Question
Book Icon
Chapter 15, Problem 29P
To determine

(a)

The projects that should be approved.

Expert Solution
Check Mark

Answer to Problem 29P

The projects B, C, D, E, H, and J should be approved.

Explanation of Solution

Given:

Salvage Value is 0.

Duration is 5 years.

Calculation:

Write the expression to calculate the present worth.

PW=P+A(1+i)n1(1+i)n×i ...... (I)

Substitute 14% for i and 5 for n in Equation (I)

PW=P+A(1+0.14)51(1+0.14)5×0.14=P+A(3.433) ...... (II)

Find the table to calculate the present worth.

Project PV(thousand)(COST) Uniform annual benefits Rate of return PW PW/COST
A $10 $2.98 15% $0.01 0.001
B $15 $5.58 25% $0.006 0.0004
C $5 $1.53 16% $0.0096 0.00192
D $20 $5.55 12% $.0065 0.000325
E $15 $4.37 14% $0.0026 0.000173
F $30 $9.81 19% $0.0046 0.000153
G $25 $7.81 17% $0.013 $0.00052
H $10 $3.49 22% $5.86 $0.586
I $5 $1.67 20% $0.0056 0.00112
J $10 $3.20 18% $0.00694 $0.000694

Here, the present worth has been calculated using Equation (I).

Conclusion:

Therefore, the projects B, C, D, E, H, and J should be approved.

To determine

(b)

The ranking order of all the acceptable projects.

Expert Solution
Check Mark

Answer to Problem 29P

The ranking has been shown below.

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

Explanation of Solution

Calculation:

Rank the project according to the PW/COST

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

Conclusion:

Rank the project according to the PW/COST

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10
To determine

(c)

The projects to be approve if only $70000 is available.

Expert Solution
Check Mark

Answer to Problem 29P

The project to be approve if only $70000 available are H, C, J, B, D, and A.

Explanation of Solution

Calculation:

Project PW/COST Ranking
H $0.586 1
C 0.00192 2
J $0.000694 3
B 0.0004 4
D 0.000325 5
E 0.000173 6
F 0.000153 7
G $0.00052 8
A 0.001 9
I 0.00112 10

If the project budget is $70000 then the project with best return should be selected.

The project to be approve if only $70000 available are H, C, J, B, D, and A.

Sum=$10000+$5000+$10000+$15000+$20000+$10000=$70000

Hence, the chosen project is correct.

Conclusion:

Therefore, the project to be approve if only $70000 available are H, C, J, B, D, and A.

To determine

(d)

If the result will be the same if the projects are ranked on IRR and calculate the opportunity cost of capital.

Expert Solution
Check Mark

Answer to Problem 29P

No, there will be change in the rank of the project if they are ranked on IRR.

The opportunity cost of capital is 20%.

Explanation of Solution

Make the table to calculate the present worth.

Project PV(thousand)(COST) Uniform annual benefits Rate of return PW PW/COST
A $10 $2.98 15% $0.01 0.001
B $15 $5.58 25% $0.006 0.0004
C $5 $1.53 16% $0.0096 0.00192
D $20 $5.55 12% $.0065 0.000325
E $15 $4.37 14% $0.0026 0.000173
F $30 $9.81 19% $0.0046 0.000153
G $25 $7.81 17% $0.013 $0.00052
H $10 $3.49 22% $5.86 $0.586
I $5 $1.67 20% $0.0056 0.00112
J $10 $3.20 18% $0.00694 $0.000694

Here, the present worth has been calculated using Equation (I).

The project with highest PW is project H and the opportunity cost will be equal to its rate of return that is 22%.

Conclusion: No, there will be change in the rank of the project if they are ranked on IRR.

The opportunity cost of capital is 20%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
• 3 different people working at any companies under the BPO industry in the Philippines. • What are the 3 different Vision, Mission, Duties and Responsibilities and Career Path of these people in their companies under the BPO industry?
Module 6 ⚫(1902) Buckner C X | (1902) How to d x (1902) Buckner F X (1902) Productic X WP Videoplayer Canvas Login | Ir x | + Σ R mybrcc.instructure.com/courses/417310/discussion_topics/3420114?module_item_id=20155705 Spring 2025 Home Announcements Modules Syllabus Grades 8 People BRCC-_Library DLASC Module 6 Discussion - Business Costs Relaunch to update For this discussion, think about where you work or a business you have a significant amount of knowledge about. What is a common product that the business sells? What are the main costs the business has to incur in order to be able to sell that product? Which of these costs are fixed and which are variable? How much additional costs would be incurred if it were to sell one additional unit of that product (marginal cost)? Write a discussion thread about this business, the product it commonly sells, and your answers to the above questions. Also, respond to at least two threads created by your classmates. In these responses, share what…
Refer to the video to answer the following:  • what are all the key policies or all the strategies the Philippine government should prioritize to accelerate sustainable economic growth?  • these should consider the Philippines current economic challenges, including inflation, unemployment, and the need for digital transformation.   "The Philippines' Strong Economic Growth"  (YouTube link: https://youtu.be/1YtEoGp2ZeM?siJQfIv5kbu0txVsLL.)
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education