 | 4 | 3.9 |
CR | 15.6 | 4 | 3.9 |
Calculate ratio for FCFS:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for SPT:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for EDD:
It is calculated by dividing average flow time and average number of jobs.
Calculate ratio for CR:
It is calculated by dividing average flow time and average number of jobs.
c)

To determine: The processing sequence of the jobs using Slack per Operation (S/O) rule
Introduction: Slack per operation is a scheduling method that helps to determine the sequence of the operation. Slack is the difference between the due date and the required time to process certain job.
Answer to Problem 15P
Explanation of Solution
Given information:
The following information is given:
Job | Processing time (days) | Due date | Remaining number of operations |
a | 5 | 8 | 2 |
b | 6 | 5 | 4 |
c | 9 | 10 | 4 |
d | 7 | 12 | 3 |
e | 8 | 10 | 2 |
Determine the processing sequence of the jobs using Slack per Operation:
Job | Job time (days) | Due date (days) | Operations remaining | Slack | Slack per operation (S/O) | Rank |
a | 4.5 | 10 | 3 | 5.5 | 1.83 | 1 |
b | 6 | 17 | 4 | 11 | 2.75 | 3 |
c | 5.2 | 12 | 3 | 6.8 | 2.27 | 2 |
d | 1.6 | 27 | 5 | 25.4 | 5.08 | 5 |
e | 2.8 | 18 | 3 | 15.2 | 5.07 | 4 |
f | 3.3 | 19 | 1 | 15.7 | 15.7 | 6 |
Supporting calculation:
Processing time, due date, and remaining number of operation is given. Rank should be assigned according to the slack per operation.
Calculate slack:
It can be calculated by subtracting the processing time from the due date.
Note: The process continues for all the jobs:
Calculate slack per operation:
It can be calculated by dividing the slack value and the remaining number of operations.
Note: The process continues for all the jobs:
Hence, the sequence of jobs using S/O is a-c-b-e-d-f.
Want to see more full solutions like this?
Chapter 16 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT
- Do you feel there is anything positive about rework?arrow_forwardDo you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forward
- Have you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forwardResearch a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forward
- Do you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forwardGiven the significant impact on finances, production timelines, and even equipment functionality, as you pointed out, what do you believe is the most effective single strategy a company can implement to significantly reduce the occurrence of rework within their operations?arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forward
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardDurban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and photographs of the bread.Mkumla said she was later contacted by a man from Sasko who apologised for the incident.According to…arrow_forwardRead the project statement and answer ALL of the questions that follow PROJECT STATEMENT The African Integrated High-Speed Railway Network (AIHSRN). African nations are preparing to invest billions in a significant overhaul of their rail infrastructure as part of an ambitious plan for the continent. One of the key projects underway is the African Integrated High-Speed Railway Network (AIHSRN), which aims to connect Africa's capital cities and major commercial centres with a high-speed railway network to enhance continental trade and competition. This network will span 2,000 km (1,243 miles) and connect 60 cities, including Nairobi, Lagos, Cairo, and Dakar. It will improve access to essential markets, enhance economic cooperation, and encourage regional collaboration. The plan is poised to revolutionise intra-African trade by reducing travel times and lowering transportation costs, making trade between African nations more competitive. The trains will be capable of reaching speeds of up…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Understanding Management (MindTap Course List)ManagementISBN:9781305502215Author:Richard L. Daft, Dorothy MarcicPublisher:Cengage Learning